Stepnell accounts hit by £30m of problem contracts

Grant Prior 4 years ago
Share

Stepnell has restated its 2019 accounts by £30m to reflect “grossly underestimated” forecast losses on problem contracts.

The adjustment means a previously stated small pre-tax profit for the year to March 31 2019 now becomes a £29.9m loss.

The updates were revealed in the firm’s latest results posted at Companies House.

External consultants were brought in by Stepnell directors to review contracts.

The company said: “In an number of instances, forecast losses on challenging contracts had been grossly understated.”

The strategic report at parent company Stepnell Holdings said the problems had been caused by “poor management procedures and inconsistent pricing.”

It added: “The directors have therefore had to remove under-performing staff, reduce the number of regions from five to three and impose tighter management controls on cash management, bidding and various construction activities.

“Directors are confident that the final legacy projects are being worked through and that the losses these projects have inflicted on the company are now under control.

“Directors expect Stepnell to return to profit in the current year.”

Latest results for the year to March 31 2020 show a group pre-tax loss of £3.4m from turnover of £127.6m.

Tom Wakeford, joint managing director of Stepnell said: “In 2019, we were impacted by onerous ground conditions on our largest project, which has proved expensive to remedy.

“We have taken a prudent position in our accounts, allowing our team to focus on the financial recovery on the project. March 2020 saw a write down of legacy contracts due to Covid-19 which had a profound effect on our clients and our sector as a whole.

“Therefore, 2019 and 2020 were difficult years for different reasons. The 2019 losses are now more than two years old and Stepnell looks very different, in a very positive way, in 2021, with an anticipated rise in profit to around £1 million.”

Latest news

Fall in office and housing activity dents industry output

Confidence fragile after 0.2% dip in output for second month
14 minutes ago

Lendlease OK’d to start Birmingham’s £1.9bn Smithfield scheme

First phase of 400 build to rent homes at Manor Square approved
48 minutes ago

Fresh plan for £170m Newcastle resi tower and hotel

Gainford Group scales down New Bridge Street scheme to 29 storeys
37 minutes ago

Mace confirmed for £140m Gatwick Airport Pier 6 extension

Contractor PJ Hegarty has started enabling works in middle of busy airport
17 hours ago

Cost of M3 upgrade soars by £80m

Budget for VolkerFitzpatrick/Balfour Beatty road job jumps to £280m
1 hour ago

Graham takes on ISG £45m Coventry cultural hub job

Firm will start conversion work in the Spring on former IKEA store
18 hours ago

Alun Griffiths to “restructure and resize” after £95m loss

Redundancies due to be announced at Welsh civils contractor
2 days ago

Fire safety project approval delays hit Van Elle profits

Piling specialist also reviews future of Canadian operation amid fresh economic uncertainty
1 day ago

JRL Malaysian backers plan £150m London city office refurb

Ardmore set to deliver landmark 25 Finsbury Circus building overhaul
1 day ago

500-home block to replace 19 storey Sutton office tower

Landmark project to deliver 312 Build to rent and 195 co-living homes
1 day ago

Building envelope specialist Bailey buys Comar

Specialist now offers complete building envelope solutions
1 day ago

Subcontractors wanted for work across Wales

Big name buyers at latest Constructionline event: Register now
1 day ago

Balfour Beatty profit dented by £83m building safety hit

Increased order book at £18bn secures growth over next two years
2 days ago

Expanding utilities specialist Ipsum buys Matrix Power

Power engineering contractor takeover will strengthen offer in North East
2 days ago

Historic scaffolding firm files administration notice

Hertfordshire based Rodells has been trading since 1898
2 days ago

Planning Bill to have “seismic” impact on construction

Building-boosting reforms go before Parliament
3 days ago

Briggs & Forrester hits record revenue and orders

M&E specialist rebounds with strong growth across three divisions
2 days ago

Man Utd confirm plan for £2bn ‘super-tent’ stadium

Club to press ahead with 100,000-seat 'Wembley of the North'
3 days ago

Government spending keeps profits edging-up at Kier

91% of work now with public sector and regulated companies
3 days ago

Costain on track for step change to 5% margin

Alex Vaughan says order book has jumped £1.5bn to £5.4bn
3 days ago

Mace tops February contracts league

Confirmation of £300m London Victoria Street project lifts firm to pole position
3 days ago

Wates raids Laing O’Rourke for new construction operations chief

George Mosey leaves Laing O'Rourke after 16 years
4 days ago

Travis Perkins CEO Pete Redfern steps down due to ill health

Redfern joined builders' merchant last year after 14 years at Taylor Wimpey
4 days ago

Morgan Sindall wins £61m Liverpool lab scheme

Construction to start this Autumn on latest Knowledge Quarter project
3 days ago

Glencar to build timber-framed office block

Work to start next month on 79,200 sq ft scheme in Maidenhead
4 days ago

Shed specialist Marbank files administration notice

£67m turnover portal-framed building specialist files court notice
4 days ago

Birmingham council submits £1bn Druids Heath plan

High rise estate to be replaced by-3,500 home eco village
4 days ago

Cannabis farm gang posed as utilities contractor

Gang jailed for 28 years after diverting power to more than 100 cannabis farms
6 days ago

Firm fined after workers climb scaffold without ladder

HSE investigation prompted by death on Liverpool site
4 days ago

Clancy renews £250m Southern Water deal

Contractor vows to maximise value for money and minimise disruption
4 days ago

Contractor services