Super sewer contingency budget raided due to cost pressure

Aaron Morby 6 years ago
Share

Thames Tideway is rolling out a cost-saving plan after having to raid much of the project contingency budget even before tunnelling has started.

First of eight TBM's started central section drive last week amid concern about soaring costs in preparation works
First of eight TBM's started central section drive last week amid concern about soaring costs in preparation works

A catalogue of engineering challenges during cofferdam and shaft construction has left the project team looking for major cost-savings.

The project’s holding company, Bazalgette Holdings Group, confirmed the total project spend so far has reached £1.48bn amid unforeseen cost pressures early on in the project.

Now contractors are being pressed to find savings and raise productivity as a value engineering exercise is undertaken and overheads are cut.

The 25km tunnel is due to be completed by 2023 at a cost £4.2bn and Tideway said it was confident the project would be completed on time and to budget.

Cost pressures were revealed as former Crossrail finance boss Mathew Duncan joined the project last week as new finance director replacing Mark Corben, whose intention to stand down was announced last year.

Key sites facing engineering challenges are at Blackfriars, where two large Victorian gas mains have caused problems, cofferdam construction at King Edward Memorial Park and Albert Embankment and shafts at east area sites.

In a statement just after the first tunnelling started last week, the firm said: “Following significant progress on the project and now having mobilised on 20 of our 21 sites, Tideway has identified several cost pressures in the programme.

“Taken together with general cost pressure across the programme this has substantially eroded available contingency.

“To mitigate the cost pressures Tideway has begun to implement cost-saving measures in partnership with our contractors and remains focussed on achieving the baseline target.

“These cost-saving measures include working with our contractors to eliminate overlap, taking measures to increase productivity, undertaking value engineering and delivering overhead savings.

“It is too early to conclude the extent to which these measures will mitigate the cost pressures, and an update will be provided on these and the cost savings programme in Tideway’s annual report and accounts next March.”

A spokeswoman for Tideway added: “There have been a number of complex engineering challenges and risks to overcome in the early stages of the project.

“With these behind us and having put in place several measures to reduce cost, our budget is intact. Tunnelling for the project started last week from our site in Battersea and we are set to complete the project on schedule and to budget.”

Latest news

Galliford Try gets go-ahead for Milton Keynes PRS tower

33-storey tower needs gateway 2 approval before work can start
6 minutes ago

Breyer Group battles for survival as rivals circle

Housing maintenance firm fights three winding up petitions in a month
6 hours ago

Careys facing £2.4m claim by developer over demolition cartel

Giant Hong Kong developer claims it was overcharged on Lots Road Power Station job
6 hours ago

Lendlease Construction renamed Bovis

US private equity firm completes £35m purchase of UK contracting business and rebrands
5 hours ago

Multiplex profit drops a third as revenue rises to £780m

Spate of new orders sets contractor up for three years of work
5 hours ago

Galliford Try and Breheny land latest Sizewell C road deals

More infrastructure deals for new nuclear power station
22 hours ago

Worker trapped in collapsed septic tank pit

Contractor and director fined after worker suffers multiple fractures
6 hours ago

Homes England buys stalled Broad Marsh site

Demolition to finally be completed as developer hunt begins
18 hours ago

Vistry go-ahead for 353 homes at Rochester Riverside

Work to start on next phase of Kent town regeneration at end of this year
1 day ago

M&E firm J S Wright collapsed owing £19m

Trade creditors hit for £11.4m by employee-owned Midlands firm
1 day ago

Right to work checks to be extended to self-employed

Government plans crackdown on illegal working and rogue employers
1 day ago

Midlands developer turns to London with £1bn resi schemes trio

SevenCapital plans 1,000 flats in Kensington, Islington and the Isle of Dogs projects
1 day ago

Deck falls off huge scissor lift at Winvic site

Two men seriously injured as platform plunges to the ground
4 days ago

Weston targets Build to Rent with new division

Weston Partnerships signs first deals with asset managers and councils
1 day ago

Bouygues seals deal for £119m Cardiff college campus

Construction to start in June on two new buildings
4 days ago

£140m cash injection to speed-up flood defence schemes

Funding part of £2.65bn investment over the next two years
1 day ago

Bid race starts for £15bn schools framework refresh

DfE throws framework open to more contractors
4 days ago

Berkeley’s £600m Borough Triangle project approved

Controversial scheme features two towers of 38 and 44-storeys
5 days ago

London Mayor calls in blocked 600-bed student scheme

Refused 20-storey London PBSA block may still be built
4 days ago

HG to build 500-bed London Stratford student scheme

Work will start later this year subject to gateway 2 safety approval
5 days ago

Arrest after pedestrian death on construction site

Tragedy during site preparation works for new Wigan car park
4 days ago

British Steel threatens closure of Scunthorpe blast furnaces

Chinese owners say sectional steel and rail supplies will be maintained
5 days ago

Planning green light for Sheffield warehouse site

Existing factories to be demolished in new scheme for Rula Developments
4 days ago

New rail property company to unlock land for 40,000 homes

First four sites released in Newcastle, Cambridge, Manchester, and Nottingham
5 days ago

Drainage specialist Subscan files administration notice

Specialist employing 131 people files court notice
5 days ago

Four win Network Rail £300m engineering design deal

Eastern region deal will include design for Northern Powerhouse Rail
5 days ago

Funding go-ahead for Banwell bypass after fresh cost hike

Galliford Try contract rises £14m to £64m after final design change
6 days ago

Graham wins Southport £75m Marine Lakes Centre

Firm replaces Kier which parted ways with backer Sefton Council
6 days ago

Chancellor unveils extra £2bn capital spend a year

Construction promised a defence dividend in military base and homes upgrade work
6 days ago

McLaren confirms subcontractor team on £135m warehouse job

Work starts on TN2 Gateway site in Kent.
6 days ago

Contractor services