Don bridge hitches delay Aberdeen bypass opening

Aaron Morby 6 years ago
Share

Scotland’s transport secretary has revealed that the opening of the Aberdeen Western Peripheral Route has been pushed back to at least December.

The already delayed scheme was expected to finally open this autumn but further problems with the River Don crossing involving concrete cladding panels have pushed it back.

The £745m road scheme has already been beset with  delays due to weather, technical problems and the collapse of contractor Carillion.

This saw the opening in the spring put back to autumn.

Transport secretary Michael Matheson told MSPs that engineers were now targeting a December opening, but that no firm date could be given.

He said that problems revealed in May at Balfour Beatty’s new Don crossing section of the scheme were more “extensive” than initially believed.

Matheson has now urged the AWPR contractor to ‘stop deliberating and start acting’ and requested an urgent meeting with the contractors’ board members to seek clarity on the timescales for opening the remaining sections of the AWPR.

He also revealed frustration that talks with Galliford Try to open the Craibstone to Stonehaven and Charleston section, which required a variation to the contract, have not progressed as hoped.

“Earlier this week, I spoke with Peter Truscott, chief executive of Galliford Try,  to receive an update on the progress they were making in discussing this variation with their lenders.

“Despite assurances that they were doing everything possible to open the road at the earliest opportunity, as well as a clear indication from Mr Truscott that they were making the necessary changes to the AWPR contract to open the 31.5km section, I was then disappointed to receive a letter from him which contradicted our discussion.

“It is this kind of inconsistency which is frustrating efforts to progress the opening of this new section. As recently as 12th September, Galliford Try issued a statement to markets to say the AWPR was on target to open in late Autumn 2018 and we had no reason to doubt that assessment.

“I have been urging the contractor to conclude its deliberations for some time. I repeated this to him on Monday and reiterated it again today in writing, It is now time for the contractor to stop deliberating and start acting. It now has to take the necessary steps to open the majority of this road and let the people of the North East enjoy the benefits they have been so patiently anticipating.

“I have therefore asked for unequivocal confirmation that the agreement is being progressed and when it will be concluded.”

 

Latest news

Berkeley’s £600m Borough Triangle project approved

Controversial scheme features two towers of 38 and 44-storeys
11 hours ago

HG to build 500-bed London Stratford student scheme

Work will start later this year subject to gateway 2 safety approval
11 hours ago

New rail property company to unlock land for 40,000 homes

First four sites released in Newcastle, Cambridge, Manchester, and Nottingham
20 hours ago

British Steel threatens closure of Scunthorpe blast furnaces

Chinese owners say sectional steel and rail supplies will be maintained
14 hours ago

Drainage specialist Subscan files administration notice

Specialist employing 131 people files court notice
20 hours ago

Four win Network Rail £300m engineering design deal

Eastern region deal will include design for Northern Powerhouse Rail
19 hours ago

Funding go-ahead for Banwell bypass after fresh cost hike

Galliford Try contract rises £14m to £64m after final design change
1 day ago

Graham wins Southport £75m Marine Lakes Centre

Firm replaces Kier which parted ways with backer Sefton Council
1 day ago

Chancellor unveils extra £2bn capital spend a year

Construction promised a defence dividend in military base and homes upgrade work
2 days ago

McLaren confirms subcontractor team on £135m warehouse job

Work starts on TN2 Gateway site in Kent.
2 days ago

Vistry profits slump after site costs reporting debacle

House builder launches internal whistle-blowing service in business culture review
2 days ago

Severfield chief to step down

Alan Dunsmore to leave structural steel group by end of June
2 days ago

Funding hurdle remains as Lower Thames Crossing gains consent

Government claims £9bn project may start in 2026 as private finance options explored
3 days ago

Mace wins £600m Euston Tower overhaul

1970s tower's foundations and core to be retained as floor plates extended
2 days ago

Summer start for main works on London green tower

Axa sanctions start at 50 Fenchurch Street 36-storey office block
2 days ago

Japan’s leading flats builder JVs with L&G for UK push

Partners plan to build over 1,000 rental homes in London
2 days ago

Wates submits plan for 1,000 homes Harrow council scheme

Former civic centre Poets' Corner site kicks off housing partnership
2 days ago

Morgan Sindall upgrades forecast for next 12 months

Overbury fit-out arm gets off to a flying start in 2025
3 days ago

Restructure underway at Henry Boot Construction

New management team restructures business after drop in turnover
3 days ago

Government pledges £2bn stop-gap funding for 18,000 homes

Funding avoids cliff-edge in social housing delivery before new grant programme agreed
3 days ago

Just two major new roads schemes to start this year

National Highways sets out one-year interim spending plan after RIS3 delay
3 days ago

Plans go in for £400m GRAHAM Manchester site

Demolition and enabling works underway with main construction set to start next year
3 days ago

Building safety levy rate set at up to £10,000 a home in London

Levy introduction pushed back a year to Autumn 2026 - list of new rates
4 days ago

BAM wins £100m revamp of Broadgate Tower in London

Front of tower 3-storey extension to use cross laminate time and re-used steel
4 days ago

£600m funding to train 60,000 construction workers

Government pledges massive cash injection to produce "site-ready" workers
5 days ago

Construction to start in May on £1bn port expansion

Work at London Gateway site will last four years
7 days ago

Utilities specialist Ipsum buys second power contractor

Acquisition of Wootton & Wootton strengthens service in Midlands and Wales
4 days ago

Councils will lose cash if they fail to fix potholes

Local authorities will have to publish road repair stats
4 days ago

Green light for London Euston Tower rebuild

British Land says nearly a third of original tower will be retained
7 days ago

Contractors struggling to keep-up with demand for data centres

More than half of clients fear supply chain will struggle
7 days ago

Contractor services