First of 1,000 giant HS2 bridge segments roll-off factory line – video

Aaron Morby 3 years ago
Share

HS2 contractor Align has rolled out the first enormous pre-cast bridge segment for Colne Valley viaduct, set to be the UK longest railway bridge in the UK.

The huge deck segments each weighing up to 140 tonnes are being made at a purpose-built 100m long factory building that is bigger in internal volume than the Royal Albert Hall.

The construction team, which includes VSL, Danny Sullivan, Sendin and Tarmac, will cast and install a total of 1,000 concrete segments, each the size of a double-decker bus.

At the peak of construction, around 12 segments will be cast every week using a ‘match-casting’ technique.

This sees each segment poured against the previous one as a cast to ensure the whole arch fits perfectly when reassembled on site.

Every segment will be a slightly different shape depending on where it fits into the viaduct.

Vast temporary pre-cast segment factory ensures quality, safety and efficiency in production, and avoid bringing segments in by road.

HS2 Project Client, David Emms said: “We’re already making strong progress on the Colne Valley Viaduct – sinking the foundations, building the first piers, and now starting production at the new modular viaduct factory.

“Once complete, this iconic structure will carry trains at up to 200mph – improving connections across the UK, freeing up rail capacity and offering passengers low carbon travel options.

“It’s great to see how much progress has been made and I look forward to seeing work on assembling the deck structure later this year.”

Daniel Altier, Align Project Director “Seeing the first deck segments being cast in the factory marks a significant milestone for the project. The design of the viaduct is such that each segment will be unique, delivering a structure which I have no doubt will be one of the most striking elements of HS2 once complete.”

The design of the Colne Valley Viaduct was inspired by the flight of a stone skipping across the water, with a series of elegant spans, some up to 80m long, carrying the railway around 10m above the surface of the lakes, River Colne and Grand Union Canal.

Work has also begun on the 56 giant piers that will support the viaduct, working from north to south.

Weighing in at around 370 tonnes, the first 6m tall reinforced concrete pier was cast on site by a team of engineers who used a specially-designed formwork to create the shape of the structure. This was then removed after 4 days to reveal the final product.

Each pier is designed to support the full weight of the deck above and rests on a set of concrete piles going up to 55m into the ground. This foundation work began earlier this year and will require the construction of 292 piles and 56 pile caps across the whole length of the viaduct.

Once complete, the team will then use a specialised ‘launching girder’ resting on top of the piers to lift the deck segments into position.

Latest news

Skanska lands design role on £1.25bn steelworks

Skanska team to work alongside main contractor McAlpine on Port Talbot project
11 hours ago

Bleak January for construction buyers

Latest bellwether survey shows output down and costs up
15 hours ago

Starmer rips up rules to ease building of nuclear reactors

Industry backs push for small modular reactors to be built where needed
18 hours ago

McAlpine tops January work league with steelworks win

Port Talbot steelworks job dominates January orders haul
19 hours ago

McLaren winning spree as £1bn turnover in sight

Major deals imminent as contractor posts stable set of results
1 day ago

Ring road builder wanted at £4bn Somerset gigafactory

Bidders wanted for £60m job. Latest video update from site
1 day ago

Kier seals HMP Glasgow super prison job at £684m

Deal finally signed to replace Scotland's notorious Barlinnie prison
2 days ago

Contract winners revealed for £332m Didcot infrastructure job

Construction set to start early next year
18 hours ago

Fraudsters jailed after £22m construction tax scam

Gang sentenced after bogus payroll firm failed to pay VAT and CIS money to revenue
2 days ago

MPB clinches substructure for HS2 Curzon Street station

Contracts for station superstructure to be let in coming months
2 days ago

Flood defence spend rises to record £2.65bn over two-years

Key projects mapped as Government injects extra £250m to shore up defences
2 days ago

Turnaround strategy continues to pay off for Careys

Profits continue to rise as £50m investment plan in full swing
2 days ago

All change on £800m Eastern Highways Alliance

Octavius and Winvic sweep up all three lots in new line-up
2 days ago

Vinci bags first phase of £350m Stockport scheme

Contractor edges-out Willmott Dixon to start major mixed-used project
2 days ago

Crest Nicholson slumps to £144m loss

Incoming CEO review unearths further writedowns on fire remediation and closed divisions
3 days ago

Piling job cuts loom over safety regulator project delays

Bottleneck in high rise project approvals hits demolition and foundation firms
3 days ago

Developer Ghelamco swaps to self delivery for Battersea tower

John F Hunt no longer part of project team on 24-storey resi scheme
4 days ago

Pagabo starts renewal race for two mega frameworks

Contractors and developers asked for input on reshaping deals worth billions
3 days ago

Giant HS2 viaduct deck slide breaks records: Video

EKFB consortium oversees four-day installation
3 days ago

Ferrovial lands £230m National Grid tunnel

Work to start shortly on Grain to Tilbury electricity infrastructure upgrade
3 days ago

Tax-row tunnellers down tools on Balfour Hinkley job

Lodge allowance tax dispute hits tunnelling site
4 days ago

Go-ahead for Square Mile’s fifth tallest tower

Multiplex set to start 99 Bishopsgate job late next year
4 days ago

New £4.5bn funding model for stalled London rail schemes

Residential TIF funding offers key to unlock Bakerloo and DLR extensions
4 days ago

Speedy Hire latest to be hit by slow CP7 rail spending

Plant-hire firm flags issues with latest Network Rail spending round
4 days ago

FM Conway family chair steps away from business after Vinci deal

Joanne Conway steps away as Andrew Hansen becomes MD
4 days ago

Manchester Hotspur Press mill scheme rescued

37-storey student tower will now go-ahead
4 days ago

Watkin Jones to advance 260-room London aparthotel

Development deal for New Kent Road project
6 days ago

Plan for film studios switched to data centre cluster

Plans in for six data centre buildings in Buckinghamshire
1 week ago

Hunt for firm to deliver £75m Cambridge Civic Quarter

Work includes £41m Guildhall and £21m Corn Exchange revamps
7 days ago

Plans in for £200m Middlesbrough regen scheme

Wates is lined up to deliver landmark Gresham rental homes scheme
7 days ago

Contractor services