£1.1bn Newport M4 public inquiry delayed for five months

Aaron Morby 8 years ago
Share

A public inquiry into the proposed M4 Relief Road in South Wales has been delayed after the UK Government confirmed it would use a new method of forecasting vehicle traffic growth.

Proposed new section of motorway will include a  major new bridge
Proposed new section of motorway will include a major new bridge

The five-month inquiry was due to start next month into the proposed 23km new section of motorway. But the Welsh Government has put back the start to March next year to give it time to assess the new growth data.

The Welsh Government pledged the delay would not affect the planned Spring 2018 construction start date for a Costain/Vinci joint venture which holds an ECI contract for the massive new section of motorway.

The UK Treasury has agreed to support the project by allowing the Welsh Government to borrow £500m towards the cost.

Cabinet Secretary for Economy and Infrastructure, Ken Skates said: “The UK Government has already expressed its desire to see work on the M4 project start as soon as possible, so it is hugely disappointing that the Department for Transport chose only to engage with us on these amendments to their traffic forecasting three days before they were introduced forcing this regrettable delay to the start date of the public inquiry.

“Assessments indicate that our proposed M4 Project is the only reasonable solution, but it is only right and proper that the proposals are scrutinised robustly, transparently and openly in an inquiry and that we test the project in light of the most up-to-date information available to ensure that we deliver the right choice for the people in Wales.

“It is essential that we, and others who wish to submit evidence to the public inquiry, now take time to fully review these new Department for Transport figures before the inquiry begins. 

“We’ve made a strong commitment to deliver a sustainable, long-term solution to the chronic traffic problems on this stretch of the M4 and I have been assured that, subject to inquiry approval, the M4 Corridor around Newport Project will still be completed in 2021.”

A Department for Transport spokesperson said: “We keep our traffic forecasts under review and made clear to Welsh officials at the start of this year we were going to update our projections.

”We are committed to working closely with the Welsh government and encourage them to deliver this project which will improve journeys for drivers.”

The new section of motorway is planned to be built between Junctions 23 and 29 south of Newport, crossing the Gwent Levels, River Usk Estuary, Newport Docks, the Llanwern Steelworks site and close to the Docks Way landfill site.

It will include a 440m main span cable-stayed bridge ranking as the fourth longest of its type in the UK.

m4 relief road corridor

Latest news

McAlpine healthcare MD joins BAM as Northern chief

Mark Gibson joins as Northern regional director
2 days ago

HS2 Align JV completes Britain’s longest rail bridge – video

Final deck segment sees HS2 viaduct break 137-year old record held by Tay Bridge
2 days ago

Green light for major London city fringe office retrofit

Overhaul of 30 Finsbury Square to start next Summer
2 days ago

John Lewis submits plan for £80m Reading rental flats scheme

Construction hoped to start on 215 flats scheme at the start of 2026
2 days ago

Balfour Beatty lands £27m Highlands flood defence scheme

Work to start imminently building river walls in Comrie
2 days ago

Buyers believe construction has “turned a corner”

Residential rebounds, commercial still strong but civils slows
3 days ago

Vistry unseats Barratt as Britain’s biggest house builder

Partnership homes specialist on track to build 18,000 homes this year
3 days ago

23 jobs axed as Lincolnshire contractor goes under

C G Godfrey provided civils and M&E services in Eastern England
3 days ago

Winvic first to use remote-control tower crane on site

Crane driver sits in ground floor command centre at Birmingham 33-storey tower
3 days ago

Starmer vows to ban Grenfell firms from public contracts

Prime Minister to write to named and shamed construction firms
3 days ago

Grenfell Inquiry calls for uber construction regulator

Shake-up must include licensing of main contractors taking on high rise projects
4 days ago

Robertson to restore historic Newcastle market

Work to revamp Grainger Market to start by the end of this month
3 days ago

Three bidders chase £1.4bn Midlands rail hub alliance

Balfour, Skanska, Bam and Laing O'Rouke in bidding for eight-year rail upgrade
4 days ago

Barratt profit nosedives as margin slumps to 4.2%

Fire safety provisions jump by an extra £126m to total £628m
4 days ago

First viaduct completed on HS2: Video site report

Eiffage, Kier, Ferrovial Construction and Bam Nuttall finish 163m long Highfurlong Brook Viaduct
4 days ago

Bouygues bags £28m Oxfordshire school job

St John’s Academy to be at heart of Wellington Gate Development
4 days ago

Willmott Dixon wins £49m Wigan college expansion

New campus for Wigan & Leigh College to be net zero in operation
4 days ago

Work to start on Liverpool office to flats job

Truman D&B wins resi conversion in Moorfields district
4 days ago

Government mothballs plan to scrap CE Mark

Building safety minister warns there is insufficient capacity in present testing regime
5 days ago

Government backs record number of clean energy projects

131 projects will produce electricity to power 11 million homes.
5 days ago

Tube station housing plan gets Government green light

Plans to transform Cockfosters Tube station were blocked by previous regime
5 days ago

Go-ahead for Bristol Temple Quay hotel and build to rent job

A trio of blocks will house a 230-room hotel, 170-room apart-hotel and 100 rental flats
5 days ago

Construction costs cut for Plymouth city centre revamp

Price of Armada Way scheme falls to £30m after exploratory work on site
5 days ago

Tilbury Douglas chief Paul Gandy to step down

Craig Tatton to take on CEO role from November
6 days ago

Local pressure unblocks £240m Oxford sewage works upgrade

Council warns Thames Water delay is halting building of thousands of new homes
6 days ago

Knights Brown bags last phase of £86m Portsmouth flood defence job

Contractor has already completed second and third phases of North Portsea Coastal Scheme
6 days ago

Bidding starts for £1bn housing decarbonising framework

National housing energy efficiency retrofit deal will come into force in 2015
6 days ago

World’s strongest land-based crane launched

Mammoet crane will help build major energy and infrastructure projects
6 days ago

Big Yellow gets go-ahead for largest London site

Storage giant to build 176,000 sq ft scheme next to Kensington Olympia
6 days ago

Worker dies after being buried by trench collapse

Court hears workers on new build housing site had no training on working within excavations
6 days ago

Contractor services