Highways England delays 22 major road projects

Aaron Morby 7 years ago
Share

Twenty-two major road improvement projects in England have been delayed or face cancellation after Highways England revised its £15bn road improvement programme.

Highways England said that 16 projects were being put back by between three months and two years to reduce the impact of roadworks on motorists and minimise congestion while improvements take place.

They include four separate upgrades to the M25, work on the M60 in Greater Manchester, the M3 in Winchester and the A5 in Nuneaton, Warwickshire,

Six more projects may not happen at all after Highways England said they were being “paused for further review” to achieve an acceptable return on investment.

But the rescheduling programme outlined in the Supplementary Delivery Plan will see 10 schemes brought forward.

10 schemes being brought forward

  • A19 Testos
  • A19 Downhill Lane
  • M56 junctions 6-8 smart motorway
  • M6 junctions 21a – 26 smart motorway
  • M6 junction 22 upgrade
  • A500 Etruria
  • M6 junction 10
  • M4 Heathrow Slips
  • A47 Acle Straight -small scale improvement
  • A47 and A12 junction enhancement

16 schemes being re-scheduled

  • A5 Dodwells to Longshoot widening
  • M3 junction 9 improvement
  • A31 Ringwood
  • M27 junctions 4-11
  • A47 North Tuddenham to Easton
  • A47 Blofield to North Burlingham dualling
  • M25 junction 25 improvement
  • M25 junction 28 improvement
  • A1 Birtley to Coal House
  • M60 junctions 24-27 and junction 1-4 smart motorway
  • A47/A11 Thickthorn
  • A47 Wansford to Sutton
  • A47 Guyhirn Junction
  • A12 Chelmsford to A120 widening
  • M25 junction 10/A3 Wisley interchange
  • M25 junctions 10-16

Schemes on hold pending value for money review

  • A1 & A19 Technology enhancements
  • M11 junctions 8 to 14 technology upgrade
  • A12 whole-route technology upgrade
  • M53 junctions 5-11 smart motorway
  • A14 Junction 10a
  • M62/ M606 Chain Bar

Highways England said two further schemes – the M5 Bridgwater junction improvements and A50 Uttoxeter Project B growth corridor project – required rework to achieve value for money, but changes in local development plans mean that these schemes could be progressed, albeit pushed back  in the early stages of Road Period 2.

Jim O’Sullivan, Highways England Chief Executive said: “Our update today is a sensible and responsible way to deliver major national investment in road infrastructure. It will keep our roads moving, deliver a lasting legacy for the country and ensure best value for money for the taxpayer.

“We have assessed the value for money provided by each of the schemes in our plans and of their impact on road users, and have also looked at how each scheme fitted with the overall objectives of the RIS and its costs and benefits.

“This rigorous process identified a number of schemes which do not meet our targets for value for money. For many of these schemes we were able to develop options to improve their value for money. For the remaining schemes
we will continue to review other value for money options and consider scheduling these schemes as part of any future RIS.”

Details of revised start dates.

Latest news

Deck falls off huge scissor lift at Winvic site

Two men seriously injured as platform plunges to the ground
2 days ago

Bouygues seals deal for £119m Cardiff college campus

Construction to start in June on two new buildings
2 days ago

Bid race starts for £15bn schools framework refresh

DfE throws framework open to more contractors
2 days ago

Berkeley’s £600m Borough Triangle project approved

Controversial scheme features two towers of 38 and 44-storeys
3 days ago

London Mayor calls in blocked 600-bed student scheme

Refused 20-storey London PBSA block may still be built
2 days ago

HG to build 500-bed London Stratford student scheme

Work will start later this year subject to gateway 2 safety approval
3 days ago

Arrest after pedestrian death on construction site

Tragedy during site preparation works for new Wigan car park
2 days ago

British Steel threatens closure of Scunthorpe blast furnaces

Chinese owners say sectional steel and rail supplies will be maintained
3 days ago

Planning green light for Sheffield warehouse site

Existing factories to be demolished in new scheme for Rula Developments
2 days ago

New rail property company to unlock land for 40,000 homes

First four sites released in Newcastle, Cambridge, Manchester, and Nottingham
3 days ago

Drainage specialist Subscan files administration notice

Specialist employing 131 people files court notice
3 days ago

Four win Network Rail £300m engineering design deal

Eastern region deal will include design for Northern Powerhouse Rail
3 days ago

Funding go-ahead for Banwell bypass after fresh cost hike

Galliford Try contract rises £14m to £64m after final design change
4 days ago

Graham wins Southport £75m Marine Lakes Centre

Firm replaces Kier which parted ways with backer Sefton Council
4 days ago

Chancellor unveils extra £2bn capital spend a year

Construction promised a defence dividend in military base and homes upgrade work
4 days ago

McLaren confirms subcontractor team on £135m warehouse job

Work starts on TN2 Gateway site in Kent.
4 days ago

Vistry profits slump after site costs reporting debacle

House builder launches internal whistle-blowing service in business culture review
4 days ago

Severfield chief to step down

Alan Dunsmore to leave structural steel group by end of June
4 days ago

Funding hurdle remains as Lower Thames Crossing gains consent

Government claims £9bn project may start in 2026 as private finance options explored
5 days ago

Mace wins £600m Euston Tower overhaul

1970s tower's foundations and core to be retained as floor plates extended
5 days ago

Summer start for main works on London green tower

Axa sanctions start at 50 Fenchurch Street 36-storey office block
4 days ago

Japan’s leading flats builder JVs with L&G for UK push

Partners plan to build over 1,000 rental homes in London
4 days ago

Wates submits plan for 1,000 homes Harrow council scheme

Former civic centre Poets' Corner site kicks off housing partnership
5 days ago

Morgan Sindall upgrades forecast for next 12 months

Overbury fit-out arm gets off to a flying start in 2025
5 days ago

Restructure underway at Henry Boot Construction

New management team restructures business after drop in turnover
5 days ago

Government pledges £2bn stop-gap funding for 18,000 homes

Funding avoids cliff-edge in social housing delivery before new grant programme agreed
5 days ago

Just two major new roads schemes to start this year

National Highways sets out one-year interim spending plan after RIS3 delay
5 days ago

Plans go in for £400m GRAHAM Manchester site

Demolition and enabling works underway with main construction set to start next year
5 days ago

Building safety levy rate set at up to £10,000 a home in London

Levy introduction pushed back a year to Autumn 2026 - list of new rates
6 days ago

BAM wins £100m revamp of Broadgate Tower in London

Front of tower 3-storey extension to use cross laminate time and re-used steel
6 days ago

Contractor services