Major steelwork firm warns project delays will hit profits

Aaron Morby 3 years ago
Share

Structural steelwork specialist Billington has warned forecast profit for this year will fall below expectations due to the impact of materials and labour supply constraints on project completions.

Billington chief Mark Smith says some key project completion dates have slipped in the face of materials and labour supply issues
Billington chief Mark Smith says some key project completion dates have slipped in the face of materials and labour supply issues

The firm had previously warned several months ago that the precise outturn for the current financial year depended on the timing of certain key contracts, combined with any potential impact from continuing material price inflation and supply chain constraints.

Mark Smith, CEO of Billington, said that it had now become evident that the completion of certain key projects would not take place by year-end, impacting the profitability, and to a lesser extent revenue.

He said: “2021 has been dominated by the continued challenges arising from the pandemic for both Billington and its clients alike.

“The construction sector is suffering material and labour supply constraints that have affected the delivery of projects and delayed anticipated completion dates.

“As a result, this has adversely impacted this year’s profitability.”

He added that the delayed profit recognition combined with a strong project pipeline had provided greater confidence Billington would meet expectations for next year.

Smith said: “Tendering opportunities remain buoyant and of a good quality, together with a good orderbook provides an increased degree of confidence for 2022 and beyond.”

Latest news

Kier wins first phase of £700m Warwick Uni campus build

Firm to start work on science and engineering precinct last this year
9 hours ago

Torsion and Khalbros to build new Leeds £1bn neighbourhood

Eastgate Quarter site acquired from Hammerson
9 hours ago

JCB to double size of US factory in wake of Trump tariffs

$500m Texas factory under construction to expand to 1m sq ft
10 hours ago

Green light for £2.4bn Luton Airport expansion

Government go-ahead to transform airport
10 hours ago

Diversification pays off for concrete frame specialist Statom

Strong results as £180m turnover firm expands into infrastructure sector
12 hours ago

Cardo in talks to buy Breyer roofing arm

More than 100 jobs could be saved at Breyer Roofing
17 hours ago

Quartet win £750m Wales & Western railway deal

Network Rail confirms partners for Reactive and Minor Works framework
17 hours ago

Plans in for £350m London Bridge life sciences hub

Snowsfields Quarter will consist of three buildings containing labs
18 hours ago

Surging labour costs push tender price forecast up

Pick-up in tender prices despite weak growth
18 hours ago

Permasteelisa wins cladding deal on Multiplex city tower

Facade specialist wins work on Fenchurch Street ‘hanging gardens’ tower
17 hours ago

Wates wins fit-out for Manchester First Street Hub

Smartspace arm secures another Government hub deal
2 days ago

Peel Ports reveals winners for £750m framework

18 firms win places on deal: Full list
2 days ago

Big trade names dropped in M Group rebrand

Acquisitive group formed from Morrison Utility services in 2016
2 days ago

Breyer Group files administration notice

Staff hope rival firm could buy assets and save jobs
2 days ago

Former Severfield director takes helm at Embrace Steel

New CEO Martin Kelly aims to step up expansion of steelwork contractor
2 days ago

£302m upgrade funding awarded to FE colleges – list

Cash shared out between England’s 179 college groups
2 days ago

FK Facades thrives but construction arm hit by ISG row

Dispute with failed contractor costs specialist £5.5m
2 days ago

Galliford Try gets go-ahead for Milton Keynes PRS tower

33-storey tower needs gateway 2 approval before work can start
2 days ago

Small house builders get £150m funding for green homes

Developers will have to meet-up to ten new criteria to benefit from interest rate discounts
2 days ago

Lendlease Construction renamed Bovis

US private equity firm completes £35m purchase of UK contracting business and rebrands
3 days ago

Breyer Group battles for survival as rivals circle

Housing maintenance firm fights three winding up petitions in a month
3 days ago

Careys facing £2.4m claim by developer over demolition cartel

Giant Hong Kong developer claims it was overcharged on Lots Road Power Station job
3 days ago

Multiplex profit drops a third as revenue rises to £780m

Spate of new orders sets contractor up for three years of work
3 days ago

Galliford Try and Breheny land latest Sizewell C road deals

More infrastructure deals for new nuclear power station
3 days ago

Worker trapped in collapsed septic tank pit

Contractor and director fined after worker suffers multiple fractures
3 days ago

Homes England buys stalled Broad Marsh site

Demolition to finally be completed as developer hunt begins
3 days ago

Vistry go-ahead for 353 homes at Rochester Riverside

Work to start on next phase of Kent town regeneration at end of this year
4 days ago

M&E firm J S Wright collapsed owing £19m

Trade creditors hit for £11.4m by employee-owned Midlands firm
4 days ago

Right to work checks to be extended to self-employed

Government plans crackdown on illegal working and rogue employers
4 days ago

Midlands developer turns to London with £1bn resi schemes trio

SevenCapital plans 1,000 flats in Kensington, Islington and the Isle of Dogs projects
4 days ago

Contractor services