Each turbine features 49 metre blades and 75 metre towers and is moved using four axle extendable flat trailers and specialist Scheuerle clamp trailers.
The Collett team Team also employed three Nooteboom Super Wing Carriers to facilitate the movement of the 49m long blades.
Quadruple extendable from 18.65m to 64.3m, these trailers offered the ideal solution for the blades, providing a 60-degree steering angle and significantly more suspension travel for extra ground clearance and added platform stability.
Beginning in July and working to a nine-week schedule Collett will cover a total of 11,500 miles, safely delivering each of the cargoes to the awaiting 750 tonne main installation crane on site.