Queensferry Crossing to open five months late

Aaron Morby 9 years ago
Share

The Scottish Government has admitted the £1.4bn Queensferry Crossing will now open in May 2017 – five months later than planned.

Forth Crossing Bridge Constructors, the consortium building the bridge, has told ministers that ongoing effects of weather on construction mean it will require more time to complete the bridge.

The joint venture of Dragados, Hochtief, American Bridge International and Morrison Construction said the new opening deadline remained challenging but achievable.

Since last September the downtime due to strong winds has been 40% compared to the 25% anticipated by the contractor.

Until May, the bridge builders thought they could make up lost time.  But in April and May an unprecedented 13 days and 12 days were lost to bad weather scuppering plans to deliver the December 2016 target.

FCBC has taken on an extra 100 workers, increased working hours, altered construction methodologies where possible and challenged critical construction sequences to identify where any programme efficiencies could be found.

But the contractors are now warning they have now reached the stage where further extra resources will not bring the delivery date forward due to the complex technical nature of the construction work.

Screen Shot 2016-06-08 at 17.23.32

Specifically the bridge deck and the cable installation process, which began in September 2015, is particularly sensitive to wind and this increases as the cables used become longer and are installed at a greater height .

FCBC have confirmed this creates an unavoidable knock-on effect for subsequent activities, road surfacing and wind barriers which will now take place in wet and cold conditions during autumn and winter 2016/2017.

The builders contract runs until June 2017, meaning the project will still technically be on time even though completion was brought forward to December this year.

Cabinet Secretary for Economy, Jobs and Fair Work Keith Brown said: “We will continue to work closely with the contractors and I will personally ensure that every pressure and every resource is brought to bear to deliver or even better the revised target date of May 2017

“Going forward, in order to ensure that this project remains on track, I have implemented enhanced governance procedures from Transport Scotland senior management and will receive twice weekly updates from the project team.

“We have always been ambitious about this project and have always worked towards a deliberately ambitious target. However, It is important to recognise that FCBC still fully expects the project to complete within the timeframe of their contract. This project is not late and there will be no impact on the public purse.”

“The December 2016 target date was set to address concerns about the long term condition of the Forth Road bridge where it was originally believed that it would be restricted as early as 2017.

“These concerns have proven to be less immediate and the recently installed structural health monitoring system is providing assurance on the ability of the FRB to sustain traffic.”

Latest news

Deck falls off huge scissor lift at Winvic site

Two men seriously injured as platform plunges to the ground
1 day ago

Bouygues seals deal for £119m Cardiff college campus

Construction to start in June on two new buildings
1 day ago

Bid race starts for £15bn schools framework refresh

DfE throws framework open to more contractors
1 day ago

Berkeley’s £600m Borough Triangle project approved

Controversial scheme features two towers of 38 and 44-storeys
2 days ago

London Mayor calls in blocked 600-bed student scheme

Refused 20-storey London PBSA block may still be built
1 day ago

HG to build 500-bed London Stratford student scheme

Work will start later this year subject to gateway 2 safety approval
2 days ago

Arrest after pedestrian death on construction site

Tragedy during site preparation works for new Wigan car park
1 day ago

British Steel threatens closure of Scunthorpe blast furnaces

Chinese owners say sectional steel and rail supplies will be maintained
2 days ago

Planning green light for Sheffield warehouse site

Existing factories to be demolished in new scheme for Rula Developments
1 day ago

New rail property company to unlock land for 40,000 homes

First four sites released in Newcastle, Cambridge, Manchester, and Nottingham
2 days ago

Drainage specialist Subscan files administration notice

Specialist employing 131 people files court notice
2 days ago

Four win Network Rail £300m engineering design deal

Eastern region deal will include design for Northern Powerhouse Rail
2 days ago

Funding go-ahead for Banwell bypass after fresh cost hike

Galliford Try contract rises £14m to £64m after final design change
3 days ago

Graham wins Southport £75m Marine Lakes Centre

Firm replaces Kier which parted ways with backer Sefton Council
3 days ago

Chancellor unveils extra £2bn capital spend a year

Construction promised a defence dividend in military base and homes upgrade work
3 days ago

McLaren confirms subcontractor team on £135m warehouse job

Work starts on TN2 Gateway site in Kent.
3 days ago

Vistry profits slump after site costs reporting debacle

House builder launches internal whistle-blowing service in business culture review
3 days ago

Severfield chief to step down

Alan Dunsmore to leave structural steel group by end of June
3 days ago

Funding hurdle remains as Lower Thames Crossing gains consent

Government claims £9bn project may start in 2026 as private finance options explored
4 days ago

Mace wins £600m Euston Tower overhaul

1970s tower's foundations and core to be retained as floor plates extended
4 days ago

Summer start for main works on London green tower

Axa sanctions start at 50 Fenchurch Street 36-storey office block
3 days ago

Japan’s leading flats builder JVs with L&G for UK push

Partners plan to build over 1,000 rental homes in London
3 days ago

Wates submits plan for 1,000 homes Harrow council scheme

Former civic centre Poets' Corner site kicks off housing partnership
4 days ago

Morgan Sindall upgrades forecast for next 12 months

Overbury fit-out arm gets off to a flying start in 2025
4 days ago

Restructure underway at Henry Boot Construction

New management team restructures business after drop in turnover
4 days ago

Government pledges £2bn stop-gap funding for 18,000 homes

Funding avoids cliff-edge in social housing delivery before new grant programme agreed
4 days ago

Just two major new roads schemes to start this year

National Highways sets out one-year interim spending plan after RIS3 delay
4 days ago

Plans go in for £400m GRAHAM Manchester site

Demolition and enabling works underway with main construction set to start next year
4 days ago

Building safety levy rate set at up to £10,000 a home in London

Levy introduction pushed back a year to Autumn 2026 - list of new rates
5 days ago

BAM wins £100m revamp of Broadgate Tower in London

Front of tower 3-storey extension to use cross laminate time and re-used steel
5 days ago

Contractor services