Crossrail told to wrap-up expensive Tier 1 contracts

Aaron Morby 3 years ago
Share

Public account committee MPs are warning that there is still no real certainty to the Elizabeth Line cost and opening schedule just four months before the first central section trains are due to operate services for the public.

Watchdog MPs have highlighted that Canary Wharf and Bond Street have had significant issues in the past and are yet to be completed.

While Bond Street has been taken off the critical path for limited first opening, MPs are still concerned about the full opening of Canary Wharf and a significant software update that is needed for the final stage of testing.

To bring greater cost certainty Crossrail Ltd also has been told to wrap up its expensive Tier 1 contracts as a matter of urgency.

The programme was spending £56m a month in the six months to March 2021, so any delay to the programme remains a significant risk to the eventual cost of the Elizabeth Line, warns in the latest Public Accounts Committee report published today.

“Crossrail Ltd must end the expensive Tier 1 contracts as soon as possible. 

“By July 2021, Crossrail Ltd expected to have updated its plans to reflect progress and risks remaining, which would inform its range of potential opening dates and costs. This has been delayed by up to two months,” it said.

The report warns that even with the Government bailout, the collapse in passenger numbers owing to the pandemic leaves the project with a potential £150m funding shortfall.

On present management estimates, the project is expected to cost £18.9bn compared to it initial budget of £14.8 in 2010.

Crossrail will still not provide a fixed opening date for the project.

It expects the central tunnelled section to open between February and June 2022 and will operate a shuttle service between Abbey Wood and Paddington. Full east-west services are not expected until December 2022.

Dame Meg Hillier MP, Chair of the Public Accounts Committee, said “We are finally, thankfully seeing a clearer sense of ownership, responsibility, and determination to complete the Crossrail programme from those in charge but there remains a serious, £150 million funding gap to finish the programme. There must be a focus now on finding real solutions to this.

“With fares down because of the ongoing impact of Covid we also need more clarity on the plans and timescale for repaying the significant government loans.”

MPs also complained that the Department for Transport has still not demonstrated that it is embedding lessons learned into its major programmes.

The report said: “This Committee has examined many major transport programmes, such as HS2, Great Western route modernisation and Thameslink, many of which have had significant problems in their delivery.

“We have told the Department many times that it needs to learn lessons, from Crossrail and from other major transport projects, so that it does not repeat the same mistakes.”

But they complain that the Department has still failed to explain in practical terms what it was doing differently, nor the real-world impact its changes have had on delivering major programmes.  

The Committee has called for a full report before November detailing what it has changed in its approach to delivering major programmes with its arms-length bodies.

 

 

Latest news

Staff stunned as engineering consultancy Clarkebond closes

Firm was only bought three months ago by rival Independent Design House Group
4 days ago

Vistry issues third profit warning in three months

Profit expected to fall £50m below forecast due to delayed completions
4 days ago

Miller Homes buys St Modwen Homes for £215m

Scottish house builder snaps up £368m turnover rival
1 week ago

Keltbray fine increased to £18m after failed bid rigging appeal

Contractor loses penalty discount for settling with competition authorities
1 week ago

Luxury house builder goes under with 70 job losses

Octagon Developments in administration after 40 years in business
1 week ago

Top Ten best read stories of 2024

The biggest headlines of an eventful year. Have a good one and here's to a successful 2025
1 week ago

BAM Nuttall fined £800,000 after concrete skip tragedy

Young labourer killed by falling bale arm
1 week ago

Keltbray infrastructure business reveals new name

AUREOS means "new dawn" after private equity acquisition
1 week ago

Stiffer fines for over-running street works from next Summer

Cash raised from lane rentals to be channeled into pothole repairs
1 week ago

£113m Basildon rental homes scheme seals build finance

Work expected to start early next year on Market Square project
1 week ago

Notting Hill Genesis seeks more tier 1 repairs contractors

London housing trust seeks eight firms for new £1.5bn repairs framework
1 week ago

Reclaimed steel oil rig columns worked into London office revamp

Curo will use reclaimed bricks and steel for Fitzrovia office overhaul
1 week ago

CITB delays levy approval consultation

Levy agreement talks pushed back by ongoing review into effectiveness of training body
1 week ago

Ofwat approves £104bn water industry spending plan

Household water bills to rise by 36% to fund quadrupling of investment
1 week ago

Costain/ Siemens JV clinches HS2 power supply job

£300m deal for HV power supply systems over the 225km route
1 week ago

Demolition team assembles on Multiplex London Wall site

Erith to start work next month at Deutsche Bank's former headquarters
1 week ago

Norwich Council acts to revive £300m Anglia Square scheme

Council uses Homes England funding to buy stalled site with planning for 1,100 homes
1 week ago

Go-ahead for 4,500-home Cambridgeshire new town

Waterbeach new town plan stalled three years ago after an Environment Agency objection
1 week ago

Henry Boot to take total control of Stonebridge Homes

Deal worth at least £30m
1 week ago

HS2 costs could hit £66bn

Government looking for next estimate to be lower
1 week ago

Mace to close construction logistics arm

Specialist business being wound down
2 weeks ago

National Grid to invest £35bn over next five years

Plan set out for record investment in electricity transmission infrastructure
2 weeks ago

Profits double at Barhale

Civils specialist sees order book top £1bn
2 weeks ago

Balfour wins 68km HV underground power cable deal

Main works to start next year on Eastern Green Link 2 job
2 weeks ago

Stunning site wrap unveiled on Sloane Street

Hoarding creates illusion of fully formed façade on £53m Galliford Try job
2 weeks ago

Heathrow Airport upgrade spend takes off again

Airport operator will spend £2.3bn over the next two years
2 weeks ago

Government buys back over 36,000 military homes

Public ownership deal to release wave of upgrade and new build work
2 weeks ago

Story Contracting staff braced for rail job losses

Work coming through slower than expected from Network Rail
2 weeks ago

Ballymore submits two plans for 3,700 East London homes

Construction could start in 2025 on Thames Road and Knights Road schemes
2 weeks ago

Blackpool council steps in on failed developer’s £300m scheme

Blackpool Central site clearance to start in the New Year as hunt starts for new developer
2 weeks ago

Contractor services