Five key safety breaches identified at Grenfell

Aaron Morby 7 years ago
Share

Deficiencies in the windows, cavity barriers and the cladding system allowed Grenfell tower to be rapidly engulfed in the blaze that saw 71 people lose their lives.

A leaked interim report for the Metropolitan Police offers the most detailed assessment yet of the failures in the refurbishment of the building.

It concludes that the fire would not have spread beyond flat 16 on the fourth floor and would not have claimed even a single life if the original facade of the building had not been over-clad between 2014 and 2016.

Parts of the building were also close to collapse at the height of the blaze, but thicker than presently required floor slabs and columns appeared to have saved the building.

According to the London Evening Standard, which has seen a leaked copy of the draft report produced by experts at BRE Global, the refurbishment of the building failed to meet fire safety standards on several counts.

There were gaps of 15cm between the window frames and concrete columns. These were plugged with a rubberised membrane, rigid foam insulation and uPVC lightweight plastic panels, the paper reported.

These materials provided a fuel that allowed the fire originally to spread to the facade and later penetrate other flats as it spread up the exterior of the building.

Cavity barriers failed to seal the void between the original concrete building fabric and the external aluminium composite material cladding during the fire. These fire blocks were often too small, or incorrectly installed found investigators.

This allowed fire to spread rapidly through a chimney effect, particularly up exterior column lines.

The BRE report also finds insulation fitted to the outside of the building was combustible, allowing fire to spread up and across sections of the facade.

ACM cladding panels had flammable polyethylene or plastic cores this allowed fire to spread upwards and across the building ,with burning droplets of polyethylene also falling and igniting combustible materials below.

Taken together the failings in the cladding system proved of greater significance taken together than in isolation.

The report also identifies a lack on door closers which meant that as tenants fled many were left open allowing smoke and fire to spread through corridors, impacting on residents escape down the single stairwell.

It also says that Grenfell should have been fitted with a wet riser main to aid firefighting rather than a dry riser and only enough room around the building for single fire engine to get close to supply water.

The report has not explicitly concluded whether the design or installation was at fault and whether works were approved or inspected.

Latest news

Site labour rates hit record high as cost inflation returns

Industry's biggest payroll firm says rates rose nearly 5% last month in London
5 hours ago

Morris & Spottiswood acquires part of ISG fit-out division

ISG Cathedral acquisition saves 111 jobs and expands presence across England
20 hours ago

New work drives Q3 construction output uplift

Third quarter activity up 0.8% despite slowdown in September
4 hours ago

Octavius cuts concrete formwork strike time by 5 days

Temperature probes reduce times for safely striking formwork
4 hours ago

Plan for 200-home student-led London scheme

Developer Regal is behind new Camden Town scheme
6 hours ago

Green light for new £45m tax office in Portsmouth

HMRC to occupy new office complex with construction starting next year
4 hours ago

Extra tunnels included in £6bn East West Rail scheme

Government unveils plans for two new tunnels in Cambridgeshire
1 day ago

Infrastructure to get £80bn boost from public sector pensions

New "megafunds" will invest in UK construction projects
1 day ago

Bidders wanted for £800m building safety framework

Fusion21 launches renewal of deal across 12 lots
2 days ago

Winchmore wins £6.5m brickwork package on Stratford flats

Latest award from Graham on £69m development
1 day ago

Motts/Jacobs JV to design £2.5bn West Yorkshire Mass Transit

First construction could begin in 2028
2 days ago

Muse signs landmark deal to redevelop Solihull shopping centre

Mell Square scheme includes 1,600 homes at 6.4ha town centre site
2 days ago

Reds10 raids house builders for two director hires

David Newey and James Bateman join as regional ops directors
3 days ago

Builder killed as telehandler overturns

House builder goes into liquidation before court hearing and £160,000 fine
3 days ago

Balfour Beatty regional MD steps down

Lindsay McGibbon is understood to be exiting for a job in the United States
2 days ago

Firms put on alert for £1.5bn decarbonisation framework

Fusion21 aims to invite bids in January for housing and public buildings retrofit framework
3 days ago

Morgan Sindall aboard for £22m London station roof renewal

Passengers will continue to use Liverpool Street Station while roof works take place above
2 days ago

Utilities contractor turns to Africa for skilled workers

IES Utilities Group recruits its 100th overhead linesman from South Africa and Zimbabwe
2 days ago

McLaren boosts building safety and refurb team

Paul Woodhams promoted to newly created MD role at expanding division
3 days ago

Firms fight to renew places on £450m JV North deal

17 firms face fight to retain places on north west housing consortium list
3 days ago

Subbies get £7m lifeline on ISG Cardiff schools site

Council strikes deal with administrators and appoints emergency interim contractor
4 days ago

United Utilities names water and waste water design consultants

AtkinsRéalis, Jacobs, Stantec, Binnies, Mott MacDonald, RPS, and WSP make line-up
3 days ago

Crown Estate in £1.5bn Cambridge Business Park revamp plan

A phased programme of construction will start in 2026
4 days ago

McLaughlin & Harvey returns to profit

Contractor back in the black and looking forward to another positive year
3 days ago

Graham wins £69m London Stratford flats job

Stratford Mill project will deliver nearly 250 flats
4 days ago

Mace to complete construction of ISG neuroscience centre

Contractor to work with UCL to finish stalled job
4 days ago

BAM finally breaks ground at £60m-plus Yeovil College

Agreed contract price 50% above original estimate on delayed Somerset college job
3 days ago

Forterra trying to pass on NI cost increases

Brick and block giant writing to customers about 2025 price rises
4 days ago

Refurb contractor Troy Central goes into administration

Suffolk based hotel and leisure specialist had a £38m turnover
4 days ago

Former ISG director joins Wates as regional construction MD

Wayne Flannery joins Wates construction board after nearly 20 years at ISG
4 days ago

Contractor services