Contractors fuming over Hinkley security delays

Grant Prior 6 years ago
Share

Workers looking to start on the Hinkley Point nuclear power plant are facing a wait of more than six weeks to get security clearance.

Contractors are fuming at the delays which they fear are putting off workers from joining the job.

One site source said: “I’ve worked on virtually every big nuclear site over the last few decades and it still took me eight weeks to get clearance.”

Security checks for site workers are carried out by independent agencies and administered by G4S under an £80m contract awarded by client EDF Energy.

Another source said: “The contractors are up in arms about this because the checks are taking so long.

“The whole process is a complete nightmare as they go through every tiny detail of your work history and background.

“It’s tough as it is getting enough workers to the site but things like this put people off.

“A lot of people hear about the delays and just go off to another job.”

EDF said:“The Government requires people working on nuclear sites to undergo security vetting.

“We’ve heard feedback from our contractors that the process is taking too long and we have been working with the regulator, the Office for Nuclear Regulation to address the issue.

“We have introduced a new level of access in August. For some groups of workers this is reducing the time needed to get clearance to just 24 hours. They will also undergo appropriate site inductions.”

Caroline Blackman, HR director for civils contractor Bouygues Laing O’Rourke said : “This new type of access has transformed the way our workers get onto site and means that you can be at work within days of getting a job rather than weeks.

“It’s a great example of how complex processes can be simplified without compromising standards.”

Latest news

Graham takes on ISG £45m Coventry cultural hub job

Firm will start conversion work in the Spring on former IKEA store
41 minutes ago

Alun Griffiths to “restructure and resize” after £95m loss

Redundancies due to be announced at Welsh civils contractor
24 hours ago

Fire safety project approval delays hit Van Elle profits

Piling specialist also reviews future of Canadian operation amid fresh economic uncertainty
7 hours ago

JRL Malaysian backers plan £150m London city office refurb

Ardmore set to deliver landmark 25 Finsbury Circus building overhaul
7 hours ago

500-home block to replace 19 storey Sutton office tower

Landmark project to deliver 312 Build to rent and 195 co-living homes
8 hours ago

Building envelope specialist Bailey buys Comar

Specialist now offers complete building envelope solutions
7 hours ago

Subcontractors wanted for work across Wales

Big name buyers at latest Constructionline event: Register now
7 hours ago

Balfour Beatty profit dented by £83m building safety hit

Increased order book at £18bn secures growth over next two years
1 day ago

Expanding utilities specialist Ipsum buys Matrix Power

Power engineering contractor takeover will strengthen offer in North East
1 day ago

Historic scaffolding firm files administration notice

Hertfordshire based Rodells has been trading since 1898
1 day ago

Planning Bill to have “seismic” impact on construction

Building-boosting reforms go before Parliament
2 days ago

Briggs & Forrester hits record revenue and orders

M&E specialist rebounds with strong growth across three divisions
1 day ago

Man Utd confirm plan for £2bn ‘super-tent’ stadium

Club to press ahead with 100,000-seat 'Wembley of the North'
2 days ago

Government spending keeps profits edging-up at Kier

91% of work now with public sector and regulated companies
2 days ago

Costain on track for step change to 5% margin

Alex Vaughan says order book has jumped £1.5bn to £5.4bn
2 days ago

Mace tops February contracts league

Confirmation of £300m London Victoria Street project lifts firm to pole position
2 days ago

Wates raids Laing O’Rourke for new construction operations chief

George Mosey leaves Laing O'Rourke after 16 years
3 days ago

Travis Perkins CEO Pete Redfern steps down due to ill health

Redfern joined builders' merchant last year after 14 years at Taylor Wimpey
3 days ago

Morgan Sindall wins £61m Liverpool lab scheme

Construction to start this Autumn on latest Knowledge Quarter project
2 days ago

Glencar to build timber-framed office block

Work to start next month on 79,200 sq ft scheme in Maidenhead
3 days ago

Shed specialist Marbank files administration notice

£67m turnover portal-framed building specialist files court notice
3 days ago

Birmingham council submits £1bn Druids Heath plan

High rise estate to be replaced by-3,500 home eco village
3 days ago

Cannabis farm gang posed as utilities contractor

Gang jailed for 28 years after diverting power to more than 100 cannabis farms
6 days ago

Firm fined after workers climb scaffold without ladder

HSE investigation prompted by death on Liverpool site
3 days ago

Clancy renews £250m Southern Water deal

Contractor vows to maximise value for money and minimise disruption
3 days ago

McLaren go-ahead for 314 flats Watford scheme

Police station and magistrates court to be demolished
4 days ago

Former Liverpool mayor charged in building contracts probe

Construction bosses also charged as part of Operation Aloft
6 days ago

Bidding to start for £700m Irish sea interconnector work

Work includes converter stations at Hunterston and Kilroot near Belfast
6 days ago

Muse to redevelop Durham County Hall HQ site

Morgan Sindall regen specialist seals another major development deal
6 days ago

Mace to transform Imperial College Great Hall

Work to start next month on ambitious refit
6 days ago

Contractor services