Mace Nova site finishes late and busts budget

Grant Prior 8 years ago
Share

Land Securities has confirmed its Nova project in Victoria has busted the budget and overrun by nine months.

The first phase at Nova was completed last month
The first phase at Nova was completed last month

The first phase of the scheme, where Mace was main contractor, was completed last month.

The developer said: “The complexities of construction – together with competition for labour in a busy sector – delayed final completion and impacted costs.”

The scheme was also hit by the failure of main concrete specialist PC Harrington.

Work was due to finish last summer and cost £248m.

In its latest results today Land Securities said is has “paused for breath” in its major development cycle as it has largely completed its latest speculative development programme.

The developer revealed a strong set of annual results today and confirmed it has its eye on the next round of opportunities in the property market.

Chief executive Robert Noel said: “Put simply, our markets remain in good health but they’ve paused for breath.”

“The foundations of the business are rock solid, underpinned by our resilient portfolio and low leverage.

“We’ve achieved our plan to have minimal development exposure and longer lease terms in London offices, a transformed retail portfolio and low gearing at this point.

In the short term, with significantly reduced risk and a portfolio of first class assets, we go forward in excellent shape, ready to make acquisitions when the time is right.

“Longer term, we remain confident in our market and our ability to deliver sustainable growth.”

Plans are being drawn-up for a second Nova East phase and Land Securities also has planning at 21 Moorfields in the City where demolition is complete with piling work set to start shortly ahead of construction of a raft that will sit above the eastern entrance to Liverpool Street Crossrail station.

It will be the platform for 522,000 sq ft of space across two buildings.

The firm said: “Completing the raft in July 2018 will mean we can complete construction of the buildings in 24 months, providing an excellent prospect for the pre-letting market.”

Land Securities also has planning consent for a 142,000 sq ft mixed use scheme in Westminster at 1 Sherwood Street, W1 and a 134,000 sq ft development in Southwark, at Sumner Street, SE1.

Latest news

Staff stunned as engineering consultancy Clarkebond closes

Firm was only bought three months ago by rival Independent Design House Group
3 days ago

Vistry issues third profit warning in three months

Profit expected to fall £50m below forecast due to delayed completions
3 days ago

Miller Homes buys St Modwen Homes for £215m

Scottish house builder snaps up £368m turnover rival
6 days ago

Keltbray fine increased to £18m after failed bid rigging appeal

Contractor loses penalty discount for settling with competition authorities
7 days ago

Luxury house builder goes under with 70 job losses

Octagon Developments in administration after 40 years in business
1 week ago

Top Ten best read stories of 2024

The biggest headlines of an eventful year. Have a good one and here's to a successful 2025
1 week ago

BAM Nuttall fined £800,000 after concrete skip tragedy

Young labourer killed by falling bale arm
1 week ago

Keltbray infrastructure business reveals new name

AUREOS means "new dawn" after private equity acquisition
1 week ago

Stiffer fines for over-running street works from next Summer

Cash raised from lane rentals to be channeled into pothole repairs
1 week ago

£113m Basildon rental homes scheme seals build finance

Work expected to start early next year on Market Square project
1 week ago

Notting Hill Genesis seeks more tier 1 repairs contractors

London housing trust seeks eight firms for new £1.5bn repairs framework
1 week ago

Reclaimed steel oil rig columns worked into London office revamp

Curo will use reclaimed bricks and steel for Fitzrovia office overhaul
1 week ago

CITB delays levy approval consultation

Levy agreement talks pushed back by ongoing review into effectiveness of training body
1 week ago

Ofwat approves £104bn water industry spending plan

Household water bills to rise by 36% to fund quadrupling of investment
1 week ago

Costain/ Siemens JV clinches HS2 power supply job

£300m deal for HV power supply systems over the 225km route
1 week ago

Demolition team assembles on Multiplex London Wall site

Erith to start work next month at Deutsche Bank's former headquarters
1 week ago

Norwich Council acts to revive £300m Anglia Square scheme

Council uses Homes England funding to buy stalled site with planning for 1,100 homes
1 week ago

Go-ahead for 4,500-home Cambridgeshire new town

Waterbeach new town plan stalled three years ago after an Environment Agency objection
1 week ago

Henry Boot to take total control of Stonebridge Homes

Deal worth at least £30m
1 week ago

HS2 costs could hit £66bn

Government looking for next estimate to be lower
1 week ago

Mace to close construction logistics arm

Specialist business being wound down
1 week ago

National Grid to invest £35bn over next five years

Plan set out for record investment in electricity transmission infrastructure
1 week ago

Profits double at Barhale

Civils specialist sees order book top £1bn
1 week ago

Balfour wins 68km HV underground power cable deal

Main works to start next year on Eastern Green Link 2 job
1 week ago

Stunning site wrap unveiled on Sloane Street

Hoarding creates illusion of fully formed façade on £53m Galliford Try job
1 week ago

Heathrow Airport upgrade spend takes off again

Airport operator will spend £2.3bn over the next two years
1 week ago

Government buys back over 36,000 military homes

Public ownership deal to release wave of upgrade and new build work
1 week ago

Story Contracting staff braced for rail job losses

Work coming through slower than expected from Network Rail
1 week ago

Ballymore submits two plans for 3,700 East London homes

Construction could start in 2025 on Thames Road and Knights Road schemes
1 week ago

Blackpool council steps in on failed developer’s £300m scheme

Blackpool Central site clearance to start in the New Year as hunt starts for new developer
2 weeks ago

Contractor services