Teenage construction worker crushed to death in manhole

Grant Prior 2 years ago
Share

Two contractors and their managers have been sentenced after an 18-year-old construction worker was killed while working on a housing site in Boston, Lincolnshire.

An HSE picture of the accident scene
An HSE picture of the accident scene

P & R Plant Hire (Lincolnshire) Limited, D. Brown (Building Contractors) Limited, Brent Woods and Darrell Tripp were all fined following the death of Josh Disdel.

In July 2018 Disdel and another worker, both employed by P & R Plant Hire, had been tasked with clearing debris from manholes at the site.

While work was taking place Disdel’s colleague was asked if he could move the works van to allow another vehicle to pass.

He was not aware that Disdel was lying on the road with his head and torso in a manhole, directly in front of the van.

As the vehicle moved forwards one of the wheels entered the top of the manhole crushing Disdel who was then taken to hospital but later died as a result of serious injuries.

An HSE investigation found that neither the principal contractor, D. Brown (Building Contractors) Limited, nor the groundworks subcontractor, P & R Plant Hire had ensured that the work was planned in such a way to ensure that workers were not exposed to risks to their health and safety.

Woods, a manager within P & R Plant Hire for approximately 10 years, sent employees to carry out the task without a risk assessment or method statement in place despite having previously produced such information in the past.

In addition, workers had not been trained to work in a road, had not been provided with any equipment to ensure the work was carried out safely and had not been provided with any instruction on any safety measures to be used at site.

Lincoln Crown Court heard that Tripp, a site manager for D. Brown (Building Contractors) Limited with 40 years industry experience , did not carry out a site induction of Disdel and failed to carry out suitable checks to ensure the workers had the relevant training.

Tripp also failed to ensure there was a safe system of work in place and there were adequate control measures.

D. Brown (Building Contractors) Limited of Spalding was found guilty of safety offences and fined £300,000 and ordered to pay costs of £15,765.92

P & R Plant Hire of Cambridgeshire pleaded guilty to safety breaches and was fined £24,000 and ordered to pay costs of £2,264.87.

Woods of Holbeach, Spalding was found guilty of safety breaches and was sentenced to 18 weeks imprisonment suspended for two years and ordered to complete 200 hours of community service and pay costs of £1200.

Tripp of Deeping St James, Peterborough was also found guilty and was sentenced to eight weeks imprisonment suspended for two years and ordered to pay costs of £1200.

Speaking after the hearing, HSE inspector Mark Welsh said: “This was a completely avoidable incident, caused by a multitude of failures by both companies and both of the individuals who appeared in court.

“All of the defendants failed to adequately plan the work to identify the risks, failed to ensure that the individuals carrying out the work were trained and competent to do so, and failed to ensure a safe system of work was in place and followed.

“The result was the tragic loss of life of a young man who was looking forward to a bright future.”

Latest news

Ridge buys rival consultant Jubb

Acquisition will see 100 new staff join Ridge
1 hour ago

Enabling works to start £130m Huyton town centre regen

Phase one includes a new council HQ, hotel and 72 flats
2 hours ago

Grainger build to rent pipeline rises to £1.4bn

Rental specialist buys sites in Sheffield and Cardiff to build 600 rental homes
2 hours ago

Kier wins Cambridgeshire County council estate upkeep

Firm will provide building and M&E services to 106 buildings across the county
1 hour ago

Louvres and solar shading specialist files for administration

Hampshire based ALPS lodges court notice after 25 years in business
2 hours ago

Speedy Hire posts a loss in latest results

Hire giant confident of better performance in next six months
2 hours ago

Esh to lead next phase of Riverside Sunderland regeneration

Infrastructure work will allow further development of Sheepfolds area
1 hour ago

Green light for £1.3bn Edinburgh coastal town revamp

First phase of Granton Waterfront scheme will see Cruden Homes create a new community
19 hours ago

Vistry chief operating officer steps down

Earl Sibley exits as his COO role axed for more direct reporting to CEO
1 day ago

House builder Camstead goes into administration

Work stopped on three current sites
2 days ago

Death of piling legend Roger Bullivant

Industry innovator dies after long illness aged 85
1 day ago

ESS Modular went down owing suppliers £7m

Modular specialist owned by ISG owner Cathexis
1 day ago

Builders back farmers in inheritance tax protest

"A rethink is desperately needed" say National Federation of Builders
1 day ago

Willmott Dixon wins £36m leisure centre upgrade

Work to start on historic Westminster 1930s Grade II listed Seymour Centre
1 day ago

Graham wins £100m Cardiff Crossrail phase 1

Work on route to Cardiff Bay to start before end of next year
2 days ago

Laing O’Rourke appoints new European MD

Peter Lyons to take-up new role in February
3 days ago

Profits dip at Stepnell ahead of demerger

Turnover and secured workloads up ahead of restructure
3 days ago

HS2 green bridge deck takes shape

100m-wide wildlife bridge to carry hedgerows and country lane over HS2
2 days ago

1,000-home Wolverhampton city centre scheme in for planning

ECF and council advance City Centre West build to rent scheme
3 days ago

Sisk clinches £54m North London council HQ revamp

Haringey's iconic Grade II listed civic centre to be brought back into use
3 days ago

Ofgem approves £2.5bn Eastern Green Link 1

Work to start next Spring on cable project from Scotland to the north of England
3 days ago

Anglian Water hunts for £1bn delivery partner

Programme delivery partner wil integrate with client team over 15-year plan
3 days ago

Hadden collapse costs supply chain £6.7m

"Highly unlikely" subcontractors will receive anything for their unpaid invoices
3 days ago

Management buyout at M&E specialist

£25m turnover Kimpton in second MBO in its 60-year history
3 days ago

BAM finalises £71m deal to replace first major RAAC school

Work to start on new St Leonards Catholic School in Durham
3 days ago

Scaffolder hit by two tonne weight at nuclear plant

Court hands out £633,000 in fines after Dungeness B decommissioning incident
3 days ago

Go-ahead for 860,000 sq ft East London medical campus

Whitechapel Road scheme of six new and repurposed buildings
3 days ago

Site labour rates hit record high as cost inflation returns

Industry's biggest payroll firm says rates rose nearly 5% last month in London
6 days ago

Morris & Spottiswood acquires part of ISG fit-out division

ISG Cathedral acquisition saves 111 jobs and expands presence across England
7 days ago

New work drives Q3 construction output uplift

Third quarter activity up 0.8% despite slowdown in September
6 days ago

Contractor services