Bad weather delays opening of Queensferry Crossing

Grant Prior 8 years ago
Share

Contractors building the new £790m Queensferry Crossing have confirmed they need more time to complete the project.

Bad weather has hampered the final stages of the scheme
Bad weather has hampered the final stages of the scheme

Bad weather and windy conditions have hampered work by the Forth Road Crossing Bridge Constructors – who consist of Hochtief, American Bridge, Dragados and Galliford Try.

Economy Secretary Keith Brown confirmed the expected opening date will be achieved in a window between mid-July and the end of August – approximately 4 to 10 weeks later than predicted on a six year construction programme.

The contractor has reported there have been fewer clear weather windows than expected, particularly in relation to wind.

This has delayed weather dependent activities causing them to bunch together at the end of the programme to a much greater degree than was anticipated in May 2016.

This means that a lot of construction activity is underway simultaneously and careful planning is required to ensure that this can be done safely, so that one activity does not impact on another.

At this stage of the project all remaining activities are vulnerable to weather conditions.

The tower cranes can only be removed in wind speeds of less than 25 mph and when this is happening, it is not possible to safely work within a 50 metre radius of the crane itself.

Work on cable stays is sensitive to wind, waterproofing the bridge deck is sensitive to rain and road surfacing is sensitive to both rain and low temperatures.

Brown said: “Today there are only nine weeks remaining to the end of May and the review has concluded that even with the best weather this date is not now safely achievable.

“I fully recognise the effort of the workforce in building this amazing new bridge. Over 13 million hours have gone into building the Queensferry Crossing over the past six years.

“There is no additional cost to the public purse and the Forth Road Bridge continues to carry traffic over the Forth during these final weeks of construction.

“While its clearly very disappointing the new bridge won’t be ready ahead of the contractual completion date, I believe it is important to take the time to make sure the bridge is built in the safest possible circumstances to the highest possible standards.”

Sally Cox, chair of the Board for the Forth Road Crossing Bridge Constructors said: “FCBC acknowledge that the uniqueness of this project and the onerous weather conditions it has experienced, particularly working at height crossing the Forth have created more challenges than we anticipated.

“FCBC have always been and remain ambitious about completing this challenging project at the earliest possible date and share Transport Scotland and the public’s frustration over this delay.

“We have assured Transport Scotland that every endeavour is and will continue to be made, to safely complete the project at the earliest opportunity.”

Latest news

Staff stunned as engineering consultancy Clarkebond closes

Firm was only bought three months ago by rival Independent Design House Group
21 hours ago

Vistry issues third profit warning in three months

Profit expected to fall £50m below forecast due to delayed completions
21 hours ago

Miller Homes buys St Modwen Homes for £215m

Scottish house builder snaps up £368m turnover rival
4 days ago

Keltbray fine increased to £18m after failed bid rigging appeal

Contractor loses penalty discount for settling with competition authorities
4 days ago

Luxury house builder goes under with 70 job losses

Octagon Developments in administration after 40 years in business
5 days ago

Top Ten best read stories of 2024

The biggest headlines of an eventful year. Have a good one and here's to a successful 2025
5 days ago

BAM Nuttall fined £800,000 after concrete skip tragedy

Young labourer killed by falling bale arm
6 days ago

Keltbray infrastructure business reveals new name

AUREOS means "new dawn" after private equity acquisition
5 days ago

Stiffer fines for over-running street works from next Summer

Cash raised from lane rentals to be channeled into pothole repairs
5 days ago

£113m Basildon rental homes scheme seals build finance

Work expected to start early next year on Market Square project
5 days ago

Notting Hill Genesis seeks more tier 1 repairs contractors

London housing trust seeks eight firms for new £1.5bn repairs framework
5 days ago

Reclaimed steel oil rig columns worked into London office revamp

Curo will use reclaimed bricks and steel for Fitzrovia office overhaul
6 days ago

CITB delays levy approval consultation

Levy agreement talks pushed back by ongoing review into effectiveness of training body
6 days ago

Ofwat approves £104bn water industry spending plan

Household water bills to rise by 36% to fund quadrupling of investment
6 days ago

Costain/ Siemens JV clinches HS2 power supply job

£300m deal for HV power supply systems over the 225km route
6 days ago

Demolition team assembles on Multiplex London Wall site

Erith to start work next month at Deutsche Bank's former headquarters
7 days ago

Norwich Council acts to revive £300m Anglia Square scheme

Council uses Homes England funding to buy stalled site with planning for 1,100 homes
6 days ago

Go-ahead for 4,500-home Cambridgeshire new town

Waterbeach new town plan stalled three years ago after an Environment Agency objection
6 days ago

Henry Boot to take total control of Stonebridge Homes

Deal worth at least £30m
6 days ago

HS2 costs could hit £66bn

Government looking for next estimate to be lower
7 days ago

Mace to close construction logistics arm

Specialist business being wound down
7 days ago

National Grid to invest £35bn over next five years

Plan set out for record investment in electricity transmission infrastructure
7 days ago

Profits double at Barhale

Civils specialist sees order book top £1bn
7 days ago

Balfour wins 68km HV underground power cable deal

Main works to start next year on Eastern Green Link 2 job
7 days ago

Stunning site wrap unveiled on Sloane Street

Hoarding creates illusion of fully formed façade on £53m Galliford Try job
7 days ago

Heathrow Airport upgrade spend takes off again

Airport operator will spend £2.3bn over the next two years
7 days ago

Government buys back over 36,000 military homes

Public ownership deal to release wave of upgrade and new build work
1 week ago

Story Contracting staff braced for rail job losses

Work coming through slower than expected from Network Rail
1 week ago

Ballymore submits two plans for 3,700 East London homes

Construction could start in 2025 on Thames Road and Knights Road schemes
1 week ago

Blackpool council steps in on failed developer’s £300m scheme

Blackpool Central site clearance to start in the New Year as hunt starts for new developer
1 week ago

Contractor services