Hinkley Point C gets green light to start ‘mammoth’ M&E works

Aaron Morby 3 years ago
Share

Hinkley Point C project bosses have just got the green light to start bulk mechanical, electrical and heating, ventilation and air conditioning component installation work at the nuclear power station site.

Bulk MEH works to start as project passes 5-year halfway mark
Bulk MEH works to start as project passes 5-year halfway mark

The forthcoming fit-out on the nuclear island of Unit 1 is described as a “mammoth undertaking”. It will require a workforce of up to 4,000 at peak times, including welders, pipe fitters and electricians, working as an alliance.

This phase of work in Somerset will take place over three years with NNB Genco, the subsidiary created by EDF Energy, teaming up with four suppliers – Balfour Beatty Bailey, Doosan, Cavendish and Altrad.

Following an in-depth assessment by The Office for Nuclear Regulation of the MEH proposals, the regulator has finally approved the start of this next phase of the project. It was initially hoped to get sign-off for bulk MEH works last October.

The MEH programme involves electrical and mechanical installations encompassing around 4,000 rooms.

Works will involve 380km of pipework, 20,000 valves, with thousands of welds and associated radiography, and 9000 km of cabling.

Construction at Hinkley Point C began in October 2016, bringing the project just past the five-year mark with projections made last year by EDF that the site should start generating power in mid-2026.

So far, most of the activity at Hinkley Point C has been in the field of civil construction but work on site is set to significantly increase around the installation of mechanical and electrical components and welding.

Shane Turner, superintending inspector for Hinkley Point C, said: “With ONR’s agreement to permission bulk MEH installation in Unit 1 nuclear island, this represents a major change to the project.

“Our scrutiny of the work at Hinkley Point C has been constant from the start and this will remain the same as developments move to its next important phase.

“At the front and centre of our regulation of any under construction plant is clear evidence from a site licensee to demonstrate its overall installation complies with the highest standards of UK safety and security.

“Only once these are met will ONR sanction the site to proceed to the next stages of the construction, installation and commissioning.”

 

Latest news

Morgan Sindall lands £20m Brunswick Wharf scheme in Bideford

North Devon waterside project will provide 100 flats
11 hours ago

New BAM leisure centre pool springs a leak

Contractor investigating "technical issues" delaying new £36m green leisure centre
14 hours ago

Green light for £150m West End office revamp

Shaftesbury Avenue office retrofit retains 75% of original building
19 hours ago

Former Keltbray managers jailed after corruption trial

Jail sentences following bribery probe on jobs including Battersea Power Station
1 day ago

Lidl pumps £500m into store and logistics expansion

Discounter plans 40 new stores this year as expansion ramps up
20 hours ago

JJ Rhatigan UK profit jumps as turnover tops £150m

Irish contractor's expansion in England gathers pace
20 hours ago

Driverless digger to be used on Taylor Woodrow site

Autonomous excavator to work at Manchester Airport after successful trial
20 hours ago

MCS Build lands Basingstoke warehouse scheme

Construction starts this month after £26m funding deal
20 hours ago

Leeds United unveil stadium revamp design

Club has still to set a timeframe for staged Elland Road upgrade
1 day ago

Bowmer & Kirkland boosts margins as profits surge to £69m

Revenue nudges up towards £1.3bn in year of expansion
2 days ago

Offshore construction starts on £4bn windfarm

Foundations for first of 95 turbines installed: Watch video
2 days ago

AECOM buys civils consultant Allen Gordon

Global giant acquires Scottish water and energy specialist
2 days ago

Plans in for £1bn Northern Gateway site in Manchester

Plan for 500-acre manufacturing and logistic park advance
2 days ago

RED wins £31m London Shoreditch student digs job

Two extra floors will be added to Willen House scheme
2 days ago

Deconstruct handed £12m Grenfell demolition

Firm maintaining building awarded job without bid race to speed process
2 days ago

Sizewell site workers get made to measure PPE

Bespoke fitting service on offer at new Bryson branch
2 days ago

Comment: Gateway is acting like a barricade

Contractors left banging their heads on an (unbuilt) brick wall
5 days ago

Final phase of £1.5bn Elephant and Castle revamp hits planning

Get Living submits revised plan for 500 homes and 450-bed student block
6 days ago

Ealing backs final phase of £1.3bn estate rebuild

Friary Park estate rebuild in Acton reaches end stage
5 days ago

Green light for scaled-down Nottingham student tower

Glasshouse Street scheme will deliver 247 student rooms
5 days ago

Aston Villa to revamp North Stand

Club to reuse existing structure rather than complete rebuild
6 days ago

Mace signs ex-ISG director to lead Euro health and tech push

Gary Sweeney to head up healthcare and life sciences consultancy arm
5 days ago

Sir Robert McAlpine claws way back into profit

Firm says return to profit and strong cash balance validates new strategy
6 days ago

Severfield to cut staff by 6% amid pricing pressure

Steelwork contractor warns of extended tighter pricing due to project delays
6 days ago

JRL completes sale of 50% stake to Malaysian giant IJM

Deal boosts balance sheet and kicks starts growth plan
6 days ago

Green light for £100m Liverpool Baltic station build

Enabling highway works to start in the autumn
7 days ago

First live tests for flying construction robots

Drones can lay construction materials at height on site
6 days ago

Three firms land £170m Gentoo Sunderland housing deal

PHS Solutions, Esh and RE:GEN to deliver 10-year home upgrade plan
7 days ago

Gateway gridlock hits build-to-rent delivery as starts nosedive

Build to rent starts plunge 18% in the capital
7 days ago

Call to shift Gateway 2 checks to end building bottleneck

"The current system isn't working but we all want to see safe buildings"
7 days ago

Contractor services