Hinkley Point C gets green light to start ‘mammoth’ M&E works

Aaron Morby 3 years ago
Share

Hinkley Point C project bosses have just got the green light to start bulk mechanical, electrical and heating, ventilation and air conditioning component installation work at the nuclear power station site.

Bulk MEH works to start as project passes 5-year halfway mark
Bulk MEH works to start as project passes 5-year halfway mark

The forthcoming fit-out on the nuclear island of Unit 1 is described as a “mammoth undertaking”. It will require a workforce of up to 4,000 at peak times, including welders, pipe fitters and electricians, working as an alliance.

This phase of work in Somerset will take place over three years with NNB Genco, the subsidiary created by EDF Energy, teaming up with four suppliers – Balfour Beatty Bailey, Doosan, Cavendish and Altrad.

Following an in-depth assessment by The Office for Nuclear Regulation of the MEH proposals, the regulator has finally approved the start of this next phase of the project. It was initially hoped to get sign-off for bulk MEH works last October.

The MEH programme involves electrical and mechanical installations encompassing around 4,000 rooms.

Works will involve 380km of pipework, 20,000 valves, with thousands of welds and associated radiography, and 9000 km of cabling.

Construction at Hinkley Point C began in October 2016, bringing the project just past the five-year mark with projections made last year by EDF that the site should start generating power in mid-2026.

So far, most of the activity at Hinkley Point C has been in the field of civil construction but work on site is set to significantly increase around the installation of mechanical and electrical components and welding.

Shane Turner, superintending inspector for Hinkley Point C, said: “With ONR’s agreement to permission bulk MEH installation in Unit 1 nuclear island, this represents a major change to the project.

“Our scrutiny of the work at Hinkley Point C has been constant from the start and this will remain the same as developments move to its next important phase.

“At the front and centre of our regulation of any under construction plant is clear evidence from a site licensee to demonstrate its overall installation complies with the highest standards of UK safety and security.

“Only once these are met will ONR sanction the site to proceed to the next stages of the construction, installation and commissioning.”

 

Latest news

Cannabis farm gang posed as utilities contractor

Gang jailed for 28 years after diverting power to more than 100 cannabis farms
2 days ago

Former Liverpool mayor charged in building contracts probe

Construction bosses also charged as part of Operation Aloft
2 days ago

Bidding to start for £700m Irish sea interconnector work

Work includes converter stations at Hunterston and Kilroot near Belfast
2 days ago

Muse to redevelop Durham County Hall HQ site

Morgan Sindall regen specialist seals another major development deal
2 days ago

Mace to transform Imperial College Great Hall

Work to start next month on ambitious refit
2 days ago

£100m plan to regenerate former Digbeth ironworks

Hartwell unveils 260,000 sq ft office and 240 homs plan
2 days ago

Legendre UK wins £21m London homes job for Clarion

Tower Hamlets building to be replaced due to building and fire safety issues
2 days ago

Construction buyers report fastest downturn since 2020

Double whammy of decreasing new orders and delayed projects
3 days ago

Bidders day for £15bn schools alliance framework

Online event to set out details of DfE alliancing framework procurement plan
3 days ago

MPs told safety regulator delays forcing industry job cuts

Industry chief warns housing select committee that BSR is now a main block on meeting housing targets
3 days ago

£600m delivery partner named for new hospital programme

Mace/T&T JV named programme delivery partner for £37bn new hospital plan
4 days ago

£230m Southampton waterfront scheme approved

Town Quay includes trio of 25 storey towers around new marina
3 days ago

Planning green light for £10bn Northumberland data centre

Blackstone-backed project will create 1,200 construction jobs
4 days ago

Bauhaus block above Southwark Station gets green light

Student accommodation and affordable housing scheme replaces original office plan
3 days ago

Police arrest plant hire fraud gang

Nine arrests after kit hired "with no intent of ever returning the machines"
4 days ago

Balfour Beatty boss Leo Quinn to step down

Group Chief Executive to be replaced by consultant AtkinsRéalis chief Philip Hoare
4 days ago

Galliford Try upgrades target as half-year profits jump 54%

Firm closes in on deal to take on ISG custodial work
4 days ago

Trespasser dies in crane fall at Willmott Dixon site

Tragedy after man breaks into £60m Manchester science park site
4 days ago

Ibstock pulls out of GRC cladding market

Materials giant blames subcontractor failures and low margins
4 days ago

Green light for 1,000-home Wolverhampton city centre regen

Phase one of ECF Smithgate scheme to start this year
4 days ago

Oval revises Manchester scheme with trio of towers

Flats doubled to 800 at reworked Albert Bridge House project
4 days ago

More repair work needed at McAlpine problem panel hotel

Contractor looking for long-term solution to loose panels
4 days ago

Redesign delays hit giant McAlpine car battery factory

Size of first building reduced and steelwork start pushed back
5 days ago

‘Affordable’ HS2 Crewe to Euston plan submitted to Treasury

Industry presses for scaled back Euston terminus and connection to Crewe
5 days ago

Regal submits plan to revive stalled London resi tower

Swiss Cottage project redesigned with second staircase and 237 flats
5 days ago

Construction boss jailed for siphoning off cash for casino

Money removed from contracting firms before they went under
6 days ago

Muse signs up to £3.2bn Solihull health campus district

Ambitious Arden Cross scheme next to HS2 Interchange advances
5 days ago

Drees & Sommer acquires RSP Consulting Engineers

Expanding consultant sees UK workforce grow to 300
5 days ago

Watkin Jones wins over £50m student digs campus upgrade

Work to start next month on phase 714-bed south London campus
6 days ago

Severfield warns on profits blaming major project delays

Steelwork firm cancels share buyback and steps up cost cutting programme
6 days ago

Contractor services