Roofer left paralysed in Wates site fall

Grant Prior 11 years ago
Share

Wates and its roofing subcontractor have been fined after a worker was left paralysed from the waist down when he fell four metres through a hole in a roof at a Swindon building site.

Giovanni Mastrodomenico, 56, from Swindon, fell through a waterproof membrane into the unguarded hole while working at the Marlborough Park development in the town on 31 August 2011.

His employer Tego Roofing Ltd, of Oxford, and principal contractor Wates Construction have been prosecuted following the incident.

Swindon Magistrates’ Court heard that Mastrodomenico was carrying out metalwork prior to the installation of a vent on the roof of the new apartment block. The hole he plunged through was where the vent was to be placed.

He fell four metres onto a concrete floor below, causing permanent injuries that have left him unable to walk and confined to a wheelchair.

An HSE investigation found that scaffolding under the hole inside the building had been removed because it was obstructing an emergency escape route, and that scaffolding planks had subsequently been placed over the hole instead.

But these planks were in turn removed to allow workmen to lay a waterproof membrane over the hole in preparation for the vent to be installed leaving nothing in place to prevent Mastrodomenico’s fall.

The court was told that the risk assessment and method statement for the work was unsuitable and insufficient because it failed to refer to the installation process for the vent.

There was confusion about who the site supervisor was when the incident happened and, although the site manager had seen the roofers working near the hole, he did not stop the work or ensure the scaffolding boards were replaced.

HSE established that Tego Roofing failed to provide adequate supervision or instruction to its employees while working on the roof.

Wates failed to plan, manage and monitor the work and did not ensure there was a risk assessment in place.

Tego Roofing Ltd, of Chalgrove, Oxford, was fined £10,000 and ordered to pay £9,460 in costs after pleading guilty to breaching CDM regulations.

Wates Construction of Leatherhead, Surrey, was fined £18,000 with costs of £11,127 after also pleading guilty to a separate breach of the same regulations.

Speaking after the hearing, HSE Inspector Keiron Jones, said: “Mr Mastrodomenico’s life and that of his family have been completely changed by the management failings on the site.

“Apart from the pain and suffering he has gone through, his employment opportunities are now restricted and he will never be able to walk again.

“Construction companies and their contractors must have proper plans in place to allow their employees to complete the job safely.

“As principal contractor, Wates failed to plan, manage and monitor the work, and ensure there was a risk assessment in place.

“Tego also failed in their duty to provide a risk assessment, ensure there was adequate supervision on-site and make sure there was a safe system of work for the installation of the vent.”

 

Latest news

Construction T Level scrapped due to lack of demand

Courses canned after less than 100 sign-up for latest round
3 hours ago

Bid rigging probe launched into school repair work

Firms raided this week with focus on roofing contracts
1 day ago

McLaren hires ex-ISG regional boss for north east expansion

Andrew Beaumont becomes MD of new Yorkshire and North East business
11 hours ago

Government commits to four new prisons in seven years

£2.3bn pledged for new prison build programme
1 day ago

Road and rail delays hit revenue at Van Elle

Turnover drops 5% as markets remain challenging for piling specialist
11 hours ago

Boot reports ‘noticeable improvement’ in planning system

Government planning reforms already unblocking council planning
11 hours ago

Go-ahead to revamp former London city hall

Project will straighten the building's leaning profile with terraces to every level
19 hours ago

United Living to divert Midlands gas pipeline

600m pipeline diversion clears way for M54 to M6 link road construction
10 hours ago

Credit insurance saves Billington from ISG hit

Steel specialist puts on extra shifts at its plants to cope with demand
1 day ago

M&E specialist Dodd doubles profit on retrofit surge

Family-owned Telford specialist delivers record revenue of nearly £250m
1 day ago

Go-ahead for 800-home Croydon dual towers

One Lansdowne Road build to rent scheme to cost £260m to build
1 day ago

Construction inflation set to return raising tender prices

End of 2024 to mark the bottom of present inflationary trough
1 day ago

Start date for vast Balfour and Costain carbon capture power job

£4bn Teesside project to start construction next year creating 3,000 jobs
2 days ago

Plans go in to start revamp of North Finchley town centre

Developer Regal unveils first details of Barnet masterplan
1 day ago

Glencar bags £18m Big Yellow London store

Six-storey stoarage centre to be built at Staples Corner
1 day ago

Plan unveiled for 31-storey London Fenchurch Street tower

Demolition work to start in 2026 for new office tower
2 days ago

Vinci Building buys tower cranes for first time

Contractor invests in two WOLFFKRAN all-electric cranes at £138m Sheffield site
2 days ago

30 local firms land United Utilities £500m framework

Minor works deal win for North West civils and M&E specialists
2 days ago

Restructure pays off as Higgins returns to profit

Housing contractor recovers from £25.9m loss last year
2 days ago

Former Heathrow boss joins Mace in board rejig

Firm completes string NED appointments to expanded group board
3 days ago

Planning officers to get powers to bypass committee stage for housing

Rayner reform plan to cut out local council planning committees
3 days ago

National Insurance hike to delay construction recovery

Arcadis paints varied picture with full recovery delayed until 2026
3 days ago

Gratte Bros rides out cost rises with profit increase

M&E specialist warns of further upward pressure on wage costs
3 days ago

Sellar’s 36-storey London City office tower approved

Demolition work to start in 2026 at 60 Gracechurch Street site
5 days ago

Roofers caught using phone lights to work at night

Roofing boss handed suspended prison sentence for lack of edge protection
3 days ago

£380m North West housing framework out for bid

St Helens-based Torus aims to build 9,000 homes by 2029
3 days ago

Historic property magazine to close

Estates Gazette has been in business since 1858
6 days ago

M&S Marble Arch rebuild approved after three-year planning fight

Plans were delayed when Michael Gove backed carbon campaigners
1 week ago

£191m revamp funding approved for London Barbican Centre

Construction to start in 2027 on five-year programme
7 days ago

RED Construction tops £100m turnover

Builder maintains profit margin at 1.7% as business nearly doubles in size
6 days ago

Contractor services