Specialists sound alarm on onerous contract clauses

Aaron Morby 6 years ago
Share

Specialists are seeing a sharp rise in the use of onerous contract clauses being introduced by main contractors.

The proliferation in the use of bespoke contracts that often purport to be standard forms is creating a minefield for unsuspecting subcontractors.

Specialists now claim that most tier one contractors have shifted away from standard forms, as they seek to shift risk on projects with paper-thin margins.

A spokesman for the British Constructional Steelwork Association, said: “We have contracts that contain more additional clauses than there are clauses in the standard version.

“While everyone accepts that there are risks in contracting this sort of behaviour is beyond risk management and verges on blatant abuse of power.”

Another subcontractor told the Enquirer: “I was presented with a standard JCT the other day that should have been around 76 pages but ran to 177 pages.

“Some firms don’t realise it but they can be agreeing to unlimited liability, or agreeing terms that PI insurers will not pay out on.”

The rise in non-standard forms has prompted the BCSA to highlight clauses now slipping into common use that are leaving firms seriously exposed.

A working party set up by the association has revised its ‘Construction Contractual Handbook’ to spotlight common contractual traps.

The latest edition is now being offered to all subcontractors as well as the wider industry community of developers, employers, contractors, consultants, surveyors and insurers.

Red flag clauses

Subcontractor to coordinate all other subcontractors trades

Example of wording: “The subcontractor shall be responsible for co-ordinating the subcontract works with the works of the main contractor, its agents and subcontractors and any other parties on the site. Such co-ordination shall include but not necessarily be limited to design (where applicable), programming, sequencing of works, checking of levels/setting out/dimensions/adequacy of preceding works, installation of health and safety.

Risk
The risk of co-ordinating the works (and checking works carried out by others) is being passed down to the subcontractor, where this should stay firmly with the main contractor.

Ground Conditions clause

“The subcontractor accepts that it has had an opportunity to inspect the physical and other conditions (including the sub-surface conditions) of or affecting the site. Any adverse ground conditions or artificial obstructions encountered during the execution of the subcontract works shall be the sole responsibility of the subcontractor and there shall be no addition to the subcontract sum nor any extension of time nor any loss or expense claim granted.”

Another also used (sent by readers)

“The Subcontractor shall not and shall not be entitled to rely upon any survey, report or other document prepared by or on behalf of the contractor and the contractor makes no representation or warranty as to the accuracy or completeness of any such survey, report or document.”

Risk
The clause puts the risk of discovering anything which would impede progress or mean that additional expense has to be incurred firmly at the subcontractor’s door.

Pay when paid clause

“The Contractor shall not be liable to make any payment to the subcontractor in respect of any work executed or materials supplied or any other provision entitling the subcontractor to payment (including for the avoidance of doubt retention withheld) for which the contractor has not received payment under the main contract.

Risk

Effectively a ‘pay when paid’ where the subcontractor has to credit risk the client and the main contractor.

Fitness for purpose clause

In bespoke contracts, often the actual words “fit for purpose” may be used. Be aware also of other wording which implies fitness for purpose, such as “meeting the performance specifications set out in the contractor’s requirements”. Under NEC3 and NEC4 contracts, fitness for purpose for design is the default position unless option X15 is selected (reasonable skill and care). In JCT2016 D&B Subcontract, Clause 2.13.1 restricts design liability to that of an architect or other appropriate professional designer (which will be “reasonable skill and care” but this is sometimes deleted.

Risk
Designing something which is fit for purpose is a more onerous duty than using reasonable skill and care to do so. It is often not covered by PI insurers, and they sometimes specifically require that you do not accept any fitness for purpose obligations.

Subcontractor payment clawback clause if employer fails (sent by readers)

In the event that the contractor had previously made payment to the subcontractor for work or matters that the contractor has an entitlement under the main contract for payment from the employer… and by reason of the insolvency of the employer, the contractor had not received, the subcontractor shall refund the contractor to the extent the contractor has paid the subcontractor.

Risk

You lose all payment!

Latest news

Site labour rates hit record high as cost inflation returns

Industry's biggest payroll firm says rates rose nearly 5% last month in London
3 days ago

Morris & Spottiswood acquires part of ISG fit-out division

ISG Cathedral acquisition saves 111 jobs and expands presence across England
3 days ago

New work drives Q3 construction output uplift

Third quarter activity up 0.8% despite slowdown in September
3 days ago

Octavius cuts concrete formwork strike time by 5 days

Temperature probes reduce times for safely striking formwork
3 days ago

Plan for 200-home student-led London scheme

Developer Regal is behind new Camden Town scheme
3 days ago

Green light for new £45m tax office in Portsmouth

HMRC to occupy new office complex with construction starting next year
3 days ago

Extra tunnels included in £6bn East West Rail scheme

Government unveils plans for two new tunnels in Cambridgeshire
4 days ago

Infrastructure to get £80bn boost from public sector pensions

New "megafunds" will invest in UK construction projects
4 days ago

Bidders wanted for £800m building safety framework

Fusion21 launches renewal of deal across 12 lots
4 days ago

Winchmore wins £6.5m brickwork package on Stratford flats

Latest award from Graham on £69m development
4 days ago

Motts/Jacobs JV to design £2.5bn West Yorkshire Mass Transit

First construction could begin in 2028
4 days ago

Muse signs landmark deal to redevelop Solihull shopping centre

Mell Square scheme includes 1,600 homes at 6.4ha town centre site
5 days ago

Reds10 raids house builders for two director hires

David Newey and James Bateman join as regional ops directors
5 days ago

Builder killed as telehandler overturns

House builder goes into liquidation before court hearing and £160,000 fine
5 days ago

Balfour Beatty regional MD steps down

Lindsay McGibbon is understood to be exiting for a job in the United States
5 days ago

Firms put on alert for £1.5bn decarbonisation framework

Fusion21 aims to invite bids in January for housing and public buildings retrofit framework
5 days ago

Morgan Sindall aboard for £22m London station roof renewal

Passengers will continue to use Liverpool Street Station while roof works take place above
5 days ago

Utilities contractor turns to Africa for skilled workers

IES Utilities Group recruits its 100th overhead linesman from South Africa and Zimbabwe
5 days ago

McLaren boosts building safety and refurb team

Paul Woodhams promoted to newly created MD role at expanding division
6 days ago

Firms fight to renew places on £450m JV North deal

17 firms face fight to retain places on north west housing consortium list
6 days ago

Subbies get £7m lifeline on ISG Cardiff schools site

Council strikes deal with administrators and appoints emergency interim contractor
6 days ago

United Utilities names water and waste water design consultants

AtkinsRéalis, Jacobs, Stantec, Binnies, Mott MacDonald, RPS, and WSP make line-up
6 days ago

Crown Estate in £1.5bn Cambridge Business Park revamp plan

A phased programme of construction will start in 2026
6 days ago

McLaughlin & Harvey returns to profit

Contractor back in the black and looking forward to another positive year
6 days ago

Graham wins £69m London Stratford flats job

Stratford Mill project will deliver nearly 250 flats
6 days ago

Mace to complete construction of ISG neuroscience centre

Contractor to work with UCL to finish stalled job
7 days ago

BAM finally breaks ground at £60m-plus Yeovil College

Agreed contract price 50% above original estimate on delayed Somerset college job
6 days ago

Forterra trying to pass on NI cost increases

Brick and block giant writing to customers about 2025 price rises
7 days ago

Refurb contractor Troy Central goes into administration

Suffolk based hotel and leisure specialist had a £38m turnover
7 days ago

Former ISG director joins Wates as regional construction MD

Wayne Flannery joins Wates construction board after nearly 20 years at ISG
7 days ago

Contractor services