Skanska Costain Strabag completes latest HS2 base slab

Grant Prior 3 years ago
Share

The Skanska Costain STRABAG joint venture (SCS JV) has completed the base slab construction of the HS2 Victoria Road ancillary shaft in Acton.

The first permanent works began at the site in February 2021 when the team poured a 160m3 concrete collar around the ancillary shaft.

They then built the first 11m of the 25m internal diameter shaft using precast concrete segments, produced by FP McCann Ltd, before completing the final 19metre depth using the sprayed concrete lining technique.

The team of around 30 engineers and operatives have since completed the shaft with a 3.3m thick base slab constructed in three different pours.

The main pour of around 1,000 m3 of concrete took place at the end of 2021, and the second and third completed by the end of January 2022 adding another 740 m3 of concrete.

The site will provide critical infrastructure for the operation of HS2. As well as the 25m internal diameter shaft, which will provide ventilation and emergency access to the Northolt Tunnels, SCS JV is building a crossover box on the site that will let trains switch tracks on the way in and out of Old Oak Common station.

HS2’s Project Client, Malcolm Codling said: “The team at Victoria Road have made huge strides, completing the base slab of the ancillary shaft, and preparing the site for the launch of two tunnel boring machines.  As we move into the next phase of work. It won’t be long until we begin to see where the railway will run through the site, taking it from our detailed construction plans to reality.”

Skanska Costain STRABAG Joint Venture’s Managing Director, James Richardson added: “We’re constructing eight ventilation shafts along our 13 miles of twin bore tunnels in London and this vent shaft is the first to advance to this stage.

“Work is progressing well at all our other shaft sites so that they are ready for the tunnel boring machines to travel through them as our huge tunnelling programme progresses over the next three years.”

The site at Victoria Road also has a crucial role to play in construction.

SCS JV will use it to assemble and launch two tunnel boring machines (TBMs) that will dig the 3.4-mile eastern section of the Northolt tunnels. The TBMs are due to arrive in early 2023 and will begin the 12 month programme of tunnelling later that year.

The site will also be connected to the Logistics Hub located at the Willesden Euroterminal by a conveyor system that will remove spoil excavated for the tunnels.

The conveyor system, which also connects the Logistics Hub to Old Oak Common station site, will become operational later this year and will contribute to reducing lorry movements for HS2, removing around 1million lorries from the road.

Latest news

Staff stunned as engineering consultancy Clarkebond closes

Firm was only bought three months ago by rival Independent Design House Group
4 days ago

Vistry issues third profit warning in three months

Profit expected to fall £50m below forecast due to delayed completions
4 days ago

Miller Homes buys St Modwen Homes for £215m

Scottish house builder snaps up £368m turnover rival
1 week ago

Keltbray fine increased to £18m after failed bid rigging appeal

Contractor loses penalty discount for settling with competition authorities
1 week ago

Luxury house builder goes under with 70 job losses

Octagon Developments in administration after 40 years in business
1 week ago

Top Ten best read stories of 2024

The biggest headlines of an eventful year. Have a good one and here's to a successful 2025
1 week ago

BAM Nuttall fined £800,000 after concrete skip tragedy

Young labourer killed by falling bale arm
1 week ago

Keltbray infrastructure business reveals new name

AUREOS means "new dawn" after private equity acquisition
1 week ago

Stiffer fines for over-running street works from next Summer

Cash raised from lane rentals to be channeled into pothole repairs
1 week ago

£113m Basildon rental homes scheme seals build finance

Work expected to start early next year on Market Square project
1 week ago

Notting Hill Genesis seeks more tier 1 repairs contractors

London housing trust seeks eight firms for new £1.5bn repairs framework
1 week ago

Reclaimed steel oil rig columns worked into London office revamp

Curo will use reclaimed bricks and steel for Fitzrovia office overhaul
1 week ago

CITB delays levy approval consultation

Levy agreement talks pushed back by ongoing review into effectiveness of training body
1 week ago

Ofwat approves £104bn water industry spending plan

Household water bills to rise by 36% to fund quadrupling of investment
1 week ago

Costain/ Siemens JV clinches HS2 power supply job

£300m deal for HV power supply systems over the 225km route
1 week ago

Demolition team assembles on Multiplex London Wall site

Erith to start work next month at Deutsche Bank's former headquarters
1 week ago

Norwich Council acts to revive £300m Anglia Square scheme

Council uses Homes England funding to buy stalled site with planning for 1,100 homes
1 week ago

Go-ahead for 4,500-home Cambridgeshire new town

Waterbeach new town plan stalled three years ago after an Environment Agency objection
1 week ago

Henry Boot to take total control of Stonebridge Homes

Deal worth at least £30m
1 week ago

HS2 costs could hit £66bn

Government looking for next estimate to be lower
1 week ago

Mace to close construction logistics arm

Specialist business being wound down
1 week ago

National Grid to invest £35bn over next five years

Plan set out for record investment in electricity transmission infrastructure
1 week ago

Profits double at Barhale

Civils specialist sees order book top £1bn
1 week ago

Balfour wins 68km HV underground power cable deal

Main works to start next year on Eastern Green Link 2 job
1 week ago

Stunning site wrap unveiled on Sloane Street

Hoarding creates illusion of fully formed façade on £53m Galliford Try job
1 week ago

Heathrow Airport upgrade spend takes off again

Airport operator will spend £2.3bn over the next two years
1 week ago

Government buys back over 36,000 military homes

Public ownership deal to release wave of upgrade and new build work
2 weeks ago

Story Contracting staff braced for rail job losses

Work coming through slower than expected from Network Rail
2 weeks ago

Ballymore submits two plans for 3,700 East London homes

Construction could start in 2025 on Thames Road and Knights Road schemes
2 weeks ago

Blackpool council steps in on failed developer’s £300m scheme

Blackpool Central site clearance to start in the New Year as hunt starts for new developer
2 weeks ago

Contractor services