Super sewer contingency budget raided due to cost pressure

Aaron Morby 6 years ago
Share

Thames Tideway is rolling out a cost-saving plan after having to raid much of the project contingency budget even before tunnelling has started.

First of eight TBM's started central section drive last week amid concern about soaring costs in preparation works
First of eight TBM's started central section drive last week amid concern about soaring costs in preparation works

A catalogue of engineering challenges during cofferdam and shaft construction has left the project team looking for major cost-savings.

The project’s holding company, Bazalgette Holdings Group, confirmed the total project spend so far has reached £1.48bn amid unforeseen cost pressures early on in the project.

Now contractors are being pressed to find savings and raise productivity as a value engineering exercise is undertaken and overheads are cut.

The 25km tunnel is due to be completed by 2023 at a cost £4.2bn and Tideway said it was confident the project would be completed on time and to budget.

Cost pressures were revealed as former Crossrail finance boss Mathew Duncan joined the project last week as new finance director replacing Mark Corben, whose intention to stand down was announced last year.

Key sites facing engineering challenges are at Blackfriars, where two large Victorian gas mains have caused problems, cofferdam construction at King Edward Memorial Park and Albert Embankment and shafts at east area sites.

In a statement just after the first tunnelling started last week, the firm said: “Following significant progress on the project and now having mobilised on 20 of our 21 sites, Tideway has identified several cost pressures in the programme.

“Taken together with general cost pressure across the programme this has substantially eroded available contingency.

“To mitigate the cost pressures Tideway has begun to implement cost-saving measures in partnership with our contractors and remains focussed on achieving the baseline target.

“These cost-saving measures include working with our contractors to eliminate overlap, taking measures to increase productivity, undertaking value engineering and delivering overhead savings.

“It is too early to conclude the extent to which these measures will mitigate the cost pressures, and an update will be provided on these and the cost savings programme in Tideway’s annual report and accounts next March.”

A spokeswoman for Tideway added: “There have been a number of complex engineering challenges and risks to overcome in the early stages of the project.

“With these behind us and having put in place several measures to reduce cost, our budget is intact. Tunnelling for the project started last week from our site in Battersea and we are set to complete the project on schedule and to budget.”

Latest news

Site labour rates hit record high as cost inflation returns

Industry's biggest payroll firm says rates rose nearly 5% last month in London
18 hours ago

Morris & Spottiswood acquires part of ISG fit-out division

ISG Cathedral acquisition saves 111 jobs and expands presence across England
1 day ago

New work drives Q3 construction output uplift

Third quarter activity up 0.8% despite slowdown in September
17 hours ago

Octavius cuts concrete formwork strike time by 5 days

Temperature probes reduce times for safely striking formwork
17 hours ago

Plan for 200-home student-led London scheme

Developer Regal is behind new Camden Town scheme
19 hours ago

Green light for new £45m tax office in Portsmouth

HMRC to occupy new office complex with construction starting next year
17 hours ago

Extra tunnels included in £6bn East West Rail scheme

Government unveils plans for two new tunnels in Cambridgeshire
2 days ago

Infrastructure to get £80bn boost from public sector pensions

New "megafunds" will invest in UK construction projects
2 days ago

Bidders wanted for £800m building safety framework

Fusion21 launches renewal of deal across 12 lots
2 days ago

Winchmore wins £6.5m brickwork package on Stratford flats

Latest award from Graham on £69m development
2 days ago

Motts/Jacobs JV to design £2.5bn West Yorkshire Mass Transit

First construction could begin in 2028
2 days ago

Muse signs landmark deal to redevelop Solihull shopping centre

Mell Square scheme includes 1,600 homes at 6.4ha town centre site
3 days ago

Reds10 raids house builders for two director hires

David Newey and James Bateman join as regional ops directors
3 days ago

Builder killed as telehandler overturns

House builder goes into liquidation before court hearing and £160,000 fine
3 days ago

Balfour Beatty regional MD steps down

Lindsay McGibbon is understood to be exiting for a job in the United States
3 days ago

Firms put on alert for £1.5bn decarbonisation framework

Fusion21 aims to invite bids in January for housing and public buildings retrofit framework
3 days ago

Morgan Sindall aboard for £22m London station roof renewal

Passengers will continue to use Liverpool Street Station while roof works take place above
3 days ago

Utilities contractor turns to Africa for skilled workers

IES Utilities Group recruits its 100th overhead linesman from South Africa and Zimbabwe
3 days ago

McLaren boosts building safety and refurb team

Paul Woodhams promoted to newly created MD role at expanding division
4 days ago

Firms fight to renew places on £450m JV North deal

17 firms face fight to retain places on north west housing consortium list
4 days ago

Subbies get £7m lifeline on ISG Cardiff schools site

Council strikes deal with administrators and appoints emergency interim contractor
4 days ago

United Utilities names water and waste water design consultants

AtkinsRéalis, Jacobs, Stantec, Binnies, Mott MacDonald, RPS, and WSP make line-up
4 days ago

Crown Estate in £1.5bn Cambridge Business Park revamp plan

A phased programme of construction will start in 2026
4 days ago

McLaughlin & Harvey returns to profit

Contractor back in the black and looking forward to another positive year
4 days ago

Graham wins £69m London Stratford flats job

Stratford Mill project will deliver nearly 250 flats
4 days ago

Mace to complete construction of ISG neuroscience centre

Contractor to work with UCL to finish stalled job
5 days ago

BAM finally breaks ground at £60m-plus Yeovil College

Agreed contract price 50% above original estimate on delayed Somerset college job
4 days ago

Forterra trying to pass on NI cost increases

Brick and block giant writing to customers about 2025 price rises
5 days ago

Refurb contractor Troy Central goes into administration

Suffolk based hotel and leisure specialist had a £38m turnover
5 days ago

Former ISG director joins Wates as regional construction MD

Wayne Flannery joins Wates construction board after nearly 20 years at ISG
5 days ago

Contractor services