Super sewer contingency budget raided due to cost pressure

Aaron Morby 6 years ago
Share

Thames Tideway is rolling out a cost-saving plan after having to raid much of the project contingency budget even before tunnelling has started.

First of eight TBM's started central section drive last week amid concern about soaring costs in preparation works
First of eight TBM's started central section drive last week amid concern about soaring costs in preparation works

A catalogue of engineering challenges during cofferdam and shaft construction has left the project team looking for major cost-savings.

The project’s holding company, Bazalgette Holdings Group, confirmed the total project spend so far has reached £1.48bn amid unforeseen cost pressures early on in the project.

Now contractors are being pressed to find savings and raise productivity as a value engineering exercise is undertaken and overheads are cut.

The 25km tunnel is due to be completed by 2023 at a cost £4.2bn and Tideway said it was confident the project would be completed on time and to budget.

Cost pressures were revealed as former Crossrail finance boss Mathew Duncan joined the project last week as new finance director replacing Mark Corben, whose intention to stand down was announced last year.

Key sites facing engineering challenges are at Blackfriars, where two large Victorian gas mains have caused problems, cofferdam construction at King Edward Memorial Park and Albert Embankment and shafts at east area sites.

In a statement just after the first tunnelling started last week, the firm said: “Following significant progress on the project and now having mobilised on 20 of our 21 sites, Tideway has identified several cost pressures in the programme.

“Taken together with general cost pressure across the programme this has substantially eroded available contingency.

“To mitigate the cost pressures Tideway has begun to implement cost-saving measures in partnership with our contractors and remains focussed on achieving the baseline target.

“These cost-saving measures include working with our contractors to eliminate overlap, taking measures to increase productivity, undertaking value engineering and delivering overhead savings.

“It is too early to conclude the extent to which these measures will mitigate the cost pressures, and an update will be provided on these and the cost savings programme in Tideway’s annual report and accounts next March.”

A spokeswoman for Tideway added: “There have been a number of complex engineering challenges and risks to overcome in the early stages of the project.

“With these behind us and having put in place several measures to reduce cost, our budget is intact. Tunnelling for the project started last week from our site in Battersea and we are set to complete the project on schedule and to budget.”

Latest news

Didcot demolition disaster probe enters tenth year

Thames Valley Police "moving towards the latter stages of enquiries"
12 hours ago

Administrators take control at Acheson Construction

40 staff made redundant at South West regional contractor
3 days ago

34 secure spots on £1bn NEPO civils framework

Balfour Beatty, Graham, Taylor Woodrow and Winvic signed up for first time
3 days ago

Bouygues claims net zero construction goal at Welsh project

Llanelli leisure centre and health campus achieves green construction target
3 days ago

Manchester civil service digital campus approved

Two Government office blocks totaling 900,000sq ft to cost £310m to build
3 days ago

New mobile charging vans crack electric plant downtime anxiety

FM Conway trials new service that recharges small plant in one hour
3 days ago

Build to rent deal kick starts 3,500-home Dagenham scheme

Deal secures 935-home first phase of Ford Dagenham plant redevelopment
3 days ago

RSK adds another 110 staff with N-Able Group deal

Consultant and construction services group makes latest acquisition
3 days ago

JRL Malaysian backers plan 580-home Wheat Quarter scheme

Plans in for Welwyn Garden City Shredded Wheat factory redevelopment
4 days ago

Recycled aggregate firms blast new waste crime levy

10% levy on all recycled aggregate producers to fund policing waste crime
4 days ago

£110m Liverpool Metalworks resi scheme gets nod

Legacie Contracts tipped for 16-storey Pumpfields project
4 days ago

Building products firm fined £1m after double accident

Scaffolder hurt in fall and worker caught in machinery at Norbord factory
4 days ago

Graham lands £42m Woking road upgrade

A320 upgrade will unlock new housing schemes along route
4 days ago

Dandara 300 homes High Wycombe project approved

Firm to demolish Chilterns Shopping Centre for build to rent job
4 days ago

Three Keltbray managers took £600,000 in bribes

Site managers convicted for taking kickbacks from labour supply specialist
5 days ago

Bidding starts for £1bn YORcivil major works deal

Eight firms face fight to renew places on big civils framework
5 days ago

ECF clinches deal for Hull 850-home urban village

East Bank waterside village plan advances
5 days ago

Maintenance firm Cardo in second Scottish acquisition

North Lanarkshire property maintenance firm Rodgers & Johnston bought
5 days ago

Kier confirms £41m Salford Uni health building job

Work starts on specialist three storey teaching building
5 days ago

Passenger train derailed after hitting track left by Colas workers

Contractor and Network Rail asked to make improvements after accident
5 days ago

Bryson signs £6m safety products deal with Skanska

Safety specialist becomes sole supplier to contracting giant
5 days ago

Murphy wins St Fergus gas compressor project

Three low emission compressor units to be installed for National Gas
5 days ago

Blenheim House payout hopes fade as claims hit £33m

Suggested 10p in the £1 payout for subcontractors now unlikely
6 days ago

£1.3bn decarbonising and fire safety deals out for bid

South East Consortium starts hunt for firms for housing upgrade work prize
6 days ago

£30m turnover M&E contractor files administration notice

TNA Electrical makes administration application
6 days ago

Plan for first big offices at £1.7bn Manchester innovation hub

500,000 sq ft of offices planned at renamed Sister development
6 days ago

Murphy starts work on £2.5bn Eastern Green Link 1

Giant subsea electricity cable project will take three years to build
6 days ago

Subcontractors wanted for work across Birmingham

Latest Constructionline event: Register now
6 days ago

Acheson Construction files administration notice

£53m turnover South West contractor lodges court notice
7 days ago

Hunt for 10 firms to deliver £37bn new hospital plan

Race starts for mega-framework with pledge to spread work among all firms
7 days ago

Contractor services