First ‘smart contracts’ used to limit bad weather risk

Aaron Morby 3 years ago
Share

Civils contractors BAM Nuttall and Ferrovial Construction are testing first-generation construction ‘smart contracts’ to reduce project programme risk from growing extremes of weather.

Cutting edge digital technologies are being used to measure and minimise weather risk on projects
Cutting edge digital technologies are being used to measure and minimise weather risk on projects

Under the new smart contracts, the old method of painstakingly collecting weather data to explain challenges and delays to project programmes is over.

A new system has been trialled on several projects from Dawlish Sea Wall to Stubbington Bypass and an HS2 enabling works site. It has provided both contractors and clients with simultaneous real-time local site weather data to pinpoint  ‘1 in 10 compensatable weather events’ used in standard form contracts like the NEC.

During the project, five compensation claims were triggered across four study sites, with the largest claim accounting for 21 weeks.

UK-based startup EHAB has developed the Weather Ledger solution that collects data in real-time and triggers various notifications for extremes instantly.

Both contractors are separately putting the system through its paces on projects as part of a trial funded by Government R&D body Innovate UK.

The smart contracts set up behind the monitoring system are being hailed as saving time and money, as well as also enabling a total reduction in the cost of weather risk through more effective risk-sharing.

It comes as data suggests 17% more rain is falling on rainy days and flood risk has increased 20-90% across the UK, according to EHAB.

The developers of the system are also exploring how to allow client and contractors to more effectively share the upside of fine weather.

A spokesman for EHAB said: “This “pay as you go” weather risk distribution could save the client money upfront and help contractors offer a more competitive price, while still providing clear cost parameters.

“We are also in talks with major insurers who could seek to underwrite the downsides of weather delay through a Parametric Insurance add-on to the smart contract.

“This could see the total weather risk of a project, or portfolio, capped. This may be an increasingly attractive proposition as more of the downsides of the climate crisis are realised by the industry.”

 

Smart contract


It’s smart because the software automatically collects the weather data collected from weather stations on site, calculates the values and will then notify, in a legally compliant way, both parties if an event has indeed occurred.

It’s a contract because both parties agree that they defer the management and operation of that specific part of the contract to the EHAB Weather Ledger.

Latest news

Ridge buys rival consultant Jubb

Acquisition will see 100 new staff join Ridge
1 hour ago

Enabling works to start £130m Huyton town centre regen

Phase one includes a new council HQ, hotel and 72 flats
2 hours ago

Grainger build to rent pipeline rises to £1.4bn

Rental specialist buys sites in Sheffield and Cardiff to build 600 rental homes
2 hours ago

Kier wins Cambridgeshire County council estate upkeep

Firm will provide building and M&E services to 106 buildings across the county
1 hour ago

Louvres and solar shading specialist files for administration

Hampshire based ALPS lodges court notice after 25 years in business
2 hours ago

Speedy Hire posts a loss in latest results

Hire giant confident of better performance in next six months
2 hours ago

Esh to lead next phase of Riverside Sunderland regeneration

Infrastructure work will allow further development of Sheepfolds area
1 hour ago

Green light for £1.3bn Edinburgh coastal town revamp

First phase of Granton Waterfront scheme will see Cruden Homes create a new community
19 hours ago

Vistry chief operating officer steps down

Earl Sibley exits as his COO role axed for more direct reporting to CEO
1 day ago

House builder Camstead goes into administration

Work stopped on three current sites
2 days ago

Death of piling legend Roger Bullivant

Industry innovator dies after long illness aged 85
1 day ago

ESS Modular went down owing suppliers £7m

Modular specialist owned by ISG owner Cathexis
1 day ago

Builders back farmers in inheritance tax protest

"A rethink is desperately needed" say National Federation of Builders
1 day ago

Willmott Dixon wins £36m leisure centre upgrade

Work to start on historic Westminster 1930s Grade II listed Seymour Centre
1 day ago

Graham wins £100m Cardiff Crossrail phase 1

Work on route to Cardiff Bay to start before end of next year
2 days ago

Laing O’Rourke appoints new European MD

Peter Lyons to take-up new role in February
3 days ago

Profits dip at Stepnell ahead of demerger

Turnover and secured workloads up ahead of restructure
3 days ago

HS2 green bridge deck takes shape

100m-wide wildlife bridge to carry hedgerows and country lane over HS2
2 days ago

1,000-home Wolverhampton city centre scheme in for planning

ECF and council advance City Centre West build to rent scheme
3 days ago

Sisk clinches £54m North London council HQ revamp

Haringey's iconic Grade II listed civic centre to be brought back into use
3 days ago

Ofgem approves £2.5bn Eastern Green Link 1

Work to start next Spring on cable project from Scotland to the north of England
3 days ago

Anglian Water hunts for £1bn delivery partner

Programme delivery partner wil integrate with client team over 15-year plan
3 days ago

Hadden collapse costs supply chain £6.7m

"Highly unlikely" subcontractors will receive anything for their unpaid invoices
3 days ago

Management buyout at M&E specialist

£25m turnover Kimpton in second MBO in its 60-year history
3 days ago

BAM finalises £71m deal to replace first major RAAC school

Work to start on new St Leonards Catholic School in Durham
3 days ago

Scaffolder hit by two tonne weight at nuclear plant

Court hands out £633,000 in fines after Dungeness B decommissioning incident
3 days ago

Go-ahead for 860,000 sq ft East London medical campus

Whitechapel Road scheme of six new and repurposed buildings
3 days ago

Site labour rates hit record high as cost inflation returns

Industry's biggest payroll firm says rates rose nearly 5% last month in London
6 days ago

Morris & Spottiswood acquires part of ISG fit-out division

ISG Cathedral acquisition saves 111 jobs and expands presence across England
7 days ago

New work drives Q3 construction output uplift

Third quarter activity up 0.8% despite slowdown in September
6 days ago

Contractor services