Amec appeal refused over £94m costs on submarine job

Aaron Morby 12 years ago
Share

Amec’s legal battle to reduce the amount it must pay of a £93.6m cost overrun on a nuclear submarine jetty contract at Faslane has failed.

Now Amec and partners Morgan Sindall face a huge bill as they hammer out with the Ministry of Defence what proportion of cost overruns were properly incurred on the troubled project.

A costly legal battle has been running as both firms struggle to finish the Faslane SSN Berthing Project, first revealed in the Enquirer, more than four years late and at an expected final cost of £235.7m.

When the project was first awarded Amec was sole contractor for the jetty. But after Morgan Sindall acquired Amec’s construction arm for £26m back in 2007, the job became a 50:50 joint venture between the two firms.

Under the terms of the contract, the contractors are liable to pay the first £50m of overruns on the agreed maximum target price for the job, which has itself already risen from £89m to £142m.

This element was not challenged in the latest legal contest, but Amec held that the remaining £43.6m cost overrun should be split between client and contractor, with Amec due any costs howsoever incurred.

An arbitration panel rejected this saying the only costs payable were the actual costs reasonably and properly incurred within the contract.

A High Court judge has now refused Amec’s attempt to appeal this decision in a written ruling this week upholding the arbitration decision.

Latest news

Balfour Beatty terminates Danny Sullivan labour deals

Around 500 workers on HS2 will be moved to alternative agencies or be taken on direct
22 hours ago

Trio face prosecution after Hinkley site death

Main contractors and client to face charges over death of site supervisor
23 hours ago

Buyers see recovery in house building sector

But civil and commercial work still in the doldrums
1 day ago

Apprentice saws-off thumb on hotel refurb site

Court hears how digit was reattached and teenager continued training with another firm
1 day ago

Laing O’Rourke tops June contracts league

£919m animal super lab dominates new orders
2 days ago

TSL turnover smashes £500m as profit almost trebles

Data centre and logistics contractor rises high on surging demand
2 days ago

Gleeson Homes chief exec leaves business after restructure

Management revamp after "challenging" year
2 days ago

Green light for 1,600-home Oldham town centre overhaul

Plans for over 1,600 homes across six regeneration sites approved
2 days ago

DSM wins Norwich city centre clearance job

Anglia Square shopping centre clearance for £300m scheme
2 days ago

13-year-old becomes UK’s youngest qualified digger driver

Grandson of Gallagher Group chairman sets industry record
2 days ago

Cubby reborn in £12m Svella-backed takeover

£50m revenue target set as 14 firms combine under new Cubby Group banner
3 days ago

North East NHS trusts plot £3bn health estate overhaul

Market engagement begins for major construction push across four trusts
3 days ago

HG goes green on cranes in £1.2m switch to battery power

Diesel-free crane drive cuts fuel bills by 94%
3 days ago

Developer fined £165,000 for fire safety failings

Firm ignored fire safety orders on apartment job in Preston
3 days ago

Bidding to start for £1.8bn North West framework

Contractors invited to bid for latest Procure Partnerships deal
3 days ago

Hill hits record £90m profit as homes pipeline swells

Build-to-rent push and £4.8bn contracting book to fuel next growth phase
3 days ago

Rayner unveils £39bn plan to build 300,000 social homes

Council building revival and rent reform feature in social and affordable homes plan
4 days ago

Keltbray bounces back with £3.2m profit

Tighter controls and smarter project selection fuel strong turnaround
4 days ago

VINCI JV wins 500-home twin town centre revamps

Chester Northgate phase 2 and Northwich Weaver Square schemes move to delivery stage
4 days ago

80 energy projects unlocked as Ofgem backs grid expansion

£24bn energy networks deal gets green light from regulator
5 days ago

How to see your stories on the Enquirer

Join our Suppliers and Buyers directory to get your news published
4 days ago

Henley lands Midland Mill revamp on Leeds tower scheme

Restoration of 18th-century mill kicks off on South Bank regeneration project
4 days ago

New boss at Eric Wright Civil Engineering

Gavin Hulme takes top job as Diane Bourne moves to group role
4 days ago

Pinewood submits £1bn data centre plan

Studio giant adds green and learning spaces to tech hub blueprint
5 days ago

Record results after TClarke goes private

Britain's biggest M&E contractor flourishes after de-listing
5 days ago

Dalkia lands £200m nuclear maintenance deal

1,000 nuclear FM staff to join M&E contractor
5 days ago

Construction comeback to outpace wider economy

Arcadis forecast fueled by spending review optimism
6 days ago

First steel goes up on giant car battery site

Severfield gets to work on McAlpine Somerset site
5 days ago

Permasteelisa wins cladding deal on Bovis city tower

Facade specialist lands package at 60 Gracechurch Street
5 days ago

Fox buys recycled asphalt specialist Fisher

Acquisition adds major recycled asphalt capacity in north west
5 days ago