Barnes family loses fight for £1.8m over bus station job

Aaron Morby 2 years ago
Share

The family owners of former Bury-based building contractor Thomas Barnes & Sons have lost their fight for compensation from the local council over the Blackburn bus exchange project.

Thomas Barnes administrator Begbies Traynor, backed by the family who are secured creditors, went to court claiming £1.8m from client Blackburn with Darwen Borough Council.

The building firm, which turned over more than £15m, was kicked off the Blackburn bus exchange project in June 2015 mid-way through construction over lack of progress on the complex job.

The administrators claim that failure by the council to make interim payments and the wrongful termination of the contract caused Thomas Barnes to collapse later in 2015.

According to the court papers, directors at Thomas Barnes at the time strongly believed that the problems which led to it being removed from the project were, in very large part, a consequence of failings of Capita, which had been hired by the council to provide a full design and project administration service on the project.

They said: “The claimant’s case is that those within the defendant and Capita who were responsible for this project were very keen to pin the blame for the serious time and cost overruns on the project on someone else and that the defendant’s decision to terminate was both led by Capita and politically motivated to put the blame on the claimant.”

All of this was strongly disputed by the defendant, said Judge Stephen Davies.

The council also argued it was entitled to terminate the contract and was entitled to a counter-claimed £1.9m for the cost of the extra work to complete the bus station.

Judge Stephen Davies accepted that Barnes was entitled to an extension of time which was greater than that allowed for by its client.

But he added that since the end of February 2015 the works had been plagued by delays which were almost entirely Barnes’ own fault and contractual responsibility.

He said any delay related-damages for Barnes fell short of the claim relating to damages arising from the council’s right to terminate the contract under provisions for delay-related breaches.

In a written judgement he said: “It follows that the claimant has no prospect of recovering anything in this litigation, since any entitlement it may establish under a final account analysis would be more than extinguished by the defendant’s right to recover and to set off against such entitlement the net cost of having the contract completed by replacement contractors.”

Latest news

Ridge buys rival consultant Jubb

Acquisition will see 100 new staff join Ridge
1 hour ago

Enabling works to start £130m Huyton town centre regen

Phase one includes a new council HQ, hotel and 72 flats
2 hours ago

Grainger build to rent pipeline rises to £1.4bn

Rental specialist buys sites in Sheffield and Cardiff to build 600 rental homes
2 hours ago

Kier wins Cambridgeshire County council estate upkeep

Firm will provide building and M&E services to 106 buildings across the county
1 hour ago

Louvres and solar shading specialist files for administration

Hampshire based ALPS lodges court notice after 25 years in business
2 hours ago

Speedy Hire posts a loss in latest results

Hire giant confident of better performance in next six months
2 hours ago

Esh to lead next phase of Riverside Sunderland regeneration

Infrastructure work will allow further development of Sheepfolds area
1 hour ago

Green light for £1.3bn Edinburgh coastal town revamp

First phase of Granton Waterfront scheme will see Cruden Homes create a new community
19 hours ago

Vistry chief operating officer steps down

Earl Sibley exits as his COO role axed for more direct reporting to CEO
1 day ago

House builder Camstead goes into administration

Work stopped on three current sites
2 days ago

Death of piling legend Roger Bullivant

Industry innovator dies after long illness aged 85
1 day ago

ESS Modular went down owing suppliers £7m

Modular specialist owned by ISG owner Cathexis
1 day ago

Builders back farmers in inheritance tax protest

"A rethink is desperately needed" say National Federation of Builders
1 day ago

Willmott Dixon wins £36m leisure centre upgrade

Work to start on historic Westminster 1930s Grade II listed Seymour Centre
1 day ago

Graham wins £100m Cardiff Crossrail phase 1

Work on route to Cardiff Bay to start before end of next year
2 days ago

Laing O’Rourke appoints new European MD

Peter Lyons to take-up new role in February
3 days ago

Profits dip at Stepnell ahead of demerger

Turnover and secured workloads up ahead of restructure
3 days ago

HS2 green bridge deck takes shape

100m-wide wildlife bridge to carry hedgerows and country lane over HS2
2 days ago

1,000-home Wolverhampton city centre scheme in for planning

ECF and council advance City Centre West build to rent scheme
3 days ago

Sisk clinches £54m North London council HQ revamp

Haringey's iconic Grade II listed civic centre to be brought back into use
3 days ago

Ofgem approves £2.5bn Eastern Green Link 1

Work to start next Spring on cable project from Scotland to the north of England
3 days ago

Anglian Water hunts for £1bn delivery partner

Programme delivery partner wil integrate with client team over 15-year plan
3 days ago

Hadden collapse costs supply chain £6.7m

"Highly unlikely" subcontractors will receive anything for their unpaid invoices
3 days ago

Management buyout at M&E specialist

£25m turnover Kimpton in second MBO in its 60-year history
3 days ago

BAM finalises £71m deal to replace first major RAAC school

Work to start on new St Leonards Catholic School in Durham
3 days ago

Scaffolder hit by two tonne weight at nuclear plant

Court hands out £633,000 in fines after Dungeness B decommissioning incident
3 days ago

Go-ahead for 860,000 sq ft East London medical campus

Whitechapel Road scheme of six new and repurposed buildings
3 days ago

Site labour rates hit record high as cost inflation returns

Industry's biggest payroll firm says rates rose nearly 5% last month in London
6 days ago

Morris & Spottiswood acquires part of ISG fit-out division

ISG Cathedral acquisition saves 111 jobs and expands presence across England
7 days ago

New work drives Q3 construction output uplift

Third quarter activity up 0.8% despite slowdown in September
6 days ago

Contractor services