M1 fraud probe exposes contract management problems

Aaron Morby 3 years ago
Share

A National Highways fraud probe revealed by the Enquirer last year has found a string of concerning management issues on the M1 J13-16 smart motorway scheme.

The investigation by the agency’s in-house counter fraud squad has now concluded and found that National Highway has suffered financial loss.

But the national roads agency has decided not to pursue any criminal prosecution due to ‘insufficient conclusive evidence’, according to the final report seen by the Enquirer.

The investigation was launched into the Costain Galliford Try joint venture job after multiple accusations were leveled between 18 September 2020 and 2 February 2021, each alleging wrongdoing on the project.

These implied procurement fraud, theft of assets and collusion leading to false claims.

This scheme for a stretch between Milton Keynes and Northampton was awarded to the CGT JV with an agreed budget of £297m. This has ballooned to £453m.

Investigators for National Highways found £320,000 of central barrier scrap metal was ‘missing from the records and unaccounted for’ .

But after failing to secure any reliable witness testimony, the probe team said they were unable to prove the allegation of theft.

The investigation also failed to find hard evidence to support allegations of the use of ghost workers on the job, and bribes for subcontract work or business favours.

While labour supply on the project soared from £362,000 to around £9.5m, an investigation by the CGT JV uncovered no evidence to support whistleblowers claims, says the report.

In response to allegations of “brown envelopes” being passed around, National Highways investigators said that, although there was evidence cash-filled envelopes changed hands, it accepted the explanation that the money was requested from subcontractors to contribute to project staff parties.

Investigators also looked at a large package contract, which jumped from an original order value of £28m to a forecast end cost of £68m.

This was due for the most part to 1,389 compensation events, which were accepted as resulting from a number of complex underlying reasons.

National Highways’ commercial assurance partners have worked with the internal project team to understand the causes for the overspends and to challenge the escalating costs where appropriate.

In the final report, investigators did raise several concerns that ‘presented an increased risk of fraud and further possible accusations of bribery or corruption’ if not addressed.

These included poor contract management, in relation to escalating costs and proper implementation of the compensation events process.

They also highlighted a lack of record-keeping supporting key decisions during a live procurement and to validate ongoing subcontractor costs throughout the life-cycle of the project.

The team also red-flagged lack of governance around single-source procurement decisions.

A CGT JV spokesperson said: “The CGT JV responded comprehensively to all the issues brought to light with a detailed and thorough investigation, with appropriate action taken and further strengthening of its compliance procedures.

“Both companies in the JV have strong policies and procedures in place, fully promote a culture of transparency and encourage potential whistle-blowers to come forward.

“Both the CGT JV and National Highways investigations confirmed that there is no connection between any of the allegations and increased costs of the M1 junction 13-16 project.

“Any inference that the two are connected in any way or that the alleged activities that were under investigation have incurred a cost to the taxpayer is incorrect. Project scopes can evolve as was the case here, and those changes have the support of all parties involved.”

National Highways smart motorways programme director David Bray said: “We take any suggestion of criminal behaviour on our projects extremely seriously and investigate every allegation thoroughly. 

“We investigated, working collaboratively with our contractors, the allegations around the M1 and M6 schemes and prevented the payment of any amounts that we were not fully satisfied with.” 

Latest news

Keltbray fine increased to £18m after failed bid rigging appeal

Contractor loses penalty discount for settling with competition authorities
13 hours ago

Luxury house builder goes under with 70 job losses

Octagon Developments in administration after 40 years in business
23 hours ago

Top Ten best read stories of 2024

The biggest headlines of an eventful year. Have a good one and here's to a successful 2025
1 day ago

BAM Nuttall fined £800,000 after concrete skip tragedy

Young labourer killed by falling bale arm
2 days ago

Keltbray infrastructure business reveals new name

AUREOS means "new dawn" after private equity acquisition
1 day ago

Stiffer fines for over-running street works from next Summer

Cash raised from lane rentals to be channeled into pothole repairs
1 day ago

£113m Basildon rental homes scheme seals build finance

Work expected to start early next year on Market Square project
1 day ago

Notting Hill Genesis seeks more tier 1 repairs contractors

London housing trust seeks eight firms for new £1.5bn repairs framework
1 day ago

Reclaimed steel oil rig columns worked into London office revamp

Curo will use reclaimed bricks and steel for Fitzrovia office overhaul
2 days ago

CITB delays levy approval consultation

Levy agreement talks pushed back by ongoing review into effectiveness of training body
2 days ago

Ofwat approves £104bn water industry spending plan

Household water bills to rise by 36% to fund quadrupling of investment
2 days ago

Costain/ Siemens JV clinches HS2 power supply job

£300m deal for HV power supply systems over the 225km route
2 days ago

Demolition team assembles on Multiplex London Wall site

Erith to start work next month at Deutsche Bank's former headquarters
3 days ago

Norwich Council acts to revive £300m Anglia Square scheme

Council uses Homes England funding to buy stalled site with planning for 1,100 homes
2 days ago

Go-ahead for 4,500-home Cambridgeshire new town

Waterbeach new town plan stalled three years ago after an Environment Agency objection
2 days ago

Henry Boot to take total control of Stonebridge Homes

Deal worth at least £30m
2 days ago

HS2 costs could hit £66bn

Government looking for next estimate to be lower
3 days ago

Mace to close construction logistics arm

Specialist business being wound down
3 days ago

National Grid to invest £35bn over next five years

Plan set out for record investment in electricity transmission infrastructure
3 days ago

Profits double at Barhale

Civils specialist sees order book top £1bn
3 days ago

Balfour wins 68km HV underground power cable deal

Main works to start next year on Eastern Green Link 2 job
3 days ago

Stunning site wrap unveiled on Sloane Street

Hoarding creates illusion of fully formed façade on £53m Galliford Try job
3 days ago

Heathrow Airport upgrade spend takes off again

Airport operator will spend £2.3bn over the next two years
3 days ago

Government buys back over 36,000 military homes

Public ownership deal to release wave of upgrade and new build work
4 days ago

Story Contracting staff braced for rail job losses

Work coming through slower than expected from Network Rail
4 days ago

Ballymore submits two plans for 3,700 East London homes

Construction could start in 2025 on Thames Road and Knights Road schemes
4 days ago

Blackpool council steps in on failed developer’s £300m scheme

Blackpool Central site clearance to start in the New Year as hunt starts for new developer
5 days ago

Brookfield submits retro-first London office plan

Milton Gate plan for Square Mile will hike space by nearly 50%
4 days ago

Bowmer + Kirkland gets start date for £100m Siemens site

Construction to begin early next year on Chippenham scheme
5 days ago

Torsion sells under-construction Leeds BTR scheme

Concrete frame due to start soon on 300-apartment complex
5 days ago

Contractor services