Specialists sound alarm on onerous contract clauses

Aaron Morby 6 years ago
Share

Specialists are seeing a sharp rise in the use of onerous contract clauses being introduced by main contractors.

The proliferation in the use of bespoke contracts that often purport to be standard forms is creating a minefield for unsuspecting subcontractors.

Specialists now claim that most tier one contractors have shifted away from standard forms, as they seek to shift risk on projects with paper-thin margins.

A spokesman for the British Constructional Steelwork Association, said: “We have contracts that contain more additional clauses than there are clauses in the standard version.

“While everyone accepts that there are risks in contracting this sort of behaviour is beyond risk management and verges on blatant abuse of power.”

Another subcontractor told the Enquirer: “I was presented with a standard JCT the other day that should have been around 76 pages but ran to 177 pages.

“Some firms don’t realise it but they can be agreeing to unlimited liability, or agreeing terms that PI insurers will not pay out on.”

The rise in non-standard forms has prompted the BCSA to highlight clauses now slipping into common use that are leaving firms seriously exposed.

A working party set up by the association has revised its ‘Construction Contractual Handbook’ to spotlight common contractual traps.

The latest edition is now being offered to all subcontractors as well as the wider industry community of developers, employers, contractors, consultants, surveyors and insurers.

Red flag clauses

Subcontractor to coordinate all other subcontractors trades

Example of wording: “The subcontractor shall be responsible for co-ordinating the subcontract works with the works of the main contractor, its agents and subcontractors and any other parties on the site. Such co-ordination shall include but not necessarily be limited to design (where applicable), programming, sequencing of works, checking of levels/setting out/dimensions/adequacy of preceding works, installation of health and safety.

Risk
The risk of co-ordinating the works (and checking works carried out by others) is being passed down to the subcontractor, where this should stay firmly with the main contractor.

Ground Conditions clause

“The subcontractor accepts that it has had an opportunity to inspect the physical and other conditions (including the sub-surface conditions) of or affecting the site. Any adverse ground conditions or artificial obstructions encountered during the execution of the subcontract works shall be the sole responsibility of the subcontractor and there shall be no addition to the subcontract sum nor any extension of time nor any loss or expense claim granted.”

Another also used (sent by readers)

“The Subcontractor shall not and shall not be entitled to rely upon any survey, report or other document prepared by or on behalf of the contractor and the contractor makes no representation or warranty as to the accuracy or completeness of any such survey, report or document.”

Risk
The clause puts the risk of discovering anything which would impede progress or mean that additional expense has to be incurred firmly at the subcontractor’s door.

Pay when paid clause

“The Contractor shall not be liable to make any payment to the subcontractor in respect of any work executed or materials supplied or any other provision entitling the subcontractor to payment (including for the avoidance of doubt retention withheld) for which the contractor has not received payment under the main contract.

Risk

Effectively a ‘pay when paid’ where the subcontractor has to credit risk the client and the main contractor.

Fitness for purpose clause

In bespoke contracts, often the actual words “fit for purpose” may be used. Be aware also of other wording which implies fitness for purpose, such as “meeting the performance specifications set out in the contractor’s requirements”. Under NEC3 and NEC4 contracts, fitness for purpose for design is the default position unless option X15 is selected (reasonable skill and care). In JCT2016 D&B Subcontract, Clause 2.13.1 restricts design liability to that of an architect or other appropriate professional designer (which will be “reasonable skill and care” but this is sometimes deleted.

Risk
Designing something which is fit for purpose is a more onerous duty than using reasonable skill and care to do so. It is often not covered by PI insurers, and they sometimes specifically require that you do not accept any fitness for purpose obligations.

Subcontractor payment clawback clause if employer fails (sent by readers)

In the event that the contractor had previously made payment to the subcontractor for work or matters that the contractor has an entitlement under the main contract for payment from the employer… and by reason of the insolvency of the employer, the contractor had not received, the subcontractor shall refund the contractor to the extent the contractor has paid the subcontractor.

Risk

You lose all payment!

Latest news

Staff stunned as engineering consultancy Clarkebond closes

Firm was only bought three months ago by rival Independent Design House Group
5 days ago

Vistry issues third profit warning in three months

Profit expected to fall £50m below forecast due to delayed completions
5 days ago

Miller Homes buys St Modwen Homes for £215m

Scottish house builder snaps up £368m turnover rival
1 week ago

Keltbray fine increased to £18m after failed bid rigging appeal

Contractor loses penalty discount for settling with competition authorities
1 week ago

Luxury house builder goes under with 70 job losses

Octagon Developments in administration after 40 years in business
1 week ago

Top Ten best read stories of 2024

The biggest headlines of an eventful year. Have a good one and here's to a successful 2025
1 week ago

BAM Nuttall fined £800,000 after concrete skip tragedy

Young labourer killed by falling bale arm
1 week ago

Keltbray infrastructure business reveals new name

AUREOS means "new dawn" after private equity acquisition
1 week ago

Stiffer fines for over-running street works from next Summer

Cash raised from lane rentals to be channeled into pothole repairs
1 week ago

£113m Basildon rental homes scheme seals build finance

Work expected to start early next year on Market Square project
1 week ago

Notting Hill Genesis seeks more tier 1 repairs contractors

London housing trust seeks eight firms for new £1.5bn repairs framework
1 week ago

Reclaimed steel oil rig columns worked into London office revamp

Curo will use reclaimed bricks and steel for Fitzrovia office overhaul
1 week ago

CITB delays levy approval consultation

Levy agreement talks pushed back by ongoing review into effectiveness of training body
1 week ago

Ofwat approves £104bn water industry spending plan

Household water bills to rise by 36% to fund quadrupling of investment
1 week ago

Costain/ Siemens JV clinches HS2 power supply job

£300m deal for HV power supply systems over the 225km route
1 week ago

Demolition team assembles on Multiplex London Wall site

Erith to start work next month at Deutsche Bank's former headquarters
2 weeks ago

Norwich Council acts to revive £300m Anglia Square scheme

Council uses Homes England funding to buy stalled site with planning for 1,100 homes
1 week ago

Go-ahead for 4,500-home Cambridgeshire new town

Waterbeach new town plan stalled three years ago after an Environment Agency objection
1 week ago

Henry Boot to take total control of Stonebridge Homes

Deal worth at least £30m
1 week ago

HS2 costs could hit £66bn

Government looking for next estimate to be lower
2 weeks ago

Mace to close construction logistics arm

Specialist business being wound down
2 weeks ago

National Grid to invest £35bn over next five years

Plan set out for record investment in electricity transmission infrastructure
2 weeks ago

Profits double at Barhale

Civils specialist sees order book top £1bn
2 weeks ago

Balfour wins 68km HV underground power cable deal

Main works to start next year on Eastern Green Link 2 job
2 weeks ago

Stunning site wrap unveiled on Sloane Street

Hoarding creates illusion of fully formed façade on £53m Galliford Try job
2 weeks ago

Heathrow Airport upgrade spend takes off again

Airport operator will spend £2.3bn over the next two years
2 weeks ago

Government buys back over 36,000 military homes

Public ownership deal to release wave of upgrade and new build work
2 weeks ago

Story Contracting staff braced for rail job losses

Work coming through slower than expected from Network Rail
2 weeks ago

Ballymore submits two plans for 3,700 East London homes

Construction could start in 2025 on Thames Road and Knights Road schemes
2 weeks ago

Blackpool council steps in on failed developer’s £300m scheme

Blackpool Central site clearance to start in the New Year as hunt starts for new developer
2 weeks ago

Contractor services