Government sinks £1.3bn Swansea tidal power plan

Aaron Morby 7 years ago
Share

Plans to build the world’s first tidal power lagoon have been rejected by the government prompting a wave of angry attacks from its promoters and MPs.

Business and Energy Secretary Greg Clark said the project would not be value for money, contradicting the Hendry Review 18 months ago that concluded the project could ignite a new industry for the UK.

“At £1.3bn, the capital cost per unit of electricity generated each year would be 3 times that of the Hinkley Point C nuclear power station.

“If a full programme of six lagoons were constructed, the Hendry Review found that the cost would be more than £50bn, and be 2.5 times the cost of Hinkley to generate a similar output of electricity,” added Clark.

The scheme would have been the world’s first tidal lagoon power project providing electricity for around 155,000 homes and sustaining 2,200 construction jobs.

Keith Clarke, chair of Tidal Lagoon Swansea Bay, said: “The treatment of the pathfinder tidal lagoon makes a mockery of a supposed new Industrial Strategy for the UK that pledges to back the disruptors and embrace new industries for a new future.

“The reality is that indecision sucks the life out of innovation and timid leadership will condemn Brexit Britain to the 20th Century.

“The entire industrial strategy of employing British manufacturing to harness British tides relies explicitly on delivery of a pathfinder at Swansea. Without it, we will again export jobs that could and should stay here.

“The lack of engagement with us during this process has been highly disturbing.”

Mark Shorrock, founder and chief executive of Tidal Lagoon Power, said: “The like-for-like comparison is that both Swansea and Hinkley Point C need a contract of £92.5 for 35 years, combined with other forms of government support.

“The difference is that one is a small bet on a homegrown and reliable energy future with minimal impact on consumers (30 pence a year on bills), the other is a massive gamble with energy security to the advantage of foreign companies and at huge cost to consumers (up to £15 a year on bills).

“The Secretary of State today appeared to airbrush from history the full story of the UK’s success in offshore wind.

‘It has indeed been a success and it has cost the nation some £8 billion in subsidy to make it so. Tidal power deserves the chance to make its contribution to the energy mix and the national economy and it will be able to do so for a much, much smaller price tag.”

Latest news

Fraudsters jailed after £22m construction tax scam

Gang sentenced after bogus payroll firm failed to pay VAT and CIS money to revenue
3 hours ago

MPB clinches substructure for HS2 Curzon Street station

Contracts for station superstructure to be let in coming months
19 hours ago

Flood defence spend rises to record £2.65bn over two-years

Key projects mapped as Government injects extra £250m to shore up defences
2 hours ago

Turnaround strategy continues to pay off for Careys

Profits continue to rise as £50m investment plan in full swing
20 hours ago

All change on £800m Eastern Highways Alliance

Octavius and Winvic sweep up all three lots in new line-up
2 hours ago

Vinci bags first phase of £350m Stockport scheme

Contractor edges-out Willmott Dixon to start major mixed-used project
19 hours ago

Crest Nicholson slumps to £144m loss

Incoming CEO review unearths further writedowns on fire remediation and closed divisions
1 day ago

Piling job cuts loom over safety regulator project delays

Bottleneck in high rise project approvals hits demolition and foundation firms
2 days ago

Developer Ghelamco swaps to self delivery for Battersea tower

John F Hunt no longer part of project team on 24-storey resi scheme
2 days ago

Pagabo starts renewal race for two mega frameworks

Contractors and developers asked for input on reshaping deals worth billions
1 day ago

Giant HS2 viaduct deck slide breaks records: Video

EKFB consortium oversees four-day installation
1 day ago

Ferrovial lands £230m National Grid tunnel

Work to start shortly on Grain to Tilbury electricity infrastructure upgrade
2 days ago

Tax-row tunnellers down tools on Balfour Hinkley job

Lodge allowance tax dispute hits tunnelling site
2 days ago

Go-ahead for Square Mile’s fifth tallest tower

Multiplex set to start 99 Bishopsgate job late next year
2 days ago

New £4.5bn funding model for stalled London rail schemes

Residential TIF funding offers key to unlock Bakerloo and DLR extensions
2 days ago

Speedy Hire latest to be hit by slow CP7 rail spending

Plant-hire firm flags issues with latest Network Rail spending round
2 days ago

FM Conway family chair steps away from business after Vinci deal

Joanne Conway steps away as Andrew Hansen becomes MD
2 days ago

Manchester Hotspur Press mill scheme rescued

37-storey student tower will now go-ahead
2 days ago

Watkin Jones to advance 260-room London aparthotel

Development deal for New Kent Road project
4 days ago

Plan for film studios switched to data centre cluster

Plans in for six data centre buildings in Buckinghamshire
6 days ago

Hunt for firm to deliver £75m Cambridge Civic Quarter

Work includes £41m Guildhall and £21m Corn Exchange revamps
5 days ago

Plans in for £200m Middlesbrough regen scheme

Wates is lined up to deliver landmark Gresham rental homes scheme
5 days ago

£600m Bristol shopping centre redevelopment approved

Galleries centre will be demolished for homes and offices quarter
5 days ago

Ant Yapi lands ultra prime London homes job

Prestige scheme replicates Regency mansions around nearby Regent’s Park
5 days ago

CITB survives another review

Report published after two more years talking about skills crisis
6 days ago

Strucktor wins record M&E package from Ardmore

Major subcontract on £240m Tribeca life science development
5 days ago

Over 800 high-rise resi jobs stalled by safety regulator

Building safety regulator project logjam hits Government growth plan
6 days ago

McAlpine under fire after another panel comes loose from hotel

High winds cause more problems at recently completed Woking hotel
7 days ago

McGee starts demolition for £500m South Bank scheme

Former ITV studios will be replaced by two office towers
6 days ago

Four arrested after hospital construction site burglary

Damage and copper wiring stolen at Hinckley and District General Hospital new building
7 days ago

Contractor services