Delays and cost hikes hit Balfour Highlands rail job

Grant Prior 4 years ago
Share

Balfour Beatty has been forced to push-back the completion date of its £16m contract to repair the UK’s highest railway.

The Scottish Government’s Highlands and Islands Enterprise (HIE) agency has confirmed the Cairngorm furnicular will not reopen until the “second half of 2022.”

The railway at the ski resort was due to reopen early next year following strengthening work on the 1.9km viaduct that supports the track.

Balfour began work in April 2021 but delays have arisen due to “technical challenges associated with designing and implementing effective solutions to an existing structure, as opposed to a new build.”

Work has also been hampered by the impact of Covid and extreme weather including blizzard conditions in the spring.

HI added that “extra effort has also been required to source vital construction materials that are currently in short supply across the UK.”

HIE interim chief executive Carroll Buxton said: “We’ve always been upfront in describing the reinstatement programme as one of the most complex and difficult civil engineering projects in Scotland.

“As well as managing technical challenges, the team has to take great care to protect the mountain environment, and deal with difficult terrain and extreme weather conditions that can quickly become hazardous.

“The original schedule was very ambitious, even without the impacts of the pandemic lasting as long as they have and before the more recent problems in sourcing construction materials of suitable quality.

“With limited time available to complete these works before winter, postponement has become inevitable.”

The funicular was built by Morrison Construction and opened in 2001 but was taken out of service in 2018 after an engineers’ inspection identified structural defects that raised safety concerns.

Buxton said: “We’re now working with our designers and contractors on a revised schedule for the remainder of the project.

“Harsh mountain conditions mean that all work will need to halt over winter and resume next spring. To ensure safety, there also needs to be a period of testing and certification at the end of the programme, so our current expectation is that the funicular can be relaunched in autumn 2022.

“Clearly, a longer timescale will also have a financial impact. We’ll be reviewing costs very carefully and will publicly confirm a revised budget as soon as it’s possible to do so.”

HIE has also approved up to £780,000 for an extensive refurbishment of the Ptarmigan building that sits on the plateau and includes the UK’s highest restaurant, a shop, exhibition space and viewing platforms.

Following competitive tender, resort operator Cairngorm Mountain (Scotland) Ltd (CMSL) has awarded a contract for the first phase of the Ptarmigan works to Simpson Builders Ltd, based in Beauly. The refurbishment is due to start at the end of August and be completed by the end of 2021.

 

Latest news

Breyer Group files administration notice

Staff hope rival firm could buy assets and save jobs
15 hours ago

Peel Ports reveals winners for £750m framework

18 firms win places on deal: Full list
13 hours ago

Wates wins fit-out for Manchester First Street Hub

Smartspace arm secures another Government hub deal
13 hours ago

Big trade names dropped in M Group rebrand

Acquisitive group formed from Morrison Utility services in 2016
11 hours ago

Former Severfield director takes helm at Embrace Steel

New CEO Martin Kelly aims to step up expansion of steelwork contractor
16 hours ago

£302m upgrade funding awarded to FE colleges – list

Cash shared out between England’s 179 college groups
15 hours ago

FK Facades thrives but construction arm hit by ISG row

Dispute with failed contractor costs specialist £5.5m
16 hours ago

Galliford Try gets go-ahead for Milton Keynes PRS tower

33-storey tower needs gateway 2 approval before work can start
1 day ago

Small house builders get £150m funding for green homes

Developers will have to meet-up to ten new criteria to benefit from interest rate discounts
16 hours ago

Lendlease Construction renamed Bovis

US private equity firm completes £35m purchase of UK contracting business and rebrands
2 days ago

Breyer Group battles for survival as rivals circle

Housing maintenance firm fights three winding up petitions in a month
2 days ago

Careys facing £2.4m claim by developer over demolition cartel

Giant Hong Kong developer claims it was overcharged on Lots Road Power Station job
2 days ago

Multiplex profit drops a third as revenue rises to £780m

Spate of new orders sets contractor up for three years of work
2 days ago

Galliford Try and Breheny land latest Sizewell C road deals

More infrastructure deals for new nuclear power station
2 days ago

Worker trapped in collapsed septic tank pit

Contractor and director fined after worker suffers multiple fractures
2 days ago

Homes England buys stalled Broad Marsh site

Demolition to finally be completed as developer hunt begins
2 days ago

Vistry go-ahead for 353 homes at Rochester Riverside

Work to start on next phase of Kent town regeneration at end of this year
3 days ago

M&E firm J S Wright collapsed owing £19m

Trade creditors hit for £11.4m by employee-owned Midlands firm
3 days ago

Right to work checks to be extended to self-employed

Government plans crackdown on illegal working and rogue employers
3 days ago

Midlands developer turns to London with £1bn resi schemes trio

SevenCapital plans 1,000 flats in Kensington, Islington and the Isle of Dogs projects
3 days ago

Deck falls off huge scissor lift at Winvic site

Two men seriously injured as platform plunges to the ground
5 days ago

Weston targets Build to Rent with new division

Weston Partnerships signs first deals with asset managers and councils
3 days ago

Bouygues seals deal for £119m Cardiff college campus

Construction to start in June on two new buildings
5 days ago

£140m cash injection to speed-up flood defence schemes

Funding part of £2.65bn investment over the next two years
3 days ago

Bid race starts for £15bn schools framework refresh

DfE throws framework open to more contractors
6 days ago

Berkeley’s £600m Borough Triangle project approved

Controversial scheme features two towers of 38 and 44-storeys
6 days ago

London Mayor calls in blocked 600-bed student scheme

Refused 20-storey London PBSA block may still be built
6 days ago

HG to build 500-bed London Stratford student scheme

Work will start later this year subject to gateway 2 safety approval
6 days ago

Arrest after pedestrian death on construction site

Tragedy during site preparation works for new Wigan car park
6 days ago

British Steel threatens closure of Scunthorpe blast furnaces

Chinese owners say sectional steel and rail supplies will be maintained
6 days ago

Contractor services