Worker killed by falling wind turbine blade

Grant Prior 9 years ago
Share

Siemens and Fluor have been fined £650,000 after a worker was killed and another seriously injured during construction of an offshore wind farm.

The incident happened when a team of engineers were loading wind turbine blades onto a sea barge for delivery to Greater Gabbard, off the Suffolk coast, on 21 May 2010.

During the loading of wind turbine components at Pakeston Quay, Harwich, a 2.11 tonne part of the blade transport arrangement fell off, crushing and fatally injuring one worker and seriously injuring another.

Chelmsford Crown Court heard both workers were employed by Siemens Windpower A/S (SWP) but were working for Fluor Ltd, the principal contractor.

The injured man, Frank Kroeger, was airlifted to Addenbrookes hospital in Cambridge where he was resuscitated twice.

He suffered a ruptured spleen, lacerations to his liver, a collapsed lung, multiple rib fractures on his left side, and significant crush injuries to his right arm and hand, with nerve damage to his thumb and fingers.

His injuries were life-changing and required almost three weeks in hospital in the UK, followed by a long period of rehabilitation and treatment near his home in Germany.

The family of the fatally-injured man have asked that his name not be released.

The investigation carried out by HSE found serious safety failings in the two firms’ management systems for the loading operation, which allowed vital parts of equipment to go unchecked before being lifted.

Following a four-week trial Fluor Ltd was found guilty of safety breaches and was today ordered to pay £275,000 in fines and £271,048 costs.

Siemens Windpower A/S (SWP) pleaded guilty at an earlier stage and were ordered to pay £375,000 in fines with costs of £105,355.

Speaking after the hearing, HSE Inspector Julie Rayner said: “This incident could easily have been avoided had suitable systems and procedures been in place to ensure that all loads were properly connected whilst being lifted.

“Had the right questions been asked when the lift was being planned and had the bolt and two brackets holding the blade and frame together been checked before they were lifted, the death and serious injury of two workers could have been prevented.

“This case clearly highlights the need to ensure that relevant information is considered when lift plans are produced to ensure that all of the relevant risks are considered.”

Latest news

Construction T Level scrapped due to lack of demand

Courses canned after less than 100 sign-up for latest round
2 hours ago

Bid rigging probe launched into school repair work

Firms raided this week with focus on roofing contracts
1 day ago

McLaren hires ex-ISG regional boss for north east expansion

Andrew Beaumont becomes MD of new Yorkshire and North East business
11 hours ago

Government commits to four new prisons in seven years

£2.3bn pledged for new prison build programme
1 day ago

Road and rail delays hit revenue at Van Elle

Turnover drops 5% as markets remain challenging for piling specialist
10 hours ago

Boot reports ‘noticeable improvement’ in planning system

Government planning reforms already unblocking council planning
10 hours ago

Go-ahead to revamp former London city hall

Project will straighten the building's leaning profile with terraces to every level
18 hours ago

United Living to divert Midlands gas pipeline

600m pipeline diversion clears way for M54 to M6 link road construction
9 hours ago

Credit insurance saves Billington from ISG hit

Steel specialist puts on extra shifts at its plants to cope with demand
1 day ago

M&E specialist Dodd doubles profit on retrofit surge

Family-owned Telford specialist delivers record revenue of nearly £250m
1 day ago

Go-ahead for 800-home Croydon dual towers

One Lansdowne Road build to rent scheme to cost £260m to build
1 day ago

Construction inflation set to return raising tender prices

End of 2024 to mark the bottom of present inflationary trough
1 day ago

Start date for vast Balfour and Costain carbon capture power job

£4bn Teesside project to start construction next year creating 3,000 jobs
2 days ago

Plans go in to start revamp of North Finchley town centre

Developer Regal unveils first details of Barnet masterplan
1 day ago

Glencar bags £18m Big Yellow London store

Six-storey stoarage centre to be built at Staples Corner
1 day ago

Plan unveiled for 31-storey London Fenchurch Street tower

Demolition work to start in 2026 for new office tower
2 days ago

Vinci Building buys tower cranes for first time

Contractor invests in two WOLFFKRAN all-electric cranes at £138m Sheffield site
2 days ago

30 local firms land United Utilities £500m framework

Minor works deal win for North West civils and M&E specialists
2 days ago

Restructure pays off as Higgins returns to profit

Housing contractor recovers from £25.9m loss last year
2 days ago

Former Heathrow boss joins Mace in board rejig

Firm completes string NED appointments to expanded group board
3 days ago

Planning officers to get powers to bypass committee stage for housing

Rayner reform plan to cut out local council planning committees
3 days ago

National Insurance hike to delay construction recovery

Arcadis paints varied picture with full recovery delayed until 2026
3 days ago

Gratte Bros rides out cost rises with profit increase

M&E specialist warns of further upward pressure on wage costs
3 days ago

Sellar’s 36-storey London City office tower approved

Demolition work to start in 2026 at 60 Gracechurch Street site
5 days ago

Roofers caught using phone lights to work at night

Roofing boss handed suspended prison sentence for lack of edge protection
3 days ago

£380m North West housing framework out for bid

St Helens-based Torus aims to build 9,000 homes by 2029
3 days ago

Historic property magazine to close

Estates Gazette has been in business since 1858
6 days ago

M&S Marble Arch rebuild approved after three-year planning fight

Plans were delayed when Michael Gove backed carbon campaigners
1 week ago

£191m revamp funding approved for London Barbican Centre

Construction to start in 2027 on five-year programme
7 days ago

RED Construction tops £100m turnover

Builder maintains profit margin at 1.7% as business nearly doubles in size
6 days ago

Contractor services