Murphy loses legal battle over delayed Beckton power plant

Aaron Morby 9 years ago
Share

J Murphy & Sons has lost its fight in the High Court to stop the client of its East London power plant project calling an on-demand bond in respect of a claim for liquidated damages of £8.27m.

Client and contractor are at loggerheads about cost overuns
Client and contractor are at loggerheads about cost overuns

The ruling ahead of attempts to settle claims is the latest blow for the contractor on its fat-fired combined heat and power project in Beckton.

The project, which is now in protracted commissioning and testing, is running nearly 15 months late,  with a handover date still to be agreed by Murphy and client Beckton Energy.

Murphy first revealed the cost of problems on the power plant scheme five months ago when it blamed much of an £16m operating loss in 2014 on the extra cost of building the combined heat and power plant.

The contractor said difficulties with design, cost escalation, supply chain and engine related technical breakdowns all had major impacts on the project.

At the time Murphy said it was reviewing its entitlement for recovery of sums, but had stuck to its policy of booking losses as they emerged.

The £70m engineer, procure and construct contract was awarded following a competitive tender three years ago and was due to be handed over in January 2015.

In the High Court, Murphy had asked the judge to rule whether client Beckton Energy could make a demand on the bond in respect of its claim for liquidated damages before the project engineer had made a determination on the amount of LDs due.

During the case its emerged that Murphy disputes Beckton’s entitlement to any liquidated damages, and claims to have suffered significant delays on the project and requested extensions of time, in particular in August 2014, February 2015, September 2015, November 2015 and December 2015.

Beckton Energy claims that extensions were not granted by the engineer because Murphy had not demonstrated that any event or circumstances gave rise to a claim for extension of time or payment.

The judge ruled the details of the main dispute were not pertinent to contract terms at issue and in a set-back for Murphy ruled that Beckton Energy was entitled to call  the on demand bond under the contract.

Latest news

£600m delivery partner named for new hospital programme

Mace/T&T JV named programme delivery partner for £37bn new hospital plan
4 hours ago

Planning green light for £10bn Northumberland data centre

Blackstone-backed project will create 1,200 construction jobs
8 hours ago

Police arrest plant hire fraud gang

Nine arrests after kit hired "with no intent of ever returning the machines"
11 hours ago

Balfour Beatty boss Leo Quinn to step down

Group Chief Executive to be replaced by consultant AtkinsRéalis chief Philip Hoare
14 hours ago

Galliford Try upgrades target as half-year profits jump 54%

Firm closes in on deal to take on ISG custodial work
14 hours ago

Trespasser dies in crane fall at Willmott Dixon site

Tragedy after man breaks into £60m Manchester science park site
14 hours ago

Ibstock pulls out of GRC cladding market

Materials giant blames subcontractor failures and low margins
14 hours ago

Green light for 1,000-home Wolverhampton city centre regen

Phase one of ECF Smithgate scheme to start this year
14 hours ago

Oval revises Manchester scheme with trio of towers

Flats doubled to 800 at reworked Albert Bridge House project
14 hours ago

More repair work needed at McAlpine problem panel hotel

Contractor looking for long-term solution to loose panels
15 hours ago

Redesign delays hit giant McAlpine car battery factory

Size of first building reduced and steelwork start pushed back
2 days ago

‘Affordable’ HS2 Crewe to Euston plan submitted to Treasury

Industry presses for scaled back Euston terminus and connection to Crewe
2 days ago

Regal submits plan to revive stalled London resi tower

Swiss Cottage project redesigned with second staircase and 237 flats
2 days ago

Construction boss jailed for siphoning off cash for casino

Money removed from contracting firms before they went under
2 days ago

Muse signs up to £3.2bn Solihull health campus district

Ambitious Arden Cross scheme next to HS2 Interchange advances
2 days ago

Drees & Sommer acquires RSP Consulting Engineers

Expanding consultant sees UK workforce grow to 300
2 days ago

Watkin Jones wins over £50m student digs campus upgrade

Work to start next month on phase 714-bed south London campus
2 days ago

Severfield warns on profits blaming major project delays

Steelwork firm cancels share buyback and steps up cost cutting programme
3 days ago

Administrators go in at aggregates firm Ashville

Administrators from Leonard Curtis now in charge of London based aggregates specialist
3 days ago

Costain start date for £67m Romford flyover replacement

Work to start this summer on Gallows Corner bridge rebuild
3 days ago

North West regional civils contractor in administration

Colin Briscoe Construction employed 25 staff
3 days ago

Work starts on tyres to jet fuel recycling plant

£100m Sunderland plant will produce around 30,000t of liquid fuel
3 days ago

Kier targets £400m of logistics work with Investec JV

Hemel Hempstead site marks start of new venture
3 days ago

Watchdog MPs raise alarm over HS2 Euston station plan

Public spending watchdog red flags 'no plan or timescale' for London Terminus
6 days ago

Network Rail fined £3.41m after Surbiton track worker death

30-year-old track worker Tyler Byrne was struck by a passenger train in Surbiton
6 days ago

Government picks 43 consultants for Net Zero programmes

Jacobs, Mace, Mott MacDonald and Costain feature across multiple lots
6 days ago

£2.2bn Gatwick second runway decision delayed

Government 'minded to approve' expansion but puts back decision to October
6 days ago

Avant Homes gets green light for £68m Scottish site

Construction set to start in July
6 days ago

Funding deal for £237m Tide Construction student tower

48-storey project will be first major student scheme on Canary Wharf
6 days ago

McLaren wins £29m south east London industrial job

Crayford urban logistics hub starts construction
7 days ago

Contractor services