Pingdemic intensifying supply chain shortages

Grant Prior 4 years ago
Share

Construction materials leaders are warning that supply chain shortages are being exacerbated by the NHS Covid app ‘pingdemic’.

The latest problems were highlighted in a statement from the  Construction Leadership Council’s Product Availability working group.

It’s update warned that “labour shortages are being exacerbated by the growing number of non-symptomatic drivers, tradespeople, merchant and manufacturing staff required to self-isolate after coming into contact with someone who tested positive for Covid-19. This will further stretch the supply chain.”

The statement penned by John Newcomb, CEO of the Builders Merchants Federation and Peter Caplehorn, CEO of the Construction Products Association gave a thorough run down of current problems and pinch points in the supply chain.

It said: “The basic trends of the last six months remain, with global demand far in excess of supply leading to product shortages, rapid and sustained price inflation, long lead times and uncertainty regarding deliveries.

“It is also clear that the global shipping industry is far from recovered from the disruption caused by the coronavirus pandemic, with congested shipping routes, container cancellations and higher costs still evident.

“The products most affected are those used in housebuilding and domestic repair maintenance and improvement (RMI), including roofing products, timber, insulation, landscaping products, blocks, sealants/PVA, PIR Insulation, kitchen carcassing and products that use plastic, e.g. drainage, some windows and bagged cement.

“Bagged cement is particularly hard hit due to ongoing unprecedented demand but both bagged and bulk cement are on allocation; there are regional variations to this with some areas affected more than others. All UK kilns are operating but it may be a while before stocks return to normal. With high demand continuing, extended delivery times are expected to remain until the end of the year.

“The high level of housing starts has caused a bow wave of demand for plastic pipes for groundworks and drainage. Some manufacturers are currently on allocation, but the expectation is that supply issues will be resolved by the end of Q3.

“Demand for wood and wood products remains very strong and timber supply will continue to tighten into Q3, following the Scandinavian holiday and maintenance season in July, continuing the upward pressure on prices.  There are some indications that the situation may start to improve after this as global demand is beginning to ease.

“Within infrastructure and commercial construction, steel and aluminium are both experiencing significant supply disruption and price inflation.

“There is also concern around the availability of steel cabling management systems which could continue into early 2022 and engineering services business are advised to plan ahead.

“Overall, prices for products and materials have increased by a reported 10-15%, consistent with the Office of National Statistics figure for May of 10.2% overall with 12.8% for those most commonly used in RMI.  Specific products, especially timber, has seen increases of 20-50% for most products and over 100% for OSB and other sheet materials. For the first time we have had reports that some merchants are destocking certain products that are no longer economic.

“Labour, or rather the lack of it, is a rising concern.  All regions report hauliers/HGV/LGV drivers are in short supply and very difficult to recruit, which is contributing to longer delivery times particularly away from major transport routes and urban areas.  We continue to support the Road Haulage Association in its discussions with the Department of Transport to address the shortage.  We are now receiving reports of other vacancies being hard to fill, from relatively unskilled roles, such as yard operatives, to experienced bricklayers.

“These labour shortages are being exacerbated by the growing number of non-symptomatic drivers, tradespeople, merchant and manufacturing staff required to self-isolate after coming into contact with someone who tested positive for Covid-19. This will further stretch the supply chain.

“Looking forward, housebuilders are managing current builds to completion but there are indications that smaller, regional developers may be forced to delay starting work on new sites until they have more certainty around product availability and lead times.

“The demand for home improvement and RMI work remains strong but most work in this area is covered by JCT contracts which have no facility for any flexibility on material costs, leading to fears that we will see business failures arising from unsustainable contracts.  This is now being investigated and may require a change in contractual positions.

“Alongside pricing, stability and accuracy of supply remains the overarching concern and regular, accurate and transparent communication throughout the supply chain to the end client is deemed vital by all.  It is important that all parties recognise the extent of the extraordinary challenges we are currently experiencing and adopt a flexible and collaborative approach to finding solutions.”

Latest news

Plan for film studios switched to data centre cluster

Plans in for six data centre buildings in Buckinghamshire
23 hours ago

Hunt for firm to deliver £75m Cambridge Civic Quarter

Work includes £41m Guildhall and £21m Corn Exchange revamps
7 hours ago

Plans in for £200m Middlesbrough regen scheme

Wates is lined up to deliver landmark Gresham rental homes scheme
7 hours ago

£600m Bristol shopping centre redevelopment approved

Galleries centre will be demolished for homes and offices quarter
8 hours ago

Ant Yapi lands ultra prime London homes job

Prestige scheme replicates Regency mansions around nearby Regent’s Park
8 hours ago

CITB survives another review

Report published after two more years talking about skills crisis
23 hours ago

Strucktor wins record M&E package from Ardmore

Major subcontract on £240m Tribeca life science development
8 hours ago

Over 800 high-rise resi jobs stalled by safety regulator

Building safety regulator project logjam hits Government growth plan
1 day ago

McAlpine under fire after another panel comes loose from hotel

High winds cause more problems at recently completed Woking hotel
2 days ago

McGee starts demolition for £500m South Bank scheme

Former ITV studios will be replaced by two office towers
1 day ago

Four arrested after hospital construction site burglary

Damage and copper wiring stolen at Hinckley and District General Hospital new building
2 days ago

Caddick kicks off Digbeth regen plan with £43m flats job

First phase 211 flats job starts wider £260m Upper Trinity Street scheme
1 day ago

Sisk starts work on £300m Children’s Cancer Centre

Great Ormond Street Hospital job will employ 500 on site and last three years
1 day ago

McAlpine clinches £1.25bn Port Talbot low carbon steelworks job

Deal to build one of the largest electric arc furnaces in the world
3 days ago

McLaren to build top-down on £60m New Bond Street contract

Contractor working to tight technical guidelines on busy Mayfair site
2 days ago

Project delays dull Van Elle first-half results

Piling specialist upbeat about year ahead as order book up 24%
2 days ago

Aggregate Industries appoints new contracting chief

Kevin Murgatroyd promoted to new role
2 days ago

Bouygues wins Immingham £170m import jetty job

French civils firm to build bulk ammonia import facility for hydrogen economy
3 days ago

Plans in for latest phase of Leith port revamp

Construction to start this year on transforming waterfront
2 days ago

Avant Homes starts redundancy consultation

Jobs under threat at Central region
3 days ago

Plans in for Barnet leisure park and 1500 homes

Regal to redevelop Great North Leisure Park in Finchley
3 days ago

JRL wins shell and core for £400m London scheme

220 Blackfriars Road project will rise to 21 and 15 storeys
4 days ago

Robertson strengthens East Midlands leadership

Woodcock promoted to ops director and Brown joins from BAM as commercial director
3 days ago

Match-maker service for stalled S106 housing projects

Clearing website to release logjam of unbuilt developer affordable home commitments
3 days ago

Turnover flat as Glencar rethinks strategy

Industrial and logistics building specialist targets "the right type of work"
4 days ago

McLaren lures another director from McAlpine

Glen Harding to help grow recently launched construction management division
4 days ago

£200m Edinburgh Lloyds HQ redevelopment plan

Landmark Port Hamilton building revamp is Edinburgh's largest ever pre-let deals
3 days ago

Chinese super embassy plan edges closer to go-ahead

Met Police drop concerns about Royal Mint site next to Tower of London
4 days ago

GMI delivers just £1m profit after clearing legacy job

Revenue falls 29% to £232m after 'controlled consolidation'
4 days ago

Construction set for gradual two-year recovery

Construction Products Association says Government will need to deliver on pro-growth strategy
4 days ago

Contractor services