Half-way point for UK’s biggest road upgrade scheme

Grant Prior 6 years ago
Share

The £1.5bn project to upgrade 21 miles of the A14 between Cambridge and Huntingdon has reached the half-way point.

Some of the team take time-out to celebrate the halfway milestone
Some of the team take time-out to celebrate the halfway milestone

Construction started on Monday 28 November 2016 and is on target to be completed by December 2020.

Since work started, more than eight million working hours have gone into the project, and eight million cubic metres of earthworks have been moved across the site – equivalent to more than three Great Pyramids of Giza.

Nine new bridges will have opened to traffic by the end of the year and construction is well under way on 25 more.

Project Director for the A14 Cambridge to Huntingdon improvement scheme David Bray said: “Our amazing team has been working incredibly hard to deliver this upgraded A14, and most days we have up to 2,700 staff working across more than 20 miles to build the new roads and bridges that are needed.

“Working on this epic project has been remarkable so far: from seeing the new road emerge as we moved earth into place for its foundations, to the wide array of bridges and structures being built, the fantastic discoveries of our archaeological team and the industry-leading work our environmental team is carrying out.

“We know drivers can be frustrated by roadworks, particularly when they’re in place for a long time, but we’re delighted to announce at this two-year anniversary that we’re on time and on budget.”

Main contractor Balfour Beatty/Costain/Skanska won the Best Civils Project to Work on at this year’s Construction Enquirer Awards.

Latest news

Luxury house builder goes under with 70 job losses

Octagon Developments in administration after 40 years in business
4 hours ago

Top Ten best read stories of 2024

The biggest headlines of an eventful year. Have a good one and here's to a successful 2025
10 hours ago

BAM Nuttall fined £800,000 after concrete skip tragedy

Young labourer killed by falling bale arm
1 day ago

Keltbray infrastructure business reveals new name

AUREOS means "new dawn" after private equity acquisition
9 hours ago

Stiffer fines for over-running street works from next Summer

Cash raised from lane rentals to be channeled into pothole repairs
9 hours ago

£113m Basildon rental homes scheme seals build finance

Work expected to start early next year on Market Square project
10 hours ago

Notting Hill Genesis seeks more tier 1 repairs contractors

London housing trust seeks eight firms for new £1.5bn repairs framework
10 hours ago

Reclaimed steel oil rig columns worked into London office revamp

Curo will use reclaimed bricks and steel for Fitzrovia office overhaul
1 day ago

CITB delays levy approval consultation

Levy agreement talks pushed back by ongoing review into effectiveness of training body
1 day ago

Ofwat approves £104bn water industry spending plan

Household water bills to rise by 36% to fund quadrupling of investment
1 day ago

Costain/ Siemens JV clinches HS2 power supply job

£300m deal for HV power supply systems over the 225km route
1 day ago

Demolition team assembles on Multiplex London Wall site

Erith to start work next month at Deutsche Bank's former headquarters
2 days ago

Norwich Council acts to revive £300m Anglia Square scheme

Council uses Homes England funding to buy stalled site with planning for 1,100 homes
1 day ago

Go-ahead for 4,500-home Cambridgeshire new town

Waterbeach new town plan stalled three years ago after an Environment Agency objection
1 day ago

Henry Boot to take total control of Stonebridge Homes

Deal worth at least £30m
1 day ago

HS2 costs could hit £66bn

Government looking for next estimate to be lower
2 days ago

Mace to close construction logistics arm

Specialist business being wound down
2 days ago

National Grid to invest £35bn over next five years

Plan set out for record investment in electricity transmission infrastructure
2 days ago

Profits double at Barhale

Civils specialist sees order book top £1bn
2 days ago

Balfour wins 68km HV underground power cable deal

Main works to start next year on Eastern Green Link 2 job
2 days ago

Stunning site wrap unveiled on Sloane Street

Hoarding creates illusion of fully formed façade on £53m Galliford Try job
2 days ago

Heathrow Airport upgrade spend takes off again

Airport operator will spend £2.3bn over the next two years
2 days ago

Government buys back over 36,000 military homes

Public ownership deal to release wave of upgrade and new build work
3 days ago

Story Contracting staff braced for rail job losses

Work coming through slower than expected from Network Rail
3 days ago

Ballymore submits two plans for 3,700 East London homes

Construction could start in 2025 on Thames Road and Knights Road schemes
3 days ago

Blackpool council steps in on failed developer’s £300m scheme

Blackpool Central site clearance to start in the New Year as hunt starts for new developer
4 days ago

Brookfield submits retro-first London office plan

Milton Gate plan for Square Mile will hike space by nearly 50%
3 days ago

Bowmer + Kirkland gets start date for £100m Siemens site

Construction to begin early next year on Chippenham scheme
4 days ago

Torsion sells under-construction Leeds BTR scheme

Concrete frame due to start soon on 300-apartment complex
4 days ago

Go-ahead for City of London’s tallest tower

1 Undershaft building will equal the Shard in height
1 week ago

Contractor services