BAM Nuttall docked £10m from bus job in Cambridge

Grant Prior 14 years ago
Share

BAM Nuttall has been docked £10m for being two years late completing construction of  its £87m Cambridgeshire Guided Busway contract.

Cambridgeshire County Council confirmed it has been deducting almost £14,000 a day in late delivery damages from BAM Nuttall since February 2009.

The dispute is understood to essentially boil down to whether extra works needed on the tram project are variations to the contract or defects.

A council cabinet meeting last week heard senior councillors describe BAM Nuttall’s latest delays as “unnecessary”.

The contractor has told council bosses all their major work is now complete.

But the council claims Nuttall has left the submission of construction and design certificates until the last minute.

Both design and construction certificates are essential for the council to be confident that the scheme has been built correctly.

The Project Manager, who is independent of both the Council and Nuttall, cannot certify the contract as complete until the most important certificates for the main structures have been received and are satisfactory.

Nuttall has been accused by the council of not yet submitting five construction and design certificates. A further 47 construction certificates, that had been previously been rejected also need to be resubmitted, and accepted, before the contract can be certified as complete.

Once Nuttall complete the Busway contract they will have 28 days to fix all notified defects on the route.

The council is lining up a new contractor to fix the defects if Nuttall misses the deadline. The costs of the work will be deducted from Nuttall.

Roy Pegram, Cabinet member for Growth, Infrastructure and Strategic Planning, said: “The Busway is not any longer, any wider or any higher than when the contract was awarded so it is clearly unacceptable that BAM Nuttall have taken two years longer than they should to build the route.

“Residents and everyone at the council would have rightly expected to see buses running a long while ago, but the contractor’s delays have directly resulted in £10m in damages being stripped from the firm.

“Although the timescale for BAM Nuttall completing the contract is in their hands, I would like to reassure people that the Council has plans in place to get the route open as soon as possible once they finally achieve that. Clearly correcting the defective work is part of this process, which will take a number of weeks.”

Council claim problems with the contract include:

Maintenance track – some areas of the track have been built at too low level which means rain water has collected and the maintenance track is flooded. These areas of the track need to be raised without affecting the flood balance in the area.

Beam expansion gaps – The County Council requires the contractor to show that the gaps between the beams will allow for expansion of the beams during periods of hot weather while giving a smooth ride for passengers.

Foundations – The County Council requires the contractor to show that the use of shallow pad foundations on some short sections of track where deeper piled foundations were originally planned is appropriate. The County Council need calculations to show the track will not move over time reducing the ride quality.

St Ives Park & Ride car park – the car park has been built with less than the specified gradient and water is ponding on the surface of the car park.

River Great Ouse Viaduct – rain water is leaking through an unsealed expansion joint onto the steel below. If this was not fixed now council taxpayers would pick up future bills for additional maintenance costs.

Latest news

Staff stunned as engineering consultancy Clarkebond closes

Firm was only bought three months ago by rival Independent Design House Group
2 days ago

Vistry issues third profit warning in three months

Profit expected to fall £50m below forecast due to delayed completions
2 days ago

Miller Homes buys St Modwen Homes for £215m

Scottish house builder snaps up £368m turnover rival
5 days ago

Keltbray fine increased to £18m after failed bid rigging appeal

Contractor loses penalty discount for settling with competition authorities
5 days ago

Luxury house builder goes under with 70 job losses

Octagon Developments in administration after 40 years in business
6 days ago

Top Ten best read stories of 2024

The biggest headlines of an eventful year. Have a good one and here's to a successful 2025
6 days ago

BAM Nuttall fined £800,000 after concrete skip tragedy

Young labourer killed by falling bale arm
7 days ago

Keltbray infrastructure business reveals new name

AUREOS means "new dawn" after private equity acquisition
6 days ago

Stiffer fines for over-running street works from next Summer

Cash raised from lane rentals to be channeled into pothole repairs
6 days ago

£113m Basildon rental homes scheme seals build finance

Work expected to start early next year on Market Square project
6 days ago

Notting Hill Genesis seeks more tier 1 repairs contractors

London housing trust seeks eight firms for new £1.5bn repairs framework
6 days ago

Reclaimed steel oil rig columns worked into London office revamp

Curo will use reclaimed bricks and steel for Fitzrovia office overhaul
7 days ago

CITB delays levy approval consultation

Levy agreement talks pushed back by ongoing review into effectiveness of training body
7 days ago

Ofwat approves £104bn water industry spending plan

Household water bills to rise by 36% to fund quadrupling of investment
1 week ago

Costain/ Siemens JV clinches HS2 power supply job

£300m deal for HV power supply systems over the 225km route
1 week ago

Demolition team assembles on Multiplex London Wall site

Erith to start work next month at Deutsche Bank's former headquarters
1 week ago

Norwich Council acts to revive £300m Anglia Square scheme

Council uses Homes England funding to buy stalled site with planning for 1,100 homes
1 week ago

Go-ahead for 4,500-home Cambridgeshire new town

Waterbeach new town plan stalled three years ago after an Environment Agency objection
1 week ago

Henry Boot to take total control of Stonebridge Homes

Deal worth at least £30m
1 week ago

HS2 costs could hit £66bn

Government looking for next estimate to be lower
1 week ago

Mace to close construction logistics arm

Specialist business being wound down
1 week ago

National Grid to invest £35bn over next five years

Plan set out for record investment in electricity transmission infrastructure
1 week ago

Profits double at Barhale

Civils specialist sees order book top £1bn
1 week ago

Balfour wins 68km HV underground power cable deal

Main works to start next year on Eastern Green Link 2 job
1 week ago

Stunning site wrap unveiled on Sloane Street

Hoarding creates illusion of fully formed façade on £53m Galliford Try job
1 week ago

Heathrow Airport upgrade spend takes off again

Airport operator will spend £2.3bn over the next two years
1 week ago

Government buys back over 36,000 military homes

Public ownership deal to release wave of upgrade and new build work
1 week ago

Story Contracting staff braced for rail job losses

Work coming through slower than expected from Network Rail
1 week ago

Ballymore submits two plans for 3,700 East London homes

Construction could start in 2025 on Thames Road and Knights Road schemes
1 week ago

Blackpool council steps in on failed developer’s £300m scheme

Blackpool Central site clearance to start in the New Year as hunt starts for new developer
1 week ago

Contractor services