HS2 minister admits concern over speed of cost rises

Aaron Morby 2 years ago
Share

HS2 Minister Andrew Stephenson has admitted he is concerned about the rate of cost rises on the £40bn phase one project.

HS2 Minister Andrew Stephenson is monitoring cost and programme progress
HS2 Minister Andrew Stephenson is monitoring cost and programme progress

His latest assessment of progress and spending comes as HS2 has spent just over a third of the target cost.

Since HS2’s watchdog MP last produced his six-month progress report for the Government actual and potential additional costs have jumped by a further £900m.

The hike comes from a £500m increase in contingency drawdown plus an extra £400m from potential further cost pressures.

“Whilst these pressures are manageable within the target cost given the remaining contingency, I am nonetheless concerned at the rate of their increase,” he admitted.

“I expect HS2 to maintain its focus on delivery to the target cost.”

So far a total of £1.3bn has been drawn down from the £5.6bn project contingency fund, leaving £4.3bn in reserve.

He revealed that the Government and HS2 were currently working to assess and mitigate the impact of ‘short-term’ global inflationary pressure on materials and labour supply on the programme.

Stephenson said £800m of the extra cost pressures arose from additional main works civils costs due to further design costs and slower than expected progress in some areas.

An extra £400m will be needed for the Euston station HS2 terminus. Although Stephenson said he hoped the move to a smaller, less complex 10-platform single-stage delivery strategy would reduce this identfied extra spend.

An extra £200m will be needed for changes to Network Rail infrastructure at Euston and Old Oak Common, while an extra £300m is needed for other parts of the overall programme.

HS2 has yet to formally cost in the impact of Covid 19 working restrictions. Its assessment of the likely financial impact of the pandemic remains between £400m and £700m.

Formal claims will be subject to government scrutiny and will require formal approval from the Treasury before funds from government-retained contingency can be allocated.

Over the next 6 months, HS2 will continue the ramp-up of construction work, launch the fourth TBM on the programme to start excavation of the London tunnels and we will see HS2 award a contract for the construction of the Interchange Station.

On Phase 2a, focus will be on progressing environmental and enabling work, early land acquisitions plus the procurement for the design delivery partner and progressing the procurement for the main works civils framework.

To date, out of the Phase One target cost of £40.3bn, £14.9bn has been spent, with an additional £0.8bn for land and property provisions. £12.7bn has been contracted and has not been spent, with the remaining amount not yet under contract.

 

Latest news

McAlpine healthcare MD joins BAM as Northern chief

Mark Gibson joins as Northern regional director
2 days ago

HS2 Align JV completes Britain’s longest rail bridge – video

Final deck segment sees HS2 viaduct break 137-year old record held by Tay Bridge
2 days ago

Green light for major London city fringe office retrofit

Overhaul of 30 Finsbury Square to start next Summer
2 days ago

John Lewis submits plan for £80m Reading rental flats scheme

Construction hoped to start on 215 flats scheme at the start of 2026
2 days ago

Balfour Beatty lands £27m Highlands flood defence scheme

Work to start imminently building river walls in Comrie
2 days ago

Buyers believe construction has “turned a corner”

Residential rebounds, commercial still strong but civils slows
3 days ago

Vistry unseats Barratt as Britain’s biggest house builder

Partnership homes specialist on track to build 18,000 homes this year
3 days ago

23 jobs axed as Lincolnshire contractor goes under

C G Godfrey provided civils and M&E services in Eastern England
3 days ago

Winvic first to use remote-control tower crane on site

Crane driver sits in ground floor command centre at Birmingham 33-storey tower
4 days ago

Starmer vows to ban Grenfell firms from public contracts

Prime Minister to write to named and shamed construction firms
3 days ago

Grenfell Inquiry calls for uber construction regulator

Shake-up must include licensing of main contractors taking on high rise projects
4 days ago

Robertson to restore historic Newcastle market

Work to revamp Grainger Market to start by the end of this month
3 days ago

Three bidders chase £1.4bn Midlands rail hub alliance

Balfour, Skanska, Bam and Laing O'Rouke in bidding for eight-year rail upgrade
4 days ago

Barratt profit nosedives as margin slumps to 4.2%

Fire safety provisions jump by an extra £126m to total £628m
4 days ago

First viaduct completed on HS2: Video site report

Eiffage, Kier, Ferrovial Construction and Bam Nuttall finish 163m long Highfurlong Brook Viaduct
4 days ago

Bouygues bags £28m Oxfordshire school job

St John’s Academy to be at heart of Wellington Gate Development
4 days ago

Willmott Dixon wins £49m Wigan college expansion

New campus for Wigan & Leigh College to be net zero in operation
4 days ago

Work to start on Liverpool office to flats job

Truman D&B wins resi conversion in Moorfields district
4 days ago

Government mothballs plan to scrap CE Mark

Building safety minister warns there is insufficient capacity in present testing regime
5 days ago

Government backs record number of clean energy projects

131 projects will produce electricity to power 11 million homes.
5 days ago

Tube station housing plan gets Government green light

Plans to transform Cockfosters Tube station were blocked by previous regime
5 days ago

Go-ahead for Bristol Temple Quay hotel and build to rent job

A trio of blocks will house a 230-room hotel, 170-room apart-hotel and 100 rental flats
5 days ago

Construction costs cut for Plymouth city centre revamp

Price of Armada Way scheme falls to £30m after exploratory work on site
5 days ago

Tilbury Douglas chief Paul Gandy to step down

Craig Tatton to take on CEO role from November
6 days ago

Local pressure unblocks £240m Oxford sewage works upgrade

Council warns Thames Water delay is halting building of thousands of new homes
6 days ago

Knights Brown bags last phase of £86m Portsmouth flood defence job

Contractor has already completed second and third phases of North Portsea Coastal Scheme
6 days ago

Bidding starts for £1bn housing decarbonising framework

National housing energy efficiency retrofit deal will come into force in 2015
6 days ago

World’s strongest land-based crane launched

Mammoet crane will help build major energy and infrastructure projects
6 days ago

Big Yellow gets go-ahead for largest London site

Storage giant to build 176,000 sq ft scheme next to Kensington Olympia
6 days ago

Worker dies after being buried by trench collapse

Court hears workers on new build housing site had no training on working within excavations
6 days ago

Contractor services