McAlpine takes plaudits as 2012 Stadium completed

Grant Prior 13 years ago
Share

Sir Robert McAlpine has been hailed for its performance completing the 2012 stadium on time and under budget without any major accidents.

Olympic Delivery Authority chairman John Armitt laid the last piece of turf yesterday marking completion of the main construction phase which has lasted nearly three years.

He said: “To complete a complicated project such as this in less than three years is testament to the skill and professionalism of the UK construction industry.

“I would like to thank the Team Stadium consortium and all of the workers for their hard work and commitment.”

Over 240 UK businesses have won contracts for the construction of the Stadium and over 5,250 people have worked on the project over the past three years.

Construction facts and figures

Construction started in May 2008 and has been completed in just under 3 years.

The design and construction team has been led by Sir Robert McAlpine, with Populous as the Architect and Buro Happold as the designer of the civils, structural and building services work. Hyland Edgar Driver were the Landscape Architects. The Planning Consultant was Savilles Hepher Dixon

Over  5250 people have worked on the project over the past 3 years with the operatives workforce peaking at 650

Over 240 businesses, from Devon to Scotland, have worked on the construction of the Stadium.

More than 5,000 reinforced concrete columns were installed into the ground, up to 20m deep, to provide the foundations to support the Stadium structure

112 steel rakers and 12,000 pre-cast concrete terracing units hold the spectator seating in place

The roof compression truss is made up of 28 steel sections, each one is 15m high by 30m long and weigh 85 tonne. A 1,350-tonne super lift crane was assembled in the field of play to lift them into place between January and July in 2009.

The cable net roof provides the correct conditions for athletes on the field of play and covering two-thirds of spectators. The roof is covered by 112 panels of white material, totalling 25,000 m². The fabric was fitted by a team of 23 expert abseilers.

To ensure that the sporting action is illuminated and to meet high definition TV standards, the Stadium is lit by 532 individual floodlights housed in 14 towers. The top of the towers reach 70 metres above the field of play.

Each of the 14 lighting tower weighs 34 tonnes and are 28m high. They were lifted into place by a 650 tonne crane over a period of 14 days in March 2010.

There will be around 700 rooms and spaces within the Stadium, including changing rooms and toilets. The fit-out work has required15,000 sq m of plasterboard, 140,000 blocks to create walls, 11km of pipes for drainage, 338km of power cables plus 33km of other data systems cabling and 12km of ventilation ducts.

The turf for the field of play was grown in Scunthorpe and was laid over a period of 3 days in March 2011.

The track will be laid later this year to allow for LOCOG to carry out temporary overlay work which may need cranes and so could damage the track if it was laid now.

The black and white spectator seats were designed in the UK and manufactured in a factory in Luton. They were fitted between May and December 2010.

The toilets for spectators are spread out across 32 separate buildings on the podium level and are all now functional.

Latest news

McAlpine healthcare MD joins BAM as Northern chief

Mark Gibson joins as Northern regional director
2 days ago

HS2 Align JV completes Britain’s longest rail bridge – video

Final deck segment sees HS2 viaduct break 137-year old record held by Tay Bridge
2 days ago

Green light for major London city fringe office retrofit

Overhaul of 30 Finsbury Square to start next Summer
2 days ago

John Lewis submits plan for £80m Reading rental flats scheme

Construction hoped to start on 215 flats scheme at the start of 2026
2 days ago

Balfour Beatty lands £27m Highlands flood defence scheme

Work to start imminently building river walls in Comrie
2 days ago

Buyers believe construction has “turned a corner”

Residential rebounds, commercial still strong but civils slows
3 days ago

Vistry unseats Barratt as Britain’s biggest house builder

Partnership homes specialist on track to build 18,000 homes this year
3 days ago

23 jobs axed as Lincolnshire contractor goes under

C G Godfrey provided civils and M&E services in Eastern England
3 days ago

Winvic first to use remote-control tower crane on site

Crane driver sits in ground floor command centre at Birmingham 33-storey tower
3 days ago

Starmer vows to ban Grenfell firms from public contracts

Prime Minister to write to named and shamed construction firms
3 days ago

Grenfell Inquiry calls for uber construction regulator

Shake-up must include licensing of main contractors taking on high rise projects
4 days ago

Robertson to restore historic Newcastle market

Work to revamp Grainger Market to start by the end of this month
3 days ago

Three bidders chase £1.4bn Midlands rail hub alliance

Balfour, Skanska, Bam and Laing O'Rouke in bidding for eight-year rail upgrade
4 days ago

Barratt profit nosedives as margin slumps to 4.2%

Fire safety provisions jump by an extra £126m to total £628m
4 days ago

First viaduct completed on HS2: Video site report

Eiffage, Kier, Ferrovial Construction and Bam Nuttall finish 163m long Highfurlong Brook Viaduct
4 days ago

Bouygues bags £28m Oxfordshire school job

St John’s Academy to be at heart of Wellington Gate Development
4 days ago

Willmott Dixon wins £49m Wigan college expansion

New campus for Wigan & Leigh College to be net zero in operation
4 days ago

Work to start on Liverpool office to flats job

Truman D&B wins resi conversion in Moorfields district
4 days ago

Government mothballs plan to scrap CE Mark

Building safety minister warns there is insufficient capacity in present testing regime
5 days ago

Government backs record number of clean energy projects

131 projects will produce electricity to power 11 million homes.
5 days ago

Tube station housing plan gets Government green light

Plans to transform Cockfosters Tube station were blocked by previous regime
5 days ago

Go-ahead for Bristol Temple Quay hotel and build to rent job

A trio of blocks will house a 230-room hotel, 170-room apart-hotel and 100 rental flats
5 days ago

Construction costs cut for Plymouth city centre revamp

Price of Armada Way scheme falls to £30m after exploratory work on site
5 days ago

Tilbury Douglas chief Paul Gandy to step down

Craig Tatton to take on CEO role from November
6 days ago

Local pressure unblocks £240m Oxford sewage works upgrade

Council warns Thames Water delay is halting building of thousands of new homes
6 days ago

Knights Brown bags last phase of £86m Portsmouth flood defence job

Contractor has already completed second and third phases of North Portsea Coastal Scheme
6 days ago

Bidding starts for £1bn housing decarbonising framework

National housing energy efficiency retrofit deal will come into force in 2015
6 days ago

World’s strongest land-based crane launched

Mammoet crane will help build major energy and infrastructure projects
6 days ago

Big Yellow gets go-ahead for largest London site

Storage giant to build 176,000 sq ft scheme next to Kensington Olympia
6 days ago

Worker dies after being buried by trench collapse

Court hears workers on new build housing site had no training on working within excavations
6 days ago

Contractor services