Administrators for collapsed steelwork contractor Cleveland Bridge have revealed the operation owes over £21m to creditors.

Cleveland Bridge also struggled to pass on steel price hikes to all its customers
Cleveland Bridge also struggled to pass on steel price hikes to all its customers

Insolvency practitioners from FRP have set out their best estimate of debts while they wait for a detailed return from directors setting out details of the contractor’s affairs.

Among the headline creditors, £6m is owed to the Arab National Bank, nearly £3m to HMRC and £2m to UK Export Finance.

Unsecured trade creditors are owed around £8m and company backer Al Rushaid Investment Company is due at least £3.8m.

In a report for creditors, administrator FRP said Cleveland Bridge had been sigificantly impacted by delays caused by Covid leading to exceptional costs of £1.7m.

The firm was also hit by a delay in a high margin contract due to the political coup in Sri Lanka.

The steelwork contractor was due to report a loss of £3.62m in 2020.

Among the specialist contractor’s mounting problems in early 2021, an estimation error on one contract resulted in an £11m project achieving a zero gross profit.

This contract made up the majority of production hours in the first quarter of the year.

FRP said that Cleveland Bridge had also failed to successfully pass on sharp steel price hike to all its customers.

As things deteriorated credit limits with suppliers holding credit insurance were reduced due to the poor trading.

In June, Cleveland Bridge engaged a team of turnaround specialists to restructure the business as managing director Chris Droogan also handed in his resignation.

The process revealed that an extra £12m was required to fund the business to the end of this year.

But Cleveland’s Saudi Arabian owners refused to provide the extra funding leading to the historic bridge builders administration on 22 July.

FRP said unsecured creditors were not expected to see any of the cash they were owed.

 

Latest news

Major Building Safety Regulator shake-up to end tower delays

HSE stripped of control and top fire chiefs brought in to fast-track stalled schemes
14 hours ago

Fox buys recycled asphalt specialist Fisher

Acquisition adds major recycled asphalt capacity in north west
7 hours ago

First steel goes up on giant car battery site

Severfield gets to work on McAlpine Somerset site
8 hours ago

Construction comeback to outpace wider economy

Arcadis forecast fueled by spending review optimism
11 hours ago

Hinkley trio sign Sizewell civils deal

Balfour,Bouygues and Laing O'Rourke form Civil Works Alliance for new power station
14 hours ago

£3.9bn data centre plan for Ravenscraig steelworks

Green energy to power massive new steel to silicon AI campus
15 hours ago

Breakthrough on HS2’s second longest tunnel

8.4 mile Northolt to Old Oak Common drive completes
15 hours ago

Neilcott on fast-track to debt-free employee ownership

£22.5m loan nearly paid down after big profit year
13 hours ago

TfL kicks off race for £700m Tube station upgrade

South Kensington and Elephant & Castle top the pipeline list
15 hours ago

Corbyn Plant Hire fleet goes under the hammer

Kit to be sold off by sister firm to collapsed groundworks contractor
14 hours ago

Government wields procurement stick on late payment

New rules would block slow payers from bidding on big public jobs
4 days ago

Hercules buys power line labour firm for £15.7m

Labour supply specialist snaps up Advantage NRG to tap booming electricity upgrade market
4 days ago

Universal bid to fast-track planning for theme park

Entertainment giant eyes 2026 start at Bedford site
4 days ago

Developer Breck to transform former Ibstock brick factory

Ravenhead works to become 300-home development
4 days ago

SP Energy Networks awards contracts worth £1.4bn

First round of awards under £5.4bn national electricity grid upgrade programme
4 days ago

Travelodge to convert Liverpool Street office building

Office-to-hotel conversion in City of London
4 days ago

Plans lodged for 1m sq ft City of London office

Barbican landmark building will reuse 40% of existing structure
4 days ago

PTSG acquires roofing specialist HD Sharman Group

Premier Technical Services Group expands building maintenance division
4 days ago

Balfour Beatty lands £833m carbon capture power plant job

Work to start later this year on Teesside carbon capture gas-fired power station
5 days ago

Svella agrees deal to save Cubby Construction

Solvent purchase set to save 214 jobs and protect supply chain
5 days ago

J Coffey holds line on margins despite £52m revenue slide

Pre-tax profit down 14% but firm eyes strong pipeline to bounce back
5 days ago

Consultants called up for £2.3bn NHS SBS panel reboot

Market asked for views ahead of next-gen procurement rollout
5 days ago

Hochtief launches new UK data centre division

German business model to be introduced for UK construction
5 days ago

Construction skills body launches with 100,000 worker target

Industry to work closer with Jobcentres to find new talent
5 days ago

Kier lands £42m Midlothian school and community hub

Contractor strengthens presence in Scotland with big education job
5 days ago

BESA audit blitz sees 14 specialist contractors suspended

Building engineering services trade body cracks down on standards
6 days ago

Engineers pull-off 220m HS2 viaduct slide in 3 days

Five-structure Northants sequence ends with 1,300t deck slide - video
6 days ago

Managing Director moves to advisory role at Shufflebottom

Alex Shufflebottom steps-down after acquisition by Embrace
6 days ago

JV North unveils winners of £500m housing blitz

Consortium gears up to deliver 3,000 new homes across North West
6 days ago

Partnerships builder Keepmoat names new chief executive

Ian Hoad to take reins as Tim Beale steps down after eight years
6 days ago