Cleveland Bridge UK collapsed owing over £21m

Aaron Morby 3 years ago
Share

Administrators for collapsed steelwork contractor Cleveland Bridge have revealed the operation owes over £21m to creditors.

Cleveland Bridge also struggled to pass on steel price hikes to all its customers
Cleveland Bridge also struggled to pass on steel price hikes to all its customers

Insolvency practitioners from FRP have set out their best estimate of debts while they wait for a detailed return from directors setting out details of the contractor’s affairs.

Among the headline creditors, £6m is owed to the Arab National Bank, nearly £3m to HMRC and £2m to UK Export Finance.

Unsecured trade creditors are owed around £8m and company backer Al Rushaid Investment Company is due at least £3.8m.

In a report for creditors, administrator FRP said Cleveland Bridge had been sigificantly impacted by delays caused by Covid leading to exceptional costs of £1.7m.

The firm was also hit by a delay in a high margin contract due to the political coup in Sri Lanka.

The steelwork contractor was due to report a loss of £3.62m in 2020.

Among the specialist contractor’s mounting problems in early 2021, an estimation error on one contract resulted in an £11m project achieving a zero gross profit.

This contract made up the majority of production hours in the first quarter of the year.

FRP said that Cleveland Bridge had also failed to successfully pass on sharp steel price hike to all its customers.

As things deteriorated credit limits with suppliers holding credit insurance were reduced due to the poor trading.

In June, Cleveland Bridge engaged a team of turnaround specialists to restructure the business as managing director Chris Droogan also handed in his resignation.

The process revealed that an extra £12m was required to fund the business to the end of this year.

But Cleveland’s Saudi Arabian owners refused to provide the extra funding leading to the historic bridge builders administration on 22 July.

FRP said unsecured creditors were not expected to see any of the cash they were owed.

 

Latest news

Demolition giant John F Hunt Group sold to staff

Chairman John Hall to remain at helm
15 hours ago

University of Warwick advances £700m campus plan

Enabling works to get underway for main build works next year
20 hours ago

Go-ahead for £750m East London data centre

Urban 11-storey data centre to be built next to River Lea and A13 in Newham
1 day ago

Keltbray Infrastructure Services buys Linbrooke rail arm

First deal since infrastructure business was bought by private equity this summer
2 days ago

Elizabeth Line wins Stirling Prize for architecture

Infrastructure scheme wins premier design prize
20 hours ago

Winners named for Worcestershire and West Mids framework

Deal covers development work from design to construction
19 hours ago

Piling starts on HS2 Curzon Street Station

Mace Dragados Joint Venture and Keltbray working on Birmingham site
20 hours ago

M Group joins top seven as revenue jumps to £2.2bn

Infrastructure services specialist continues to hunt acquisitions
2 days ago

BlackRock to take control of Lanes Group

Takeover of leading water contractor to complete this month
2 days ago

Yorkshire and Lincolnshire builders’ merchant goes under

1928-founded Builders Merchant Company hit by winding up petition
2 days ago

Trio wins £170m West Country new build housing deal

Curo Enterprise, E.G. Carter and Speller Metcalfe Malvern
2 days ago

Roofer dies in fall from potato box on forklift

Court hears how victim fell 16ft from makeshift platform
2 days ago

Clancy bolsters senior management team

Skanska project director Jon Arnold joins as operations director of energy
2 days ago

High tech construction plant could save country £417bn

Costain report says kit which connects and drives itself will provide a massive economic boost
3 days ago

Concrete frame defects cost Bellway another £14m

Cost of repairing Greenwich scheme rises while £5.4m was spent on aborted Crest Nicholson chase
3 days ago

Green light for 52-storey Isle of Dogs resi tower

460 flats One East Point project will be built at 3-4 Harbour Exchange
3 days ago

Contractors urged to “hire now” as labour supply crunch looms

Vacancies rise and wages grow as fight for new workers intensifies
3 days ago

Kier confirmed for £20m Yasa Motors Bicester HQ

Developer Bicester Motion advances future mobility business park
3 days ago

Data centres and airport expansion to spur growth

Government hails £25bn data centre and £1.1bn Stansted Airport expansion plan
3 days ago

Hinkley Point second reactor unit build up to 30% faster

Engineering team lifts last giant steel ring onto reactor 2 yesterday
3 days ago

BAM reassures supply chain after winding-up petition

Firm's credit rating temporarily affected after dispute with supplier
4 days ago

Winvic secures Leeds build to rent scheme

Phase one of £500m Sweet Street South Bank regeneration starts
4 days ago

£60m turnover construction group sold to staff

Meldrum Construction Services Group becomes Employee Owned Trust
4 days ago

Starmer vows to “rip out” obstacles to investment

Prime Minister to make pledge at inaugural International Investment Summit
4 days ago

VolkerFitzpatrick starts prep-work for £210m M3 junction upgrade

Main works to begin in early 2025 on Winchester junction job
4 days ago

London super sewer turned on after eight years of construction

£4.5bn project starts protecting River Thames from pollution
4 days ago

Housing and office new work jump fuels output recovery

August new construction work rebounds 1.6% after early summer fall
7 days ago

£300m London City fringe office tower approved

Rocket's 27-storey One Fairchild Street job set for take-off
1 week ago

Consultants named for London Tube Bakerloo Line extension

Aecom and architect WW+P to work up designs for four new stations
7 days ago

15 giant bridge beams lifted into place at HS2 station

Balfour Beatty VINCI carries-out civils work for Solihull station: Video
1 week ago

Contractor services