Potash mine cash crisis forces construction slowdown

Aaron Morby 6 years ago
Share

North York moors potash mine developer Sirius Minerals is scaling back construction on the project amid a funding crisis.

Shares in the firm crashed 60% to 4p on Tuesday morning as it reported failure to raise $500m for the next major phase of construction for the huge fertiliser mining project.

The firm said it would now look at cutting development costs and try to find alternative funding.

Sirius chief executive Chris Frasers said the project had around £180m or six months of cash left under the reduced programme before construction would have to halt.

“Due to the ongoing poor bond market conditions for an issuer like Sirius we have not been able to deliver our stage 2 financing plan,” he said.

“As a result, we have taken the decision to reduce the rate of development across the project in order to preserve funding to allow more time to develop alternatives and preserve the significant amount of inherent value in this world-class project.

“The company will now conduct a comprehensive strategic review over the next six months to assess and incorporate optimisations to the project development plan and to develop a different financing structure for the funds required.”

The board of directors added that it believed additional financing would be secured in the coming months, but warned there was a risk that a successful outcome may not be reached.

The Woodsmith mine project involves sinking two 1.5km shafts below a national park on the North York Moors to access a huge deposit of polyhalite, a mineral that can be used as fertiliser.

Excavation of the main shaft has reached its target depth of 118m using conventional excavation techniques and a shaft boring roadheader has now arrived at the Woodsmith Mine site to continue excavations.

Austrian tunnelling specialist Strabag has the contract for the three main 23-mile tunnel drives to transport excavated material to the coast.

The first of three tunnel boring machines “Stella Rose” is presently at work and completed 1.2km of tunnelling, over two months ahead of schedule.

A contract was signed with P J Carey at the start of this month to deliver port handling facilities at Teesside, cancelling a previous contract with McLaughlin & Harvey.

Latest news

Breyer Group battles for survival as rivals circle

Housing maintenance firm fights three winding up petitions in a month
22 hours ago

Galliford Try gets go-ahead for Milton Keynes PRS tower

33-storey tower needs gateway 2 approval before work can start
17 hours ago

Careys facing £2.4m claim by developer over demolition cartel

Giant Hong Kong developer claims it was overcharged on Lots Road Power Station job
22 hours ago

Lendlease Construction renamed Bovis

US private equity firm completes £35m purchase of UK contracting business and rebrands
22 hours ago

Multiplex profit drops a third as revenue rises to £780m

Spate of new orders sets contractor up for three years of work
22 hours ago

Galliford Try and Breheny land latest Sizewell C road deals

More infrastructure deals for new nuclear power station
2 days ago

Worker trapped in collapsed septic tank pit

Contractor and director fined after worker suffers multiple fractures
23 hours ago

Homes England buys stalled Broad Marsh site

Demolition to finally be completed as developer hunt begins
1 day ago

Vistry go-ahead for 353 homes at Rochester Riverside

Work to start on next phase of Kent town regeneration at end of this year
2 days ago

M&E firm J S Wright collapsed owing £19m

Trade creditors hit for £11.4m by employee-owned Midlands firm
2 days ago

Right to work checks to be extended to self-employed

Government plans crackdown on illegal working and rogue employers
2 days ago

Midlands developer turns to London with £1bn resi schemes trio

SevenCapital plans 1,000 flats in Kensington, Islington and the Isle of Dogs projects
2 days ago

Deck falls off huge scissor lift at Winvic site

Two men seriously injured as platform plunges to the ground
5 days ago

Weston targets Build to Rent with new division

Weston Partnerships signs first deals with asset managers and councils
2 days ago

Bouygues seals deal for £119m Cardiff college campus

Construction to start in June on two new buildings
5 days ago

£140m cash injection to speed-up flood defence schemes

Funding part of £2.65bn investment over the next two years
2 days ago

Bid race starts for £15bn schools framework refresh

DfE throws framework open to more contractors
5 days ago

Berkeley’s £600m Borough Triangle project approved

Controversial scheme features two towers of 38 and 44-storeys
6 days ago

London Mayor calls in blocked 600-bed student scheme

Refused 20-storey London PBSA block may still be built
5 days ago

HG to build 500-bed London Stratford student scheme

Work will start later this year subject to gateway 2 safety approval
6 days ago

Arrest after pedestrian death on construction site

Tragedy during site preparation works for new Wigan car park
5 days ago

British Steel threatens closure of Scunthorpe blast furnaces

Chinese owners say sectional steel and rail supplies will be maintained
6 days ago

Planning green light for Sheffield warehouse site

Existing factories to be demolished in new scheme for Rula Developments
5 days ago

New rail property company to unlock land for 40,000 homes

First four sites released in Newcastle, Cambridge, Manchester, and Nottingham
6 days ago

Drainage specialist Subscan files administration notice

Specialist employing 131 people files court notice
6 days ago

Four win Network Rail £300m engineering design deal

Eastern region deal will include design for Northern Powerhouse Rail
6 days ago

Funding go-ahead for Banwell bypass after fresh cost hike

Galliford Try contract rises £14m to £64m after final design change
6 days ago

Graham wins Southport £75m Marine Lakes Centre

Firm replaces Kier which parted ways with backer Sefton Council
6 days ago

Chancellor unveils extra £2bn capital spend a year

Construction promised a defence dividend in military base and homes upgrade work
7 days ago

McLaren confirms subcontractor team on £135m warehouse job

Work starts on TN2 Gateway site in Kent.
7 days ago

Contractor services