Bad weather delays opening of Queensferry Crossing

Grant Prior 8 years ago
Share

Contractors building the new £790m Queensferry Crossing have confirmed they need more time to complete the project.

Bad weather has hampered the final stages of the scheme
Bad weather has hampered the final stages of the scheme

Bad weather and windy conditions have hampered work by the Forth Road Crossing Bridge Constructors – who consist of Hochtief, American Bridge, Dragados and Galliford Try.

Economy Secretary Keith Brown confirmed the expected opening date will be achieved in a window between mid-July and the end of August – approximately 4 to 10 weeks later than predicted on a six year construction programme.

The contractor has reported there have been fewer clear weather windows than expected, particularly in relation to wind.

This has delayed weather dependent activities causing them to bunch together at the end of the programme to a much greater degree than was anticipated in May 2016.

This means that a lot of construction activity is underway simultaneously and careful planning is required to ensure that this can be done safely, so that one activity does not impact on another.

At this stage of the project all remaining activities are vulnerable to weather conditions.

The tower cranes can only be removed in wind speeds of less than 25 mph and when this is happening, it is not possible to safely work within a 50 metre radius of the crane itself.

Work on cable stays is sensitive to wind, waterproofing the bridge deck is sensitive to rain and road surfacing is sensitive to both rain and low temperatures.

Brown said: “Today there are only nine weeks remaining to the end of May and the review has concluded that even with the best weather this date is not now safely achievable.

“I fully recognise the effort of the workforce in building this amazing new bridge. Over 13 million hours have gone into building the Queensferry Crossing over the past six years.

“There is no additional cost to the public purse and the Forth Road Bridge continues to carry traffic over the Forth during these final weeks of construction.

“While its clearly very disappointing the new bridge won’t be ready ahead of the contractual completion date, I believe it is important to take the time to make sure the bridge is built in the safest possible circumstances to the highest possible standards.”

Sally Cox, chair of the Board for the Forth Road Crossing Bridge Constructors said: “FCBC acknowledge that the uniqueness of this project and the onerous weather conditions it has experienced, particularly working at height crossing the Forth have created more challenges than we anticipated.

“FCBC have always been and remain ambitious about completing this challenging project at the earliest possible date and share Transport Scotland and the public’s frustration over this delay.

“We have assured Transport Scotland that every endeavour is and will continue to be made, to safely complete the project at the earliest opportunity.”

Latest news

Winners revealed for £5.4bn electricity grid upgrade

SP Energy Networks unveils 19 winners - full list
19 hours ago

Malaysian property giant to buy 50% stake in JRL

IJM Land to buy into diversified £800m turnover south east contractor
1 day ago

Fast-track skills hubs to train 5,000 extra apprentices

Plan for network of 32 skills hubs to rain construction apprentices in half the time
18 hours ago

Luxury house builder files administration notice

£31m turnover Octagon Developments Ltd lodges court notice
1 day ago

Morgan Sindall takes on £22m stalled ISG Cardiff school job

Workplan is being drawn up ahead of restart on Penarth school
1 day ago

Walker Modular wins bathroom pod deal on student tower

Sealant-free construction method helps supplier dominate student market
1 day ago

Over £600m awarded for decarbonisation projects – full lists

Over 240 public building energy upgrade projects secure cash
2 days ago

Enabling works to start on £130m Huyton town centre regen

Phase one includes a new council HQ, hotel and 72 flats
2 days ago

Ridge buys rival consultant Jubb

Acquisition will see 100 new staff join Ridge
2 days ago

Grainger build to rent pipeline rises to £1.4bn

Rental specialist buys sites in Sheffield and Cardiff to build 600 rental homes
2 days ago

Kier wins Cambridgeshire County council estate upkeep

Firm will provide building and M&E services to 106 buildings across the county
2 days ago

Louvres and solar shading specialist files for administration

Hampshire based ALPS lodges court notice after 25 years in business
2 days ago

Speedy Hire posts a loss in latest results

Hire giant confident of better performance in next six months
2 days ago

Esh to lead next phase of Riverside Sunderland regeneration

Infrastructure work will allow further development of Sheepfolds area
2 days ago

Green light for £1.3bn Edinburgh coastal town revamp

First phase of Granton Waterfront scheme will see Cruden Homes create a new community
3 days ago

Vistry chief operating officer steps down

Earl Sibley exits as his COO role axed for more direct reporting to CEO
3 days ago

House builder Camstead goes into administration

Work stopped on three current sites
4 days ago

Death of piling legend Roger Bullivant

Industry innovator dies after long illness aged 85
3 days ago

ESS Modular went down owing suppliers £7m

Modular specialist owned by ISG owner Cathexis
3 days ago

Builders back farmers in inheritance tax protest

"A rethink is desperately needed" say National Federation of Builders
3 days ago

Willmott Dixon wins £36m leisure centre upgrade

Work to start on historic Westminster 1930s Grade II listed Seymour Centre
3 days ago

Graham wins £100m Cardiff Crossrail phase 1

Work on route to Cardiff Bay to start before end of next year
4 days ago

Laing O’Rourke appoints new European MD

Peter Lyons to take-up new role in February
5 days ago

Profits dip at Stepnell ahead of demerger

Turnover and secured workloads up ahead of restructure
5 days ago

HS2 green bridge deck takes shape

100m-wide wildlife bridge to carry hedgerows and country lane over HS2
4 days ago

1,000-home Wolverhampton city centre scheme in for planning

ECF and council advance City Centre West build to rent scheme
5 days ago

Sisk clinches £54m North London council HQ revamp

Haringey's iconic Grade II listed civic centre to be brought back into use
5 days ago

Ofgem approves £2.5bn Eastern Green Link 1

Work to start next Spring on cable project from Scotland to the north of England
5 days ago

Anglian Water hunts for £1bn delivery partner

Programme delivery partner wil integrate with client team over 15-year plan
5 days ago

Hadden collapse costs supply chain £6.7m

"Highly unlikely" subcontractors will receive anything for their unpaid invoices
5 days ago

Contractor services