A 10-storey concrete core on a Salford luxury private flats scheme is being demolished after serious flaws were uncovered midway through construction.

Service core that is being demolished
Service core that is being demolished

Developer Property Alliance Group has decided to demolish the concrete core of the largest of three planned clustered buildings because of concerns about the amount of rebar in the base.

The Manchester Uptown scheme on the wider Irwell Riverside site will consist of three sloping towers containing over 150 flats, fabricated as modules offsite and fitted around the three cores.

The Enquirer understands the core base was not strong enough and the developer alerted Salford Council.

Sources estimate the core may have cost £3m-£4m to build.

The condemned structure was built by civil engineering contractor Bemus Construction Services, which fell into administration three weeks ago with the loss of around 100 jobs.

But insiders say the problems stem from rebar design rather than build issues.

How the Uptown Manchester scheme will look when finished

A spokesperson for Alliance said: “Our project team has identified engineering issues at Uptown, so our priority is to rectify these as safely and efficiently as possible.

“This will require partial demolition of the development.”

The demolition work, which is being carried out by local firm PP O’Connor, will take around two weeks.

In the meantime, the off-site element of the construction programme will continue to reduce programme delay.

“This is an unfortunate situation, but we would like to reassure the local community that the site is safe and we are doing everything we can to minimise any potential disruption,” said the Alliance spokesperson.

“We will ensure residents are kept informed throughout the works and members of our team are available to address any queries or concerns.

“Although it is too early to confirm how this will impact the construction programme, we are confident the issues will be resolved quickly, avoiding a significant delay.”

Contractor FK Group is delivering the project.

 

Latest news

Universal Civils and Build picks-up another ISG job

Contractor to complete Wilson Sports Village in Clayton-le-Moors
4 hours ago

Prep work starts for vast HS2 box slide under A46

Freyssinet designed system will push 14,500t box under Kenilworth Bypass
1 day ago

Downing Construction hit by third year of losses

Building safety works and problem student job tip Liverpool builder £5.8m into red
9 hours ago

Problem contracts make it another tricky year for Taziker

Infrastructure specialist confident restructure and new strategy now paying off
10 hours ago

£250m Stockport homes scheme set to start

Oak Construction to deliver first block in 440-flats scheme
9 hours ago

Morgan Sindall wins Canary Wharf office-to-labs job

Construction to start this month on £65m conversion
1 day ago

Building stone firm ignores silica dust safety warnings

Workers at risk after manufacturer ignores HSE improvement notices
10 hours ago

Resi developer Sheen Lane heading for administration

Richmond based firm has a turnover of £50m
1 day ago

Building safety act adding six months to delivery times

New approval gateways slow student room development programmes
1 day ago

Five contractors win £550m airfield framework deal

MAG picks team for Manchester, Stansted and East Midlands airports
1 day ago

Galldris bounces back to strong profits

South east civils specialist gets trading margin up to 11%
1 day ago

Management buyout at Midlands contractor

Family business GI Sykes sold to management
1 day ago

Taylor Woodrow wins Wolverhampton city centre revamp

£19m contract will last two-and-a-half years
1 day ago

Morgan Sindall contracts league champion for second year

Kier ranks second in closely contested race between majors
2 days ago

New Year layoffs as Scottish modular house builder collapses

East Ayrshire Connect Modular falls into administration
2 days ago

Thames Water bidders day for £2.2bn reservoir scheme

Tenders to be invited in October for new Abingdon reservoir in Oxfordshire
2 days ago

Buckingham Plant Hire quits heavy kit market

Firm to sell fleet and focus on lighter, sustainable plant
3 days ago

Clients ‘ignoring building safety’ reforms

Clients still subjecting contractors to aggressive and sub-economic pricing
2 days ago

Castleforge plans expansion after £100m data centre deal

Investor moves into booming data centre market
2 days ago

Construction output growth drops to six-month low

Subcontractor rates rise at fastest rate for 18 months
3 days ago

Suir Engineering swoops for Scottish M&E contractor

Irish M&E firm launches UK expansion with Taylor & Fraser acquisition
3 days ago

Aggregates supply firm files administration notice

Ashville Aggregates and Concrete operates across London and South East
3 days ago

Plans in for 44-storey Manchester resi tower

Developer Glenbrook to appoint contractor this year
4 days ago

Briggs & Forrester names new engineering services MD

Will Newman replaces Ian Lawrence who steps down after eight years
3 days ago

Morgan Sindall bags Salford Uni acoustics building

Planning submitted for Acoustics Building at Crescent Innovation area
4 days ago

Lambeth to release six sites for £250m homes plan

Call for development partner to deliver 450 mixed tenure homes
3 days ago

Adrian Speller joins brother as joint MD of Midlands builder

Speller Metcalfe boosts senior leadership team
4 days ago

Winner unveiled for £2.9bn aqueduct revamp

Construction costs for Haweswater Aqueduct rise to £2.9bn from £1.75bn
7 days ago

Fortem and Equans face fight for £3bn housing upkeep deal

Birmingham City Council aims to sign new 10-year deals for four regions
4 days ago

Lendlease strikes deal to sell UK construction arm for £35m

US private equity firm Atlas to finalise purchase deal by summer
1 week ago

Contractor services