HS2 Euston needs full design reset as costs set to double

Aaron Morby 2 years ago
Share

The public spending watchdog has called for an urgent total design rethink of the Euston terminus of HS2 as costs soar.

National Audit Offcie calls for full project review to develop a design that is deliverable and value for money.
National Audit Offcie calls for full project review to develop a design that is deliverable and value for money.

A new National Audit Office report into the station warns that forecast project costs have continued to balloon despite attempts to simplify the project.

The original £2.6bn station budget is now reckoned to have soared to £4.8bn, even with the cost-cutting decision to trim back platforms from 11 to 10.

Spending to date on advanced works has already hit £548m.

NAO experts warn that the Government’s latest two-year pause in new construction can only inflate long-term costs further.

This is due to costs associated with demobilising and then remobilising teams, contractual changes, and managing the project for longer.

It has called on the Government to use the two-year pause to go back to the drawing board and develop a design that is affordable, deliverable and value for money.

The NAO’s report recommends the DfT works with stakeholders: Euston Partnership, HS2 Ltd, Network Rail, Lendlease and local partners to reassess the expectations for the HS2 Euston project, its budget, and the public benefits.

Gareth Davies, the head of the NAO said: “Government is once again having to revise plans for Euston HS2.

“Clearly, the 2020 reset of the station design has not succeeded.

“DfT and HS2 Ltd have not been able to develop an affordable scope that is integrated with other activity at Euston, despite their focus on costs and governance since 2020. Recent high inflation has added to the challenge.

“The March 2023 announcement by the Transport Secretary pausing new construction work should now give DfT and HS2 Ltd the necessary time to put the HS2 Euston project on a more realistic and stable footing.

“However, the deferral of spending to manage inflationary pressures will lead to additional costs and potentially a more expensive project overall, and that will need to be managed closely.”

Meg Hillier MP, Chair of the Committee of Public Accounts. added: “Attempts to reset the High Speed 2 Euston Station have failed.

“It is still unaffordable and no further forward than it was three years ago.

“Today’s NAO report shows that the redesigned station would have cost nearly double what was budgeted.

“Department for Transport and High Speed Two Ltd have wasted enough time and money. They must get Euston right next time or risk squandering what benefits remain.”

Euston Station cost reality check


  • In January 2020, the NAO reported that the work at Euston was more complex than originally anticipated and that there was uncertainty over the HS2 station design.
  • The following month the Oakervee Review 2 raised concerns about the design of the HS2 Euston station and concluded that the existing design was unsatisfactory.
  • In April 2020, HS2 Ltd set the station budget at £2.6bn, but by June 2020 it estimated that it could cost as much as £4.4bn.
  • In November 2020, the DfT instructed HS2 Ltd to pause construction on the 11-platform design to begin work on a new 10-platform plan.
  • These new plans are now £0.4bn more expensive than the previous 11-platform design.
  • In Autumn 2021 the Department also directed HS2 Ltd to integrate more closely with Network Rail’s redevelopment of the existing rail station and confirmed the extent of the surrounding commercial and residential developments.
  • Much of the previous design work was then scrapped, at a cost of £106m to the taxpayer, despite DfT’s efforts to minimise this.
  • To help with this integration, and in response to the Oakervee recommendations, in December 2021 the DfT formally established the Euston Partnership to bring together the different bodies involved with projects on the Euston site, including delivery of HS2 Euston station.
  • Following the Transport Secretary’s announcement to delay works in March 2023, the DfT will now need to consider how best to control the budget.
  • By the end of December 2022 HS2 Ltd had spent more than £2bn on the HS2 Euston station and its approaches, including design, land, and preparatory works.
  • The land purchases and preparatory works cost £1.5bn and were funded from the wider HS2 budget.

Latest news

Driver escapes injury as scaffold collapses onto van

Major three-lift scaffold fall blocks north London high street
3 days ago

Gilbert Ash to be sold to staff

£267m turnover contractor to transition to an Employee Ownership Trust
4 days ago

M Group seals biggest-ever deal with Telent takeover

Digital infrastructure specialist deal lifts turnover to £3bn
3 days ago

Aggregates firm Ashville went down owing more than £3m

Debts revealed in Companies House update
3 days ago

Cardo saves 100 jobs at Breyer roofing arm

Private equity-backed Welsh maintenance group continues to expand
4 days ago

Excavator knocked off lorry going under bridge

Traffic Commissioner inquiry after accident in south London
3 days ago

Czech energy tycoon buys UK’s biggest rebar supplier

Spanish offload Celsa UK operation to be rebranded 7 Steel UK
4 days ago

Caddick Construction targets £400m turnover

Regional shake-up pays off at contracting arm
5 days ago

Redrow chief steps down after Barratt merger

Matthew Pratt leaving after 22 years
5 days ago

United Living names new property services senior team

New CEO and COO appointed to lead growth in housing upkeep and retrofit
4 days ago

Wynne triples turnover in three years to over £90m

Five-year growth strategy pays off
4 days ago

Speedy Hire blames Budget for branch closures

National Insurance rises accelerate closure programme
4 days ago

Builder gets suspended sentence for Covid loan fraud

M&E specialist inflated turnover to claim maximum loan
4 days ago

Scores of M&E firms win places on £400m CHIC framework

Axis Europe and Seddon secured spots on social housing deal
5 days ago

Coroner hears how worker was crushed under digger

Inquest opens into tragedy at Rose Builders site
5 days ago

Billington lowers 2025 forecast amid pricing pressure

Tender prices under pressure due to project delays and cancellations
5 days ago

Willmott Dixon lands Dover town centre revamp

Alliance agreed to regenerate several key council sites
6 days ago

Go-ahead for London City office-to-flats scheme

Hub's 150 Minories job in Aldgate to create 280 co-living homes
6 days ago

Wates mobilises as £200m Middlesbrough scheme approved

Gresham Street scheme includes a hotel, 240 flats and over 400 student rooms
6 days ago

Crashed M&E contractor TNA owed supply chain £7m

Sister company buys assets including company vans
6 days ago

Renaker eyes bumper 2025 despite Gateway 2 concern

Strong construction pipeline to support another record year
6 days ago

Wessex Water picks civils firms for £65m framework

Over 40 smaller firms will support AMP8 civils spending programme
6 days ago

Green light for nearly 400 flats at Leeds scheme

Three blocks up to 18 storeys approved at Armley Road
6 days ago

Subcontractors wanted across South London

Work up for grabs from main contractors and clients: Register now for Constructionline event
6 days ago

Heavy lorry ban on Severn Bridge as cables deteriorate

Crossing "not designed and built for today’s levels or weight of traffic"
6 days ago

Muse submits Oldham town centre regeneration plan

Plan advances for six sites to deliver 2000 homes, an hotel and office space
1 week ago

Construction returns to growth after two tough months

Concern grows Trump turmoil is spooking property investors
1 week ago

Skanska wins £43m Clifton Bridge deal

Contractors says scheme is a "complex project that will be delivered to tight timescales"
1 week ago

Green light for 44-storey Manchester resi tower

Developer Glenbrook to start hunt for main contractor
1 week ago

Ten win £670m Network Rail eastern region small works deal

CK Rail, QTS, Colt and Construction Marine pick up two lots
1 week ago

Contractor services