Crossrail told to wrap-up expensive Tier 1 contracts

Aaron Morby 3 years ago
Share

Public account committee MPs are warning that there is still no real certainty to the Elizabeth Line cost and opening schedule just four months before the first central section trains are due to operate services for the public.

Watchdog MPs have highlighted that Canary Wharf and Bond Street have had significant issues in the past and are yet to be completed.

While Bond Street has been taken off the critical path for limited first opening, MPs are still concerned about the full opening of Canary Wharf and a significant software update that is needed for the final stage of testing.

To bring greater cost certainty Crossrail Ltd also has been told to wrap up its expensive Tier 1 contracts as a matter of urgency.

The programme was spending £56m a month in the six months to March 2021, so any delay to the programme remains a significant risk to the eventual cost of the Elizabeth Line, warns in the latest Public Accounts Committee report published today.

“Crossrail Ltd must end the expensive Tier 1 contracts as soon as possible. 

“By July 2021, Crossrail Ltd expected to have updated its plans to reflect progress and risks remaining, which would inform its range of potential opening dates and costs. This has been delayed by up to two months,” it said.

The report warns that even with the Government bailout, the collapse in passenger numbers owing to the pandemic leaves the project with a potential £150m funding shortfall.

On present management estimates, the project is expected to cost £18.9bn compared to it initial budget of £14.8 in 2010.

Crossrail will still not provide a fixed opening date for the project.

It expects the central tunnelled section to open between February and June 2022 and will operate a shuttle service between Abbey Wood and Paddington. Full east-west services are not expected until December 2022.

Dame Meg Hillier MP, Chair of the Public Accounts Committee, said “We are finally, thankfully seeing a clearer sense of ownership, responsibility, and determination to complete the Crossrail programme from those in charge but there remains a serious, £150 million funding gap to finish the programme. There must be a focus now on finding real solutions to this.

“With fares down because of the ongoing impact of Covid we also need more clarity on the plans and timescale for repaying the significant government loans.”

MPs also complained that the Department for Transport has still not demonstrated that it is embedding lessons learned into its major programmes.

The report said: “This Committee has examined many major transport programmes, such as HS2, Great Western route modernisation and Thameslink, many of which have had significant problems in their delivery.

“We have told the Department many times that it needs to learn lessons, from Crossrail and from other major transport projects, so that it does not repeat the same mistakes.”

But they complain that the Department has still failed to explain in practical terms what it was doing differently, nor the real-world impact its changes have had on delivering major programmes.  

The Committee has called for a full report before November detailing what it has changed in its approach to delivering major programmes with its arms-length bodies.

 

 

Latest news

Kier wins first phase of £700m Warwick Uni campus build

Firm to start work on science and engineering precinct last this year
9 hours ago

Torsion and Khalbros to build new Leeds £1bn neighbourhood

Eastgate Quarter site acquired from Hammerson
9 hours ago

JCB to double size of US factory in wake of Trump tariffs

$500m Texas factory under construction to expand to 1m sq ft
10 hours ago

Green light for £2.4bn Luton Airport expansion

Government go-ahead to transform airport
10 hours ago

Diversification pays off for concrete frame specialist Statom

Strong results as £180m turnover firm expands into infrastructure sector
12 hours ago

Cardo in talks to buy Breyer roofing arm

More than 100 jobs could be saved at Breyer Roofing
17 hours ago

Quartet win £750m Wales & Western railway deal

Network Rail confirms partners for Reactive and Minor Works framework
17 hours ago

Plans in for £350m London Bridge life sciences hub

Snowsfields Quarter will consist of three buildings containing labs
18 hours ago

Surging labour costs push tender price forecast up

Pick-up in tender prices despite weak growth
18 hours ago

Permasteelisa wins cladding deal on Multiplex city tower

Facade specialist wins work on Fenchurch Street ‘hanging gardens’ tower
17 hours ago

Wates wins fit-out for Manchester First Street Hub

Smartspace arm secures another Government hub deal
2 days ago

Peel Ports reveals winners for £750m framework

18 firms win places on deal: Full list
2 days ago

Big trade names dropped in M Group rebrand

Acquisitive group formed from Morrison Utility services in 2016
2 days ago

Breyer Group files administration notice

Staff hope rival firm could buy assets and save jobs
2 days ago

Former Severfield director takes helm at Embrace Steel

New CEO Martin Kelly aims to step up expansion of steelwork contractor
2 days ago

£302m upgrade funding awarded to FE colleges – list

Cash shared out between England’s 179 college groups
2 days ago

FK Facades thrives but construction arm hit by ISG row

Dispute with failed contractor costs specialist £5.5m
2 days ago

Galliford Try gets go-ahead for Milton Keynes PRS tower

33-storey tower needs gateway 2 approval before work can start
2 days ago

Small house builders get £150m funding for green homes

Developers will have to meet-up to ten new criteria to benefit from interest rate discounts
2 days ago

Lendlease Construction renamed Bovis

US private equity firm completes £35m purchase of UK contracting business and rebrands
3 days ago

Breyer Group battles for survival as rivals circle

Housing maintenance firm fights three winding up petitions in a month
3 days ago

Careys facing £2.4m claim by developer over demolition cartel

Giant Hong Kong developer claims it was overcharged on Lots Road Power Station job
3 days ago

Multiplex profit drops a third as revenue rises to £780m

Spate of new orders sets contractor up for three years of work
3 days ago

Galliford Try and Breheny land latest Sizewell C road deals

More infrastructure deals for new nuclear power station
3 days ago

Worker trapped in collapsed septic tank pit

Contractor and director fined after worker suffers multiple fractures
3 days ago

Homes England buys stalled Broad Marsh site

Demolition to finally be completed as developer hunt begins
3 days ago

Vistry go-ahead for 353 homes at Rochester Riverside

Work to start on next phase of Kent town regeneration at end of this year
4 days ago

M&E firm J S Wright collapsed owing £19m

Trade creditors hit for £11.4m by employee-owned Midlands firm
4 days ago

Right to work checks to be extended to self-employed

Government plans crackdown on illegal working and rogue employers
4 days ago

Midlands developer turns to London with £1bn resi schemes trio

SevenCapital plans 1,000 flats in Kensington, Islington and the Isle of Dogs projects
4 days ago

Contractor services