Extra design work digs £200m deeper into HS2 contingency

Aaron Morby 2 years ago
Share

The cost of extra design work on the HS2 main work contracts has eaten £200m into contingency funding for the project in the last six months.

Already HS2 is supporting nearly 30,000 construction jobs as it approaches peak construction next year
Already HS2 is supporting nearly 30,000 construction jobs as it approaches peak construction next year

The latest progress report on the mega project reveals that HS2 has had to dig deeper into its £5bn contingency funds.

Significant amounts of the original design work on HS2’s Euston station have been ditched after the decision was taken for the station to be scaled back from 11 to 10 platforms.

HS2 chiefs are now projecting around £1.9bn of net additional cost pressures on phase 1, an increase of about £200m since March and £700m more than a year ago.

So far the mega project has drawn £1.5bn or 28% of its £5.6bn contingency for phase 1, leaving about £4bn in the pot to complete phase one of the project within the 2029 to 2033 time frame.

The latest project spend figures are based on 2019 prices and do not take into account industry-wide construction materials inflation which hit 18% according to official Government figures in the year to August.

HS2 is now ramping up to hit peak construction next year and is now supporting 29,000 construction jobs, with nearly 2,600 firms to date working on the project.

Transport secretary Mark Harper in a six-month HS2 monitoring report to Parliament said:  “While inflation is not affecting the overall affordability of HS2 in real terms because the total budgets and cost estimates for each phase are set in 2019 prices, it is creating pressures against its existing annual funding settlements, which have been set in cash.

“I am clear that HS2 Ltd and its supply chain must do all that they can to mitigate inflationary pressures.”

He said that HS2 was tasked in September to develop and implement actions to bring projected costs back in line with the target cost.

It has since identified an estimated £800m of net savings and efficiencies within phase 1.

These principally consist of savings across the main works civils portfolio and savings in the acquisition and resale of land and property.

These have partly offset gross cost pressures resulting in the latest published net figure.

Harper reported that HS2 phase 1 was still on track to be delivered within its maximum targeted cost including contingency of £45bn.

The phase 2a budget remains unchanged, with a cost range of £5.2bn to £7.2bn.

Government intends to set a target cost alongside the publication of the full business case shortly.

On phase 2b Western Leg, the overall cost range has fallen by around £3bn after removing the Golborne Link.

 

Latest news

Ridge buys rival consultant Jubb

Acquisition will see 100 new staff join Ridge
59 mins ago

Enabling works to start £130m Huyton town centre regen

Phase one includes a new council HQ, hotel and 72 flats
1 hour ago

Grainger build to rent pipeline rises to £1.4bn

Rental specialist buys sites in Sheffield and Cardiff to build 600 rental homes
1 hour ago

Kier wins Cambridgeshire County council estate upkeep

Firm will provide building and M&E services to 106 buildings across the county
52 mins ago

Louvres and solar shading specialist files for administration

Hampshire based ALPS lodges court notice after 25 years in business
2 hours ago

Speedy Hire posts a loss in latest results

Hire giant confident of better performance in next six months
2 hours ago

Esh to lead next phase of Riverside Sunderland regeneration

Infrastructure work will allow further development of Sheepfolds area
37 mins ago

Green light for £1.3bn Edinburgh coastal town revamp

First phase of Granton Waterfront scheme will see Cruden Homes create a new community
18 hours ago

Vistry chief operating officer steps down

Earl Sibley exits as his COO role axed for more direct reporting to CEO
1 day ago

House builder Camstead goes into administration

Work stopped on three current sites
2 days ago

Death of piling legend Roger Bullivant

Industry innovator dies after long illness aged 85
1 day ago

ESS Modular went down owing suppliers £7m

Modular specialist owned by ISG owner Cathexis
1 day ago

Builders back farmers in inheritance tax protest

"A rethink is desperately needed" say National Federation of Builders
1 day ago

Willmott Dixon wins £36m leisure centre upgrade

Work to start on historic Westminster 1930s Grade II listed Seymour Centre
1 day ago

Graham wins £100m Cardiff Crossrail phase 1

Work on route to Cardiff Bay to start before end of next year
2 days ago

Laing O’Rourke appoints new European MD

Peter Lyons to take-up new role in February
3 days ago

Profits dip at Stepnell ahead of demerger

Turnover and secured workloads up ahead of restructure
3 days ago

HS2 green bridge deck takes shape

100m-wide wildlife bridge to carry hedgerows and country lane over HS2
2 days ago

1,000-home Wolverhampton city centre scheme in for planning

ECF and council advance City Centre West build to rent scheme
3 days ago

Sisk clinches £54m North London council HQ revamp

Haringey's iconic Grade II listed civic centre to be brought back into use
3 days ago

Ofgem approves £2.5bn Eastern Green Link 1

Work to start next Spring on cable project from Scotland to the north of England
3 days ago

Anglian Water hunts for £1bn delivery partner

Programme delivery partner wil integrate with client team over 15-year plan
3 days ago

Hadden collapse costs supply chain £6.7m

"Highly unlikely" subcontractors will receive anything for their unpaid invoices
3 days ago

Management buyout at M&E specialist

£25m turnover Kimpton in second MBO in its 60-year history
3 days ago

BAM finalises £71m deal to replace first major RAAC school

Work to start on new St Leonards Catholic School in Durham
3 days ago

Scaffolder hit by two tonne weight at nuclear plant

Court hands out £633,000 in fines after Dungeness B decommissioning incident
3 days ago

Go-ahead for 860,000 sq ft East London medical campus

Whitechapel Road scheme of six new and repurposed buildings
3 days ago

Site labour rates hit record high as cost inflation returns

Industry's biggest payroll firm says rates rose nearly 5% last month in London
6 days ago

Morris & Spottiswood acquires part of ISG fit-out division

ISG Cathedral acquisition saves 111 jobs and expands presence across England
7 days ago

New work drives Q3 construction output uplift

Third quarter activity up 0.8% despite slowdown in September
6 days ago

Contractor services