Bad weather delays opening of Queensferry Crossing

Grant Prior 8 years ago
Share

Contractors building the new £790m Queensferry Crossing have confirmed they need more time to complete the project.

Bad weather has hampered the final stages of the scheme
Bad weather has hampered the final stages of the scheme

Bad weather and windy conditions have hampered work by the Forth Road Crossing Bridge Constructors – who consist of Hochtief, American Bridge, Dragados and Galliford Try.

Economy Secretary Keith Brown confirmed the expected opening date will be achieved in a window between mid-July and the end of August – approximately 4 to 10 weeks later than predicted on a six year construction programme.

The contractor has reported there have been fewer clear weather windows than expected, particularly in relation to wind.

This has delayed weather dependent activities causing them to bunch together at the end of the programme to a much greater degree than was anticipated in May 2016.

This means that a lot of construction activity is underway simultaneously and careful planning is required to ensure that this can be done safely, so that one activity does not impact on another.

At this stage of the project all remaining activities are vulnerable to weather conditions.

The tower cranes can only be removed in wind speeds of less than 25 mph and when this is happening, it is not possible to safely work within a 50 metre radius of the crane itself.

Work on cable stays is sensitive to wind, waterproofing the bridge deck is sensitive to rain and road surfacing is sensitive to both rain and low temperatures.

Brown said: “Today there are only nine weeks remaining to the end of May and the review has concluded that even with the best weather this date is not now safely achievable.

“I fully recognise the effort of the workforce in building this amazing new bridge. Over 13 million hours have gone into building the Queensferry Crossing over the past six years.

“There is no additional cost to the public purse and the Forth Road Bridge continues to carry traffic over the Forth during these final weeks of construction.

“While its clearly very disappointing the new bridge won’t be ready ahead of the contractual completion date, I believe it is important to take the time to make sure the bridge is built in the safest possible circumstances to the highest possible standards.”

Sally Cox, chair of the Board for the Forth Road Crossing Bridge Constructors said: “FCBC acknowledge that the uniqueness of this project and the onerous weather conditions it has experienced, particularly working at height crossing the Forth have created more challenges than we anticipated.

“FCBC have always been and remain ambitious about completing this challenging project at the earliest possible date and share Transport Scotland and the public’s frustration over this delay.

“We have assured Transport Scotland that every endeavour is and will continue to be made, to safely complete the project at the earliest opportunity.”

Latest news

Deck falls off huge scissor lift at Winvic site

Two men seriously injured as platform plunges to the ground
2 days ago

Bouygues seals deal for £119m Cardiff college campus

Construction to start in June on two new buildings
2 days ago

Bid race starts for £15bn schools framework refresh

DfE throws framework open to more contractors
2 days ago

Berkeley’s £600m Borough Triangle project approved

Controversial scheme features two towers of 38 and 44-storeys
3 days ago

London Mayor calls in blocked 600-bed student scheme

Refused 20-storey London PBSA block may still be built
2 days ago

HG to build 500-bed London Stratford student scheme

Work will start later this year subject to gateway 2 safety approval
3 days ago

Arrest after pedestrian death on construction site

Tragedy during site preparation works for new Wigan car park
2 days ago

British Steel threatens closure of Scunthorpe blast furnaces

Chinese owners say sectional steel and rail supplies will be maintained
3 days ago

Planning green light for Sheffield warehouse site

Existing factories to be demolished in new scheme for Rula Developments
2 days ago

New rail property company to unlock land for 40,000 homes

First four sites released in Newcastle, Cambridge, Manchester, and Nottingham
3 days ago

Drainage specialist Subscan files administration notice

Specialist employing 131 people files court notice
3 days ago

Four win Network Rail £300m engineering design deal

Eastern region deal will include design for Northern Powerhouse Rail
3 days ago

Funding go-ahead for Banwell bypass after fresh cost hike

Galliford Try contract rises £14m to £64m after final design change
4 days ago

Graham wins Southport £75m Marine Lakes Centre

Firm replaces Kier which parted ways with backer Sefton Council
4 days ago

Chancellor unveils extra £2bn capital spend a year

Construction promised a defence dividend in military base and homes upgrade work
4 days ago

McLaren confirms subcontractor team on £135m warehouse job

Work starts on TN2 Gateway site in Kent.
4 days ago

Vistry profits slump after site costs reporting debacle

House builder launches internal whistle-blowing service in business culture review
4 days ago

Severfield chief to step down

Alan Dunsmore to leave structural steel group by end of June
4 days ago

Funding hurdle remains as Lower Thames Crossing gains consent

Government claims £9bn project may start in 2026 as private finance options explored
5 days ago

Mace wins £600m Euston Tower overhaul

1970s tower's foundations and core to be retained as floor plates extended
5 days ago

Summer start for main works on London green tower

Axa sanctions start at 50 Fenchurch Street 36-storey office block
4 days ago

Japan’s leading flats builder JVs with L&G for UK push

Partners plan to build over 1,000 rental homes in London
4 days ago

Wates submits plan for 1,000 homes Harrow council scheme

Former civic centre Poets' Corner site kicks off housing partnership
5 days ago

Morgan Sindall upgrades forecast for next 12 months

Overbury fit-out arm gets off to a flying start in 2025
5 days ago

Restructure underway at Henry Boot Construction

New management team restructures business after drop in turnover
5 days ago

Government pledges £2bn stop-gap funding for 18,000 homes

Funding avoids cliff-edge in social housing delivery before new grant programme agreed
5 days ago

Just two major new roads schemes to start this year

National Highways sets out one-year interim spending plan after RIS3 delay
5 days ago

Plans go in for £400m GRAHAM Manchester site

Demolition and enabling works underway with main construction set to start next year
5 days ago

Building safety levy rate set at up to £10,000 a home in London

Levy introduction pushed back a year to Autumn 2026 - list of new rates
6 days ago

BAM wins £100m revamp of Broadgate Tower in London

Front of tower 3-storey extension to use cross laminate time and re-used steel
6 days ago

Contractor services