HS2 Euston needs full design reset as costs set to double

Aaron Morby 2 years ago
Share

The public spending watchdog has called for an urgent total design rethink of the Euston terminus of HS2 as costs soar.

National Audit Offcie calls for full project review to develop a design that is deliverable and value for money.
National Audit Offcie calls for full project review to develop a design that is deliverable and value for money.

A new National Audit Office report into the station warns that forecast project costs have continued to balloon despite attempts to simplify the project.

The original £2.6bn station budget is now reckoned to have soared to £4.8bn, even with the cost-cutting decision to trim back platforms from 11 to 10.

Spending to date on advanced works has already hit £548m.

NAO experts warn that the Government’s latest two-year pause in new construction can only inflate long-term costs further.

This is due to costs associated with demobilising and then remobilising teams, contractual changes, and managing the project for longer.

It has called on the Government to use the two-year pause to go back to the drawing board and develop a design that is affordable, deliverable and value for money.

The NAO’s report recommends the DfT works with stakeholders: Euston Partnership, HS2 Ltd, Network Rail, Lendlease and local partners to reassess the expectations for the HS2 Euston project, its budget, and the public benefits.

Gareth Davies, the head of the NAO said: “Government is once again having to revise plans for Euston HS2.

“Clearly, the 2020 reset of the station design has not succeeded.

“DfT and HS2 Ltd have not been able to develop an affordable scope that is integrated with other activity at Euston, despite their focus on costs and governance since 2020. Recent high inflation has added to the challenge.

“The March 2023 announcement by the Transport Secretary pausing new construction work should now give DfT and HS2 Ltd the necessary time to put the HS2 Euston project on a more realistic and stable footing.

“However, the deferral of spending to manage inflationary pressures will lead to additional costs and potentially a more expensive project overall, and that will need to be managed closely.”

Meg Hillier MP, Chair of the Committee of Public Accounts. added: “Attempts to reset the High Speed 2 Euston Station have failed.

“It is still unaffordable and no further forward than it was three years ago.

“Today’s NAO report shows that the redesigned station would have cost nearly double what was budgeted.

“Department for Transport and High Speed Two Ltd have wasted enough time and money. They must get Euston right next time or risk squandering what benefits remain.”

Euston Station cost reality check


  • In January 2020, the NAO reported that the work at Euston was more complex than originally anticipated and that there was uncertainty over the HS2 station design.
  • The following month the Oakervee Review 2 raised concerns about the design of the HS2 Euston station and concluded that the existing design was unsatisfactory.
  • In April 2020, HS2 Ltd set the station budget at £2.6bn, but by June 2020 it estimated that it could cost as much as £4.4bn.
  • In November 2020, the DfT instructed HS2 Ltd to pause construction on the 11-platform design to begin work on a new 10-platform plan.
  • These new plans are now £0.4bn more expensive than the previous 11-platform design.
  • In Autumn 2021 the Department also directed HS2 Ltd to integrate more closely with Network Rail’s redevelopment of the existing rail station and confirmed the extent of the surrounding commercial and residential developments.
  • Much of the previous design work was then scrapped, at a cost of £106m to the taxpayer, despite DfT’s efforts to minimise this.
  • To help with this integration, and in response to the Oakervee recommendations, in December 2021 the DfT formally established the Euston Partnership to bring together the different bodies involved with projects on the Euston site, including delivery of HS2 Euston station.
  • Following the Transport Secretary’s announcement to delay works in March 2023, the DfT will now need to consider how best to control the budget.
  • By the end of December 2022 HS2 Ltd had spent more than £2bn on the HS2 Euston station and its approaches, including design, land, and preparatory works.
  • The land purchases and preparatory works cost £1.5bn and were funded from the wider HS2 budget.

Latest news

Ridge buys rival consultant Jubb

Acquisition will see 100 new staff join Ridge
1 hour ago

Enabling works to start £130m Huyton town centre regen

Phase one includes a new council HQ, hotel and 72 flats
2 hours ago

Grainger build to rent pipeline rises to £1.4bn

Rental specialist buys sites in Sheffield and Cardiff to build 600 rental homes
2 hours ago

Kier wins Cambridgeshire County council estate upkeep

Firm will provide building and M&E services to 106 buildings across the county
1 hour ago

Louvres and solar shading specialist files for administration

Hampshire based ALPS lodges court notice after 25 years in business
2 hours ago

Speedy Hire posts a loss in latest results

Hire giant confident of better performance in next six months
2 hours ago

Esh to lead next phase of Riverside Sunderland regeneration

Infrastructure work will allow further development of Sheepfolds area
1 hour ago

Green light for £1.3bn Edinburgh coastal town revamp

First phase of Granton Waterfront scheme will see Cruden Homes create a new community
19 hours ago

Vistry chief operating officer steps down

Earl Sibley exits as his COO role axed for more direct reporting to CEO
1 day ago

House builder Camstead goes into administration

Work stopped on three current sites
2 days ago

Death of piling legend Roger Bullivant

Industry innovator dies after long illness aged 85
1 day ago

ESS Modular went down owing suppliers £7m

Modular specialist owned by ISG owner Cathexis
1 day ago

Builders back farmers in inheritance tax protest

"A rethink is desperately needed" say National Federation of Builders
1 day ago

Willmott Dixon wins £36m leisure centre upgrade

Work to start on historic Westminster 1930s Grade II listed Seymour Centre
1 day ago

Graham wins £100m Cardiff Crossrail phase 1

Work on route to Cardiff Bay to start before end of next year
2 days ago

Laing O’Rourke appoints new European MD

Peter Lyons to take-up new role in February
3 days ago

Profits dip at Stepnell ahead of demerger

Turnover and secured workloads up ahead of restructure
3 days ago

HS2 green bridge deck takes shape

100m-wide wildlife bridge to carry hedgerows and country lane over HS2
2 days ago

1,000-home Wolverhampton city centre scheme in for planning

ECF and council advance City Centre West build to rent scheme
3 days ago

Sisk clinches £54m North London council HQ revamp

Haringey's iconic Grade II listed civic centre to be brought back into use
3 days ago

Ofgem approves £2.5bn Eastern Green Link 1

Work to start next Spring on cable project from Scotland to the north of England
3 days ago

Anglian Water hunts for £1bn delivery partner

Programme delivery partner wil integrate with client team over 15-year plan
3 days ago

Hadden collapse costs supply chain £6.7m

"Highly unlikely" subcontractors will receive anything for their unpaid invoices
3 days ago

Management buyout at M&E specialist

£25m turnover Kimpton in second MBO in its 60-year history
3 days ago

BAM finalises £71m deal to replace first major RAAC school

Work to start on new St Leonards Catholic School in Durham
3 days ago

Scaffolder hit by two tonne weight at nuclear plant

Court hands out £633,000 in fines after Dungeness B decommissioning incident
3 days ago

Go-ahead for 860,000 sq ft East London medical campus

Whitechapel Road scheme of six new and repurposed buildings
3 days ago

Site labour rates hit record high as cost inflation returns

Industry's biggest payroll firm says rates rose nearly 5% last month in London
6 days ago

Morris & Spottiswood acquires part of ISG fit-out division

ISG Cathedral acquisition saves 111 jobs and expands presence across England
7 days ago

New work drives Q3 construction output uplift

Third quarter activity up 0.8% despite slowdown in September
6 days ago

Contractor services