Infrastructure project final costs average 80% above bid prices

Aaron Morby 6 years ago
Share

Infrastructure project outturn costs are running nearly 80% higher than winning tender prices, according to new project data.

 London 2012 games is considered a crowning success, yet the games cost over three times the original budget.  The evolution of the budget and the political and public acceptance of this overspend, compares starkly with attitudes to Crossrail at 26% over budget
London 2012 games is considered a crowning success, yet the games cost over three times the original budget. The evolution of the budget and the political and public acceptance of this overspend, compares starkly with attitudes to Crossrail at 26% over budget

An influential report from Institution of Civil Engineers, which publishes the fresh figures from 25 projects, warns that the sector is facing a twin market failure.

A combination of unforeseeable cost increases driven by both external and project risks and low contractor margins, depressed by fears of not winning major project work, has stifled innovation, skills and sustainability, warn senior engineers.

The regular failure to deliver to budget has prompted calls for mindset changes among clients about cost envelopes during early project planning, more detailed scoping and much fairer allocation of risk with contractors.

The report is published as contractors planning to deliver HS2 main civils packages are locked in talks to agree on final bid prices near original cost estimates.

A leading infrastructure contractor supplied figures for projects awarded between 2009 and 2018 on the proviso it remained anonymous.

Only one project was delivered within the original tender price, with project costs swelling by 80% on average above the original contract value on the rest

The ICE emphatically rules out excessive profit taking, pointing out pre-tax margins in construction fell from just under 3% in 2013 to an average of –0.9% in 2018.

Miles Ashley, Chair of the report’s Steering Group, said: “Industry and government need to work smarter, find ways to reduce the disparity between forecasts and outturns, but also to change the narrative and ensure the wider public, the end users, are also aware of the whole-life benefits these incredible infrastructure projects are bringing to them.”

Recommendations


  • Infrastructure owners should complete scope, design and exploration before work starts to avoid scope creep or retroactive changes, taking steps to include contractors in design at an early stage.
  • The Government and infrastructure owners must move away from capital cost as the most important metric when assessing project benefits, and recognise the importance of whole-life economic, social and environmental value.
  • All public infrastructure owners undertaking procurement must award contracts based on a cost estimate range, using a should-cost estimate as a reference point, with an amount of contingency allocated appropriate to the level of project maturity.
  • Principles set out in the Government Outsourcing Playbook should be mandatory for infrastructure owners, this includes infrastructure owners undertaking should-cost modelling to help inform their expectations and knowledge of appropriate tender prices during the procurement process.

Report: Reducing the gap between cost estimates and outturns for major infrastructure projects and programmes

Latest news

Tax-row tunnellers down tools on Balfour Hinkley job

Lodge allowance tax dispute hits tunnelling site
3 hours ago

Go-ahead for Square Mile’s fifth tallest tower

Multiplex set to start 99 Bishopsgate job late next year
12 hours ago

New £4.5bn funding model for stalled London rail schemes

Residential TIF funding offers key to unlock Bakerloo and DLR extensions
3 hours ago

Speedy Hire latest to be hit by slow CP7 rail spending

Plant-hire firm flags issues with latest Network Rail spending round
3 hours ago

FM Conway family chair steps away from business after Vinci deal

Joanne Conway steps away as Andrew Hansen becomes MD
2 hours ago

Manchester Hotspur Press mill scheme rescued

37-storey student tower will now go-ahead
3 hours ago

Watkin Jones to advance 260-room London aparthotel

Development deal for New Kent Road project
2 days ago

Plan for film studios switched to data centre cluster

Plans in for six data centre buildings in Buckinghamshire
4 days ago

Hunt for firm to deliver £75m Cambridge Civic Quarter

Work includes £41m Guildhall and £21m Corn Exchange revamps
3 days ago

Plans in for £200m Middlesbrough regen scheme

Wates is lined up to deliver landmark Gresham rental homes scheme
3 days ago

£600m Bristol shopping centre redevelopment approved

Galleries centre will be demolished for homes and offices quarter
3 days ago

Ant Yapi lands ultra prime London homes job

Prestige scheme replicates Regency mansions around nearby Regent’s Park
3 days ago

CITB survives another review

Report published after two more years talking about skills crisis
4 days ago

Strucktor wins record M&E package from Ardmore

Major subcontract on £240m Tribeca life science development
3 days ago

Over 800 high-rise resi jobs stalled by safety regulator

Building safety regulator project logjam hits Government growth plan
4 days ago

McAlpine under fire after another panel comes loose from hotel

High winds cause more problems at recently completed Woking hotel
5 days ago

McGee starts demolition for £500m South Bank scheme

Former ITV studios will be replaced by two office towers
4 days ago

Four arrested after hospital construction site burglary

Damage and copper wiring stolen at Hinckley and District General Hospital new building
5 days ago

Caddick kicks off Digbeth regen plan with £43m flats job

First phase 211 flats job starts wider £260m Upper Trinity Street scheme
4 days ago

Sisk starts work on £300m Children’s Cancer Centre

Great Ormond Street Hospital job will employ 500 on site and last three years
4 days ago

McAlpine clinches £1.25bn Port Talbot low carbon steelworks job

Deal to build one of the largest electric arc furnaces in the world
6 days ago

McLaren to build top-down on £60m New Bond Street contract

Contractor working to tight technical guidelines on busy Mayfair site
5 days ago

Project delays dull Van Elle first-half results

Piling specialist upbeat about year ahead as order book up 24%
5 days ago

Aggregate Industries appoints new contracting chief

Kevin Murgatroyd promoted to new role
5 days ago

Bouygues wins Immingham £170m import jetty job

French civils firm to build bulk ammonia import facility for hydrogen economy
6 days ago

Plans in for latest phase of Leith port revamp

Construction to start this year on transforming waterfront
5 days ago

Avant Homes starts redundancy consultation

Jobs under threat at Central region
6 days ago

Plans in for Barnet leisure park and 1500 homes

Regal to redevelop Great North Leisure Park in Finchley
6 days ago

JRL wins shell and core for £400m London scheme

220 Blackfriars Road project will rise to 21 and 15 storeys
7 days ago

Robertson strengthens East Midlands leadership

Woodcock promoted to ops director and Brown joins from BAM as commercial director
6 days ago

Contractor services