Align hits key milestone on HS2 Colne Valley viaduct

Aaron Morby 2 years ago
Share

HS2’s main works contractor Align JV has completed the first set of V-shaped bridge piers for what will be the UK’s longest railway bridge

The  V-piers are designed to support the viaduct deck over a series of lakes the Colne Valley Viaduct crosses between the end of the London tunnels and the start of the Chiltern tunnels.

Designed to bear the weight of the 80m wide arches over the lakes, the ‘v-piers’ are twice as large as simpler piers that carry the viaduct over land.

The ‘V piers’ will support a row of elegant arches whose design was inspired by the flight of a stone skimming over the surface of the water.

Cast in place using a series of giant moulds, each pier has a separate tower crane, with a temporary access bridge linking them with the main construction site. Cofferdams were used to hold back the water while the 60m deep foundations were built into the bed of the lakes.

Each pier weighs around 1,800 tonnes and took nine months to complete. To help the engineers master the complex shape of the pier, a mock-up was built off site before work began on the real piers.

The Colne Valley Viaduct – which is being built near Hillingdon – will carry high speed trains more than two miles (3.4km) across the Grand Union Canal, River Colne, local roads and a series of lakes

In total, 11 ‘v-piers’ will support the viaduct over water with a further 45 piers on land.

A 160m long bridge-building machine, known as a ‘launching girder’, will be used to lift the giant concrete deck segments that form the viaduct’s arches into position. Once each section is complete, the machine inches itself forward to build the next stage.

Originally built in 2004, the launching girder was first used during the construction of the Hong Kong East Tsing Yi Viaduct. The machine is named ‘Dominique’ in memory of Bouygues engineer Dominique Droniou who played a leading role in its design.

Deck segments will be placed alternately on each side, using a cantilever approach to balance the structure, as two half-arches are constructed simultaneously. Steel tensioning cables are then threaded through the segments to strengthen the bridge.

Align Project Director, Daniel Altier said:“I am delighted that by working as an integrated team with our supply chain partners, we have been able to erect nearly a third of the deck and complete the first V pier, just a year since Dominique starting operating.”

In the last year, it has installed over 300 out of 1,000 segments required to complete the viaduct deck, installing up to three pairs of segments each day.

To allow for the gentle curve of the viaduct, each of the one thousand segments that form the arches and deck are slightly different – and all are manufactured at a temporary factory set up close by, with direct access to the M25.

Aerial showing the extent of the 3.4km Colne Valley Viaduct once complete

The huge viaduct project is being led by HS2’s main works contractor Align JV – a team made up of Bouygues Travaux Publics, Sir Robert McAlpine and VolkerFitzpatrick working with key suppliers including VSL, Kilnbridge, Tarmac and KVJV.

 

Latest news

Kier seals HMP Glasgow super prison job at £684m

Deal finally signed to replace Scotland's notorious Barlinnie prison
1 hour ago

Fraudsters jailed after £22m construction tax scam

Gang sentenced after bogus payroll firm failed to pay VAT and CIS money to revenue
7 hours ago

MPB clinches substructure for HS2 Curzon Street station

Contracts for station superstructure to be let in coming months
23 hours ago

Flood defence spend rises to record £2.65bn over two-years

Key projects mapped as Government injects extra £250m to shore up defences
6 hours ago

Turnaround strategy continues to pay off for Careys

Profits continue to rise as £50m investment plan in full swing
24 hours ago

All change on £800m Eastern Highways Alliance

Octavius and Winvic sweep up all three lots in new line-up
6 hours ago

Vinci bags first phase of £350m Stockport scheme

Contractor edges-out Willmott Dixon to start major mixed-used project
23 hours ago

Crest Nicholson slumps to £144m loss

Incoming CEO review unearths further writedowns on fire remediation and closed divisions
1 day ago

Piling job cuts loom over safety regulator project delays

Bottleneck in high rise project approvals hits demolition and foundation firms
2 days ago

Developer Ghelamco swaps to self delivery for Battersea tower

John F Hunt no longer part of project team on 24-storey resi scheme
2 days ago

Pagabo starts renewal race for two mega frameworks

Contractors and developers asked for input on reshaping deals worth billions
1 day ago

Giant HS2 viaduct deck slide breaks records: Video

EKFB consortium oversees four-day installation
1 day ago

Ferrovial lands £230m National Grid tunnel

Work to start shortly on Grain to Tilbury electricity infrastructure upgrade
2 days ago

Tax-row tunnellers down tools on Balfour Hinkley job

Lodge allowance tax dispute hits tunnelling site
2 days ago

Go-ahead for Square Mile’s fifth tallest tower

Multiplex set to start 99 Bishopsgate job late next year
3 days ago

New £4.5bn funding model for stalled London rail schemes

Residential TIF funding offers key to unlock Bakerloo and DLR extensions
2 days ago

Speedy Hire latest to be hit by slow CP7 rail spending

Plant-hire firm flags issues with latest Network Rail spending round
2 days ago

FM Conway family chair steps away from business after Vinci deal

Joanne Conway steps away as Andrew Hansen becomes MD
2 days ago

Manchester Hotspur Press mill scheme rescued

37-storey student tower will now go-ahead
2 days ago

Watkin Jones to advance 260-room London aparthotel

Development deal for New Kent Road project
5 days ago

Plan for film studios switched to data centre cluster

Plans in for six data centre buildings in Buckinghamshire
6 days ago

Hunt for firm to deliver £75m Cambridge Civic Quarter

Work includes £41m Guildhall and £21m Corn Exchange revamps
5 days ago

Plans in for £200m Middlesbrough regen scheme

Wates is lined up to deliver landmark Gresham rental homes scheme
5 days ago

£600m Bristol shopping centre redevelopment approved

Galleries centre will be demolished for homes and offices quarter
5 days ago

Ant Yapi lands ultra prime London homes job

Prestige scheme replicates Regency mansions around nearby Regent’s Park
5 days ago

CITB survives another review

Report published after two more years talking about skills crisis
6 days ago

Strucktor wins record M&E package from Ardmore

Major subcontract on £240m Tribeca life science development
5 days ago

Over 800 high-rise resi jobs stalled by safety regulator

Building safety regulator project logjam hits Government growth plan
6 days ago

McAlpine under fire after another panel comes loose from hotel

High winds cause more problems at recently completed Woking hotel
7 days ago

McGee starts demolition for £500m South Bank scheme

Former ITV studios will be replaced by two office towers
6 days ago

Contractor services