Contractors fuming over Hinkley security delays

Grant Prior 6 years ago
Share

Workers looking to start on the Hinkley Point nuclear power plant are facing a wait of more than six weeks to get security clearance.

Contractors are fuming at the delays which they fear are putting off workers from joining the job.

One site source said: “I’ve worked on virtually every big nuclear site over the last few decades and it still took me eight weeks to get clearance.”

Security checks for site workers are carried out by independent agencies and administered by G4S under an £80m contract awarded by client EDF Energy.

Another source said: “The contractors are up in arms about this because the checks are taking so long.

“The whole process is a complete nightmare as they go through every tiny detail of your work history and background.

“It’s tough as it is getting enough workers to the site but things like this put people off.

“A lot of people hear about the delays and just go off to another job.”

EDF said:“The Government requires people working on nuclear sites to undergo security vetting.

“We’ve heard feedback from our contractors that the process is taking too long and we have been working with the regulator, the Office for Nuclear Regulation to address the issue.

“We have introduced a new level of access in August. For some groups of workers this is reducing the time needed to get clearance to just 24 hours. They will also undergo appropriate site inductions.”

Caroline Blackman, HR director for civils contractor Bouygues Laing O’Rourke said : “This new type of access has transformed the way our workers get onto site and means that you can be at work within days of getting a job rather than weeks.

“It’s a great example of how complex processes can be simplified without compromising standards.”

Latest news

Tax-row tunnellers down tools on Balfour Hinkley job

Lodge allowance tax dispute hits tunnelling site
3 hours ago

Go-ahead for Square Mile’s fifth tallest tower

Multiplex set to start 99 Bishopsgate job late next year
12 hours ago

New £4.5bn funding model for stalled London rail schemes

Residential TIF funding offers key to unlock Bakerloo and DLR extensions
3 hours ago

Speedy Hire latest to be hit by slow CP7 rail spending

Plant-hire firm flags issues with latest Network Rail spending round
3 hours ago

FM Conway family chair steps away from business after Vinci deal

Joanne Conway steps away as Andrew Hansen becomes MD
2 hours ago

Manchester Hotspur Press mill scheme rescued

37-storey student tower will now go-ahead
3 hours ago

Watkin Jones to advance 260-room London aparthotel

Development deal for New Kent Road project
2 days ago

Plan for film studios switched to data centre cluster

Plans in for six data centre buildings in Buckinghamshire
4 days ago

Hunt for firm to deliver £75m Cambridge Civic Quarter

Work includes £41m Guildhall and £21m Corn Exchange revamps
3 days ago

Plans in for £200m Middlesbrough regen scheme

Wates is lined up to deliver landmark Gresham rental homes scheme
3 days ago

£600m Bristol shopping centre redevelopment approved

Galleries centre will be demolished for homes and offices quarter
3 days ago

Ant Yapi lands ultra prime London homes job

Prestige scheme replicates Regency mansions around nearby Regent’s Park
3 days ago

CITB survives another review

Report published after two more years talking about skills crisis
4 days ago

Strucktor wins record M&E package from Ardmore

Major subcontract on £240m Tribeca life science development
3 days ago

Over 800 high-rise resi jobs stalled by safety regulator

Building safety regulator project logjam hits Government growth plan
4 days ago

McAlpine under fire after another panel comes loose from hotel

High winds cause more problems at recently completed Woking hotel
5 days ago

McGee starts demolition for £500m South Bank scheme

Former ITV studios will be replaced by two office towers
4 days ago

Four arrested after hospital construction site burglary

Damage and copper wiring stolen at Hinckley and District General Hospital new building
5 days ago

Caddick kicks off Digbeth regen plan with £43m flats job

First phase 211 flats job starts wider £260m Upper Trinity Street scheme
4 days ago

Sisk starts work on £300m Children’s Cancer Centre

Great Ormond Street Hospital job will employ 500 on site and last three years
4 days ago

McAlpine clinches £1.25bn Port Talbot low carbon steelworks job

Deal to build one of the largest electric arc furnaces in the world
6 days ago

McLaren to build top-down on £60m New Bond Street contract

Contractor working to tight technical guidelines on busy Mayfair site
5 days ago

Project delays dull Van Elle first-half results

Piling specialist upbeat about year ahead as order book up 24%
5 days ago

Aggregate Industries appoints new contracting chief

Kevin Murgatroyd promoted to new role
5 days ago

Bouygues wins Immingham £170m import jetty job

French civils firm to build bulk ammonia import facility for hydrogen economy
6 days ago

Plans in for latest phase of Leith port revamp

Construction to start this year on transforming waterfront
5 days ago

Avant Homes starts redundancy consultation

Jobs under threat at Central region
6 days ago

Plans in for Barnet leisure park and 1500 homes

Regal to redevelop Great North Leisure Park in Finchley
6 days ago

JRL wins shell and core for £400m London scheme

220 Blackfriars Road project will rise to 21 and 15 storeys
7 days ago

Robertson strengthens East Midlands leadership

Woodcock promoted to ops director and Brown joins from BAM as commercial director
6 days ago

Contractor services