Work will include the structural and slab foundations of all five units forming phase two.
Aarsleff will use three of its Junttan PMx22 and PM20 piling rigs to install over 1,140no. precast concrete piles of 250mm and 300mm square.
Some of the piles in a small area of the site were specified to be installed using minimal vibration methods due to being in close proximity to the London Tilbury rail line.
Aarsleff was able to offer a CFA solution for these piles which will be installed using their Soilmec SF50, one of Aarsleff’s latest rig investments.
Aarsleff’s Senior Technical Estimator Dan Coe said: ““We are pleased to be awarded the piling works for phase two of Segro Park Rainham. It is also great to be working with A & H Construction again this year, having installed precast concrete piles in July for them on a new retail development off Newport Road in Cardiff.”
Aarsleff Ground Engineering expect to complete their piling works before Christmas with construction to be complete and ready for lease in Quarter 3 of 2020.