Builder has lucky escape in 14 metre casino fall

Grant Prior 11 years ago
Share

The main contractor in charge of refurbishing the historic Hippodrome Casino in Leicester Square has been fined after a worker fell from an unguarded edge and plunged four storeys.

The 35-year-old subcontractor, who does not want to be named, broke his left leg and several bones in his foot in the incident in March 2012.

His fall was two-staged as the unguarded edge was above a plant room.

He dropped into the room and then through a riser duct for an air-conditioning system, where he fell a further four storeys. The total distance was more than 14 metres.

The metal sheeting at the bottom of the duct partially cushioned the impact and may have saved his life.

Westminster Magistrates’ Court heard that the injured contractor was in a loft overlooking the plant room after taking an alternative route from the roof area of the building.

There was no edge protection in the loft to prevent a fall, and the riser duct for the air-conditioning was exposed because a sturdy cover had been removed, leaving just a plastic sheet to keep out dust.

HSE told the court that had the edge been adequately protected, as was later achieved using scaffolding, then the incident could have been avoided.

A properly secured cover for the duct could also have prevented the initial one storey drop from becoming any worse.

The District Judge also heard that Beck Interiors was aware of the need to improve its management of work at height risks, having received written advice from HSE officials and independent safety advisors following earlier visits to this site and others.

The company, of Cox Lane, Chessington, was fined a total of £20,000 and ordered to pay £13,365 in costs after pleading guilty to safety charges.

After the hearing HSE Inspector Stephron Baker-Holmes said: “This was a serious incident that could have ended in tragedy. It is astonishing that the worker plunged so far and escaped more serious harm, and he is incredibly fortunate that the metal duct broke his fall.

“This case highlights the need for principal contractors to proactively manage work at height risks, and to take appropriate action to prevent or mitigate falls.

“The company expressed regret, but asserted that the injured person should not have been in the loft area. However the fact is that others were also accessing the loft, and the risk of falling should have been adequately controlled.”

Latest news

McAlpine healthcare MD joins BAM as Northern chief

Mark Gibson joins as Northern regional director
2 days ago

HS2 Align JV completes Britain’s longest rail bridge – video

Final deck segment sees HS2 viaduct break 137-year old record held by Tay Bridge
2 days ago

Green light for major London city fringe office retrofit

Overhaul of 30 Finsbury Square to start next Summer
2 days ago

John Lewis submits plan for £80m Reading rental flats scheme

Construction hoped to start on 215 flats scheme at the start of 2026
2 days ago

Balfour Beatty lands £27m Highlands flood defence scheme

Work to start imminently building river walls in Comrie
2 days ago

Buyers believe construction has “turned a corner”

Residential rebounds, commercial still strong but civils slows
3 days ago

Vistry unseats Barratt as Britain’s biggest house builder

Partnership homes specialist on track to build 18,000 homes this year
3 days ago

23 jobs axed as Lincolnshire contractor goes under

C G Godfrey provided civils and M&E services in Eastern England
3 days ago

Winvic first to use remote-control tower crane on site

Crane driver sits in ground floor command centre at Birmingham 33-storey tower
3 days ago

Starmer vows to ban Grenfell firms from public contracts

Prime Minister to write to named and shamed construction firms
3 days ago

Grenfell Inquiry calls for uber construction regulator

Shake-up must include licensing of main contractors taking on high rise projects
4 days ago

Robertson to restore historic Newcastle market

Work to revamp Grainger Market to start by the end of this month
3 days ago

Three bidders chase £1.4bn Midlands rail hub alliance

Balfour, Skanska, Bam and Laing O'Rouke in bidding for eight-year rail upgrade
4 days ago

Barratt profit nosedives as margin slumps to 4.2%

Fire safety provisions jump by an extra £126m to total £628m
4 days ago

First viaduct completed on HS2: Video site report

Eiffage, Kier, Ferrovial Construction and Bam Nuttall finish 163m long Highfurlong Brook Viaduct
4 days ago

Bouygues bags £28m Oxfordshire school job

St John’s Academy to be at heart of Wellington Gate Development
4 days ago

Willmott Dixon wins £49m Wigan college expansion

New campus for Wigan & Leigh College to be net zero in operation
4 days ago

Work to start on Liverpool office to flats job

Truman D&B wins resi conversion in Moorfields district
4 days ago

Government mothballs plan to scrap CE Mark

Building safety minister warns there is insufficient capacity in present testing regime
5 days ago

Government backs record number of clean energy projects

131 projects will produce electricity to power 11 million homes.
5 days ago

Tube station housing plan gets Government green light

Plans to transform Cockfosters Tube station were blocked by previous regime
5 days ago

Go-ahead for Bristol Temple Quay hotel and build to rent job

A trio of blocks will house a 230-room hotel, 170-room apart-hotel and 100 rental flats
5 days ago

Construction costs cut for Plymouth city centre revamp

Price of Armada Way scheme falls to £30m after exploratory work on site
5 days ago

Tilbury Douglas chief Paul Gandy to step down

Craig Tatton to take on CEO role from November
6 days ago

Local pressure unblocks £240m Oxford sewage works upgrade

Council warns Thames Water delay is halting building of thousands of new homes
6 days ago

Knights Brown bags last phase of £86m Portsmouth flood defence job

Contractor has already completed second and third phases of North Portsea Coastal Scheme
6 days ago

Bidding starts for £1bn housing decarbonising framework

National housing energy efficiency retrofit deal will come into force in 2015
6 days ago

World’s strongest land-based crane launched

Mammoet crane will help build major energy and infrastructure projects
6 days ago

Big Yellow gets go-ahead for largest London site

Storage giant to build 176,000 sq ft scheme next to Kensington Olympia
6 days ago

Worker dies after being buried by trench collapse

Court hears workers on new build housing site had no training on working within excavations
6 days ago

Contractor services