Centre Point Tower developer claws back £1m from McAlpine

Aaron Morby 7 years ago
Share

The developer behind London’s Centre Point tower conversion into luxury apartments has clawed back a £1m payment to Sir Robert McAlpine in the High Court.

Developer Almacantar and McAlpine became pitched against each other following a bust-up over delivering the project as a design and build job.

McAlpine was working on the £100m-plus project under a pre-construction service agreement (PCSA) signed in Spetember 2012. But by June 2014 ahead of moving to the next main contract stage, McAlpine said it would no longer entertain a design and build contract and proposed a construction management or management contract form of procurement.

Almacantar rejected the offer and the contract was terminated in September. Three months later Almacantar appointed Multiplex as the main contractor for the job.

The two then became embroiled in a dispute about whether the contract terms allowed a final part of McAlpine’s fee to be released under the PCSA agreement.

McAlpine contended that the previous two-stage contract terms allowed it to be paid a remaining 50% tranche of fee when any main contractor was appointed.

Almacantar argued that the terms of releasing the second part of the fee only applied once a main contract was agreed with McAlpine, not any other contractor.

Initially an adjudicator ruled in McAlpine’s favour, but the High Court has now backed Almacantar, ordering McApine to repay the £1.1m including interest awarded in the adjudication.

Justice Jefford said: “This is not a contract under which, if Almacantar exercised its right to terminate, it would, with impunity, avoid paying the second 50% of the fee.

“The purpose of the PCSA was to put Almacantar in a position to proceed with a well-planned design and build contract with developed contractor’s proposals and a robust contract sum.

“In most circumstances in which Almacantar terminated SRM’s engagement, Almacantar would to a greater or lesser extent lose those benefits and have to go back to the drawing board with another contractor.

“That would be the position if the parties could not reach agreement, if Almacantar was dissatisfied with SRM or if, as happened, SRM did not wish to proceed.”

Justice Jefford added: “The only circumstance in which Almacantar would have a windfall  – but a fairly valueless one – and SRM would be unfairly out of pocket would be if Almacantar decided not to proceed with the project at all.

“If on the other hand SRM’s construction of the PCSA were right, they would receive the second 50% of the fee even if its services had been of no benefit to Almacantar in engaging with another contractor.”

 

 

Latest news

Deck falls off huge scissor lift at Winvic site

Two men seriously injured as platform plunges to the ground
2 days ago

Bouygues seals deal for £119m Cardiff college campus

Construction to start in June on two new buildings
2 days ago

Bid race starts for £15bn schools framework refresh

DfE throws framework open to more contractors
2 days ago

Berkeley’s £600m Borough Triangle project approved

Controversial scheme features two towers of 38 and 44-storeys
3 days ago

London Mayor calls in blocked 600-bed student scheme

Refused 20-storey London PBSA block may still be built
2 days ago

HG to build 500-bed London Stratford student scheme

Work will start later this year subject to gateway 2 safety approval
3 days ago

Arrest after pedestrian death on construction site

Tragedy during site preparation works for new Wigan car park
2 days ago

British Steel threatens closure of Scunthorpe blast furnaces

Chinese owners say sectional steel and rail supplies will be maintained
3 days ago

Planning green light for Sheffield warehouse site

Existing factories to be demolished in new scheme for Rula Developments
2 days ago

New rail property company to unlock land for 40,000 homes

First four sites released in Newcastle, Cambridge, Manchester, and Nottingham
3 days ago

Drainage specialist Subscan files administration notice

Specialist employing 131 people files court notice
3 days ago

Four win Network Rail £300m engineering design deal

Eastern region deal will include design for Northern Powerhouse Rail
3 days ago

Funding go-ahead for Banwell bypass after fresh cost hike

Galliford Try contract rises £14m to £64m after final design change
3 days ago

Graham wins Southport £75m Marine Lakes Centre

Firm replaces Kier which parted ways with backer Sefton Council
3 days ago

Chancellor unveils extra £2bn capital spend a year

Construction promised a defence dividend in military base and homes upgrade work
4 days ago

McLaren confirms subcontractor team on £135m warehouse job

Work starts on TN2 Gateway site in Kent.
4 days ago

Vistry profits slump after site costs reporting debacle

House builder launches internal whistle-blowing service in business culture review
4 days ago

Severfield chief to step down

Alan Dunsmore to leave structural steel group by end of June
4 days ago

Funding hurdle remains as Lower Thames Crossing gains consent

Government claims £9bn project may start in 2026 as private finance options explored
5 days ago

Mace wins £600m Euston Tower overhaul

1970s tower's foundations and core to be retained as floor plates extended
5 days ago

Summer start for main works on London green tower

Axa sanctions start at 50 Fenchurch Street 36-storey office block
4 days ago

Japan’s leading flats builder JVs with L&G for UK push

Partners plan to build over 1,000 rental homes in London
4 days ago

Wates submits plan for 1,000 homes Harrow council scheme

Former civic centre Poets' Corner site kicks off housing partnership
4 days ago

Morgan Sindall upgrades forecast for next 12 months

Overbury fit-out arm gets off to a flying start in 2025
5 days ago

Restructure underway at Henry Boot Construction

New management team restructures business after drop in turnover
5 days ago

Government pledges £2bn stop-gap funding for 18,000 homes

Funding avoids cliff-edge in social housing delivery before new grant programme agreed
5 days ago

Just two major new roads schemes to start this year

National Highways sets out one-year interim spending plan after RIS3 delay
5 days ago

Plans go in for £400m GRAHAM Manchester site

Demolition and enabling works underway with main construction set to start next year
5 days ago

Building safety levy rate set at up to £10,000 a home in London

Levy introduction pushed back a year to Autumn 2026 - list of new rates
6 days ago

BAM wins £100m revamp of Broadgate Tower in London

Front of tower 3-storey extension to use cross laminate time and re-used steel
6 days ago

Contractor services