London super sewer passes halfway point

Aaron Morby 5 years ago
Share

Tunnellers boring the London super sewer have just passed the halfway mark on the vast £3.8bn project.

The main tunnel at Battersea
The main tunnel at Battersea

The giant machines digging the main Thames Tideway tunnel have now bored over 13km of the 25km total length.

The tunnel now stretches as far west as Fulham and, eastwards, it has reached Blackfriars in the City of London – passing under 13 bridges including Albert Bridge, Westminster Bridge and Waterloo Bridge.

TBM Rachel digging the west section has passed the 3km mark on her 7km journey from Fulham to Acton.

So far, the tunnels have been constructed using four tunnel boring machines.

Two more tunnelling machines are due to start working in east London this year, creating the eastern section of the main tunnel from Bermondsey to Newham, as well as a slightly smaller 4km connection tunnel in Greenwich.

The project is looking to develop innovative ways of works and has introduced pre-shift work-outs to help prevent musculoskeletal disorders at Thames Tideway.

Tunnel team’s ‘stretch and flex’ sessions at the beginning of shifts, enabling engineers, site managers and drivers alike to prepare for the day’s tasks while getting a little bit of exercise in the process.

Andy Mitchell, Tideway CEO, said: “After more than three years of exceptional work by our teams across London, we’ve reached the halfway mark on the super sewer.

“There’s still a way to go but reaching this point on schedule is testament to the success of the team, who have achieved a huge number of engineering feats – including tunnelling under the river through a variety of ground conditions, building new pieces of land in the Thames to work in and digging giant shafts up to 50m deep below London.

Secondary lining for a 60m-deep shaft built in Bermondsey is now complete using 4,000 cu m of slip-formed concrete

“Once complete, not only will we have a cleaner river but there will be seven new areas of public space created along the Thames, transforming the embankment and creating new areas for Londoners and visitors to reconnect with the river.”

As well as the main tunnel, a 1km connection tunnel is also currently under construction in Wandsworth.

Three million tonnes of excavated material have been transported by river, avoiding 340,000 HGV journeys

Tunnelling is due to complete in 2022, allowing up to two years of commissioning for a March 2024 opening.

Latest news

Domis to start this year on £350m Nobu towers

Developer Salboy gains planning for Viadux second phase in Manchester
1 day ago

Muse submits Oldham town centre regeneration plan

Plan advances for six sites to deliver 2000 homes, an hotel and office space
1 day ago

Construction returns to growth after two tough months

Concern grows Trump turmoil is spooking property investors
1 day ago

Skanska wins £43m Clifton Bridge deal

Contractors says scheme is a "complex project that will be delivered to tight timescales"
1 day ago

Green light for 44-storey Manchester resi tower

Developer Glenbrook to start hunt for main contractor
2 days ago

Ten win £670m Network Rail eastern region small works deal

CK Rail, QTS, Colt and Construction Marine pick up two lots
2 days ago

Mears aims to dominate in compliance and housing upkeep

Firm hails 100% rebid success on a slew of major contract renewals
2 days ago

Investigation after two track workers hit by wagon

Accident in Glasgow during engineering possession
1 day ago

Durkan finance chief joins house builder Thakeham

Paul Kimber confirmed as new Chief Financial Officer
1 day ago

Water win sees Mott MacDonald Bentley hunt for new staff

Recruitment event for the South of England: Register now
2 days ago

Labour master VAT fraudsters target subcontractors

Tax authorities looking to clamp down on payroll fraud
2 days ago

Phoenix ME rides out ISG collapse with record 74% turnover surge

Pre-tax profit up after Phoenix re-engaged on all former ISG jobs
2 days ago

Mace confirmed for £200m London City office retrofit

Four upper floors to be added to 65 Gresham Street
2 days ago

£200m Viking onshore pipeline project approved

55km underground pipeline to be built from Immingham to Theddlethorpe
2 days ago

Plans in for Bristol Brabazon over-station office block

YTL Construction UK to build 8-storey office block
2 days ago

UK Power Networks fined for unsafe street works

Council officers spot unguarded excavations
2 days ago

Lindum profit jumps 28% as turnover nears £200m

507 staff shareholders share in strong year as pre-tax profit hits £10.4m
3 days ago

Universal to build theme park in Bedford

Work to start next year creating 20,000 construction jobs
3 days ago

Go-ahead for £400m Cambridge sewage treatment works

Major greenbelt project pivotal to 8,000-home North East Cambridge scheme
3 days ago

Erith pays down bid-rigging fine over two years early

Total employee ownership bonuses top £5.3m for nearly 450 staff
3 days ago

Network Rail property JV to deliver Cambridge North homes

Blockwork will deliver over 400 homes around local station
3 days ago

Construction worker dies on Essex site

Fatal accident at housing job run by Rose Builders
4 days ago

Pension fund charges hit profits at Wates

Bottom line also hit by closing out construction contracts
4 days ago

Muse submits £35m St Helens transport hub plan

Vinci lined up for project forming part of £100m town centre regeneration
3 days ago

Firms called for input on £108m Selsey coastal defence scheme

10-year construction plan to combat failing sea walls and eroding beaches
4 days ago

Renamed Bovis Construction suffered £16m loss last year

Firm slumped into red before being sold to US group Atlas Holdings
4 days ago

Plans in for £1bn Liverpool Street Station scheme

21-storey offices above station main concourse to help fund upgrade
4 days ago

Project director leaves giant McAlpine car battery site

Change in site team at flagship £4bn Agratas factory
4 days ago

Nexus Infrastructure orders up 11% at half-year

Tamdown housing civils arm orders up despite housing recovery delay
4 days ago

Five firms win £450m Scottish electricity network upgrade

Major investment by Energy company SSEN Distribution
5 days ago

Contractor services