Laing O’Rourke completes first HS2 bridge in two days

Grant Prior 4 years ago
Share

Laing O’Rourke joint venture LM has completed the installation of a 65-metre bridge over the M42, in just two days forming the first permanent structure to be delivered for HS2.

The job was carried out by engineering specialist Expanded, working on behalf of HS2 enabling works contractor, LMJV (Laing O’Rourke and J. Murphy & Sons Joint Venture).

The 2,750 tonne bridge structure was carried along the motorway on a self-propelled modular transporter.

The 448-wheel transporter took just one hour and 45 minutes to move the bridge span 150 metres into position, where it was affixed to a composite concrete deck to complete the overall bridge structure.

The successful installation marks the completion of the first of four bridges to be built close to the new Interchange Station at Solihull.

It will form part of the major remodelling of the regional road network to improve the circulation of traffic around the HS2 railway line and connect the existing road network to the new Interchange Station.

Mark Thurston, HS2 Ltd’s CEO said: “This new road bridge is the first permanent structure to be installed along the route of Britain’s new railway, so today represents an important milestone for the project and the West Midlands region.

“Constructing the bridge off site and using innovative engineering practices to install it over the motorway enabled us to carry out the work in just two days, keeping disruption to a minimum for road users”.

Simon Russell, LM project director, said: “This is British construction design and engineering innovation at its finest.

“Major components of the bridge and its supports were built offsite under safe, high quality conditions, then transported to site for assembly.

“Advanced digital capabilities allowed us to design all elements of the structure in a virtual world, before building it for real.”

The new road bridge over the M42 was built using a Design for Manufacture and Assembly (DfMA) strategy.

Expanded Structures led the construction programme on site, with 1,610 tonnes of precast and insitu concrete delivered, including 115 modular abutment shells and 298 precast deck components.

These major structural elements of the bridge supports and deck were made at Laing O’Rourke’s Centre for Modern Construction (formerly EIP) in Nottinghamshire.

Regional supplier Cleveland Bridge supplied 1,130 tonnes of steel plate girders.

Peter Lyons, Business Unit Leader, Expanded, said: “Offsite manufacturing and modular construction offer substantial benefits in terms of greater efficiency, higher quality, safety, and reduced time on site and disruption to local communities and road users.

“By delivering factory made components and assembling them on site, we have constructed abutment walls in 5 days, compared to between 8-12 weeks for traditional methods, achieved with a site team averaging just eight operatives.”

Later this year, a similar operation will take place to position a bridge over the A446, also as part of remodelling of road networks around the future Interchange Station.

The LM team will also be installing two further bridges which will span the high-speed line itself.

 

 

Latest news

Ridge buys rival consultant Jubb

Acquisition will see 100 new staff join Ridge
1 hour ago

Enabling works to start £130m Huyton town centre regen

Phase one includes a new council HQ, hotel and 72 flats
2 hours ago

Grainger build to rent pipeline rises to £1.4bn

Rental specialist buys sites in Sheffield and Cardiff to build 600 rental homes
2 hours ago

Kier wins Cambridgeshire County council estate upkeep

Firm will provide building and M&E services to 106 buildings across the county
1 hour ago

Louvres and solar shading specialist files for administration

Hampshire based ALPS lodges court notice after 25 years in business
2 hours ago

Speedy Hire posts a loss in latest results

Hire giant confident of better performance in next six months
2 hours ago

Esh to lead next phase of Riverside Sunderland regeneration

Infrastructure work will allow further development of Sheepfolds area
1 hour ago

Green light for £1.3bn Edinburgh coastal town revamp

First phase of Granton Waterfront scheme will see Cruden Homes create a new community
19 hours ago

Vistry chief operating officer steps down

Earl Sibley exits as his COO role axed for more direct reporting to CEO
1 day ago

House builder Camstead goes into administration

Work stopped on three current sites
2 days ago

Death of piling legend Roger Bullivant

Industry innovator dies after long illness aged 85
1 day ago

ESS Modular went down owing suppliers £7m

Modular specialist owned by ISG owner Cathexis
1 day ago

Builders back farmers in inheritance tax protest

"A rethink is desperately needed" say National Federation of Builders
1 day ago

Willmott Dixon wins £36m leisure centre upgrade

Work to start on historic Westminster 1930s Grade II listed Seymour Centre
1 day ago

Graham wins £100m Cardiff Crossrail phase 1

Work on route to Cardiff Bay to start before end of next year
2 days ago

Laing O’Rourke appoints new European MD

Peter Lyons to take-up new role in February
3 days ago

Profits dip at Stepnell ahead of demerger

Turnover and secured workloads up ahead of restructure
3 days ago

HS2 green bridge deck takes shape

100m-wide wildlife bridge to carry hedgerows and country lane over HS2
2 days ago

1,000-home Wolverhampton city centre scheme in for planning

ECF and council advance City Centre West build to rent scheme
3 days ago

Sisk clinches £54m North London council HQ revamp

Haringey's iconic Grade II listed civic centre to be brought back into use
3 days ago

Ofgem approves £2.5bn Eastern Green Link 1

Work to start next Spring on cable project from Scotland to the north of England
3 days ago

Anglian Water hunts for £1bn delivery partner

Programme delivery partner wil integrate with client team over 15-year plan
3 days ago

Hadden collapse costs supply chain £6.7m

"Highly unlikely" subcontractors will receive anything for their unpaid invoices
3 days ago

Management buyout at M&E specialist

£25m turnover Kimpton in second MBO in its 60-year history
3 days ago

BAM finalises £71m deal to replace first major RAAC school

Work to start on new St Leonards Catholic School in Durham
3 days ago

Scaffolder hit by two tonne weight at nuclear plant

Court hands out £633,000 in fines after Dungeness B decommissioning incident
3 days ago

Go-ahead for 860,000 sq ft East London medical campus

Whitechapel Road scheme of six new and repurposed buildings
3 days ago

Site labour rates hit record high as cost inflation returns

Industry's biggest payroll firm says rates rose nearly 5% last month in London
6 days ago

Morris & Spottiswood acquires part of ISG fit-out division

ISG Cathedral acquisition saves 111 jobs and expands presence across England
7 days ago

New work drives Q3 construction output uplift

Third quarter activity up 0.8% despite slowdown in September
6 days ago

Contractor services