Cost consultant Arcadis has warned that the second staircase rule in the Capital will set back tall residential projects in procurement by up to 9 months.

The firm also warns that the delay will be felt across the country once the Government introduces proposals for 11-storey and above block of flats across the country.

In its latest tender price forecast for the UK, the cost consultant warned the new fire safety-based design delay would worsen the wider market slowdown.

Simon Rawlinson, head of Strategic Research & Insight at Arcadis, said that London’s high rise residential market should brace for significant delays following the GLA’s accelerated introduction of a mandatory second staircase requirement for all new residential buildings over 30m.

While many affected buildings are part of long programmes, offering time for redesign, in reality all taller residential developments currently in procurement will likely be postponed by 6-9 months for redesign, he warned

The impact of this will likely spread to regional markets once the staircase requirement is confirmed nationwide.

He said: “Our view is that loss of workload associated with second staircase delays is a material factor influencing market conditions in London, with an anticipated reduction in tender price inflation to 2% in 2023.”

The forecaster also predicted materials price inflation and shortages were behind the industry now as stock levels on products like bricks return to more normal levels and energy prices.

Looking ahead, Rawlinson said: “Even if 2023 turns out to be better than forecast, we will see a significant slowdown compared to the past two years.

“Our view is that building workload will stabilise in 2024 at new but mostly reduced levels and that the greatest area of uncertainty will be the rate of growth of work to power and water networks.”

Arcadis Summer 2023 Construction Price Inflation Forecast


For 2025, Arcadis forecasts prices across all sectors will rise by 3-4%. This is a marginal upgrade reflecting the potential for some bounce back in price pressure as workload picks up.

Latest news

Green light for £250m West End office revamp

Shaftesbury Avenue office retrofit retains 75% of original building
25 minutes ago

Four jailed after Keltbray corruption trial

Jail sentences following bribery probe on jobs including Battersea Power Station
11 hours ago

Lidl pumps £500m into store and logistics expansion

Discounter plans 40 new stores this year as expansion ramps up
18 minutes ago

JJ Rhatigan UK profit jumps as turnover tops £150m

Irish contractor's expansion in England gathers pace
42 minutes ago

Driverless digger to be used on Taylor Woodrow site

Autonomous excavator to work at Manchester Airport after successful trial
37 minutes ago

MCS Build lands Basingstoke warehouse scheme

Construction starts this month after £26m funding deal
14 minutes ago

Leeds United unveil stadium revamp design

Club has still to set a timeframe for staged Elland Road upgrade
9 hours ago

Bowmer & Kirkland boosts margins as profits surge to £69m

Revenue nudges up towards £1.3bn in year of expansion
1 day ago

Offshore construction starts on £4bn windfarm

Foundations for first of 95 turbines installed: Watch video
1 day ago

AECOM buys civils consultant Allen Gordon

Global giant acquires Scottish water and energy specialist
24 hours ago

Plans in for £1bn Northern Gateway site in Manchester

Plan for 500-acre manufacturing and logistic park advance
24 hours ago

RED wins £31m London Shoreditch student digs job

Two extra floors will be added to Willen House scheme
1 day ago

Deconstruct handed £12m Grenfell demolition

Firm maintaining building awarded job without bid race to speed process
1 day ago

Sizewell site workers get made to measure PPE

Bespoke fitting service on offer at new Bryson branch
1 day ago

Comment: Gateway is acting like a barricade

Contractors left banging their heads on an (unbuilt) brick wall
4 days ago

Final phase of £1.5bn Elephant and Castle revamp hits planning

Get Living submits revised plan for 500 homes and 450-bed student block
5 days ago

Ealing backs final phase of £1.3bn estate rebuild

Friary Park estate rebuild in Acton reaches end stage
4 days ago

Green light for scaled-down Nottingham student tower

Glasshouse Street scheme will deliver 247 student rooms
4 days ago

Aston Villa to revamp North Stand

Club to reuse existing structure rather than complete rebuild
5 days ago

Mace signs ex-ISG director to lead Euro health and tech push

Gary Sweeney to head up healthcare and life sciences consultancy arm
4 days ago

Sir Robert McAlpine claws way back into profit

Firm says return to profit and strong cash balance validates new strategy
5 days ago

Severfield to cut staff by 6% amid pricing pressure

Steelwork contractor warns of extended tighter pricing due to project delays
5 days ago

JRL completes sale of 50% stake to Malaysian giant IJM

Deal boosts balance sheet and kicks starts growth plan
5 days ago

Green light for £100m Liverpool Baltic station build

Enabling highway works to start in the autumn
6 days ago

First live tests for flying construction robots

Drones can lay construction materials at height on site
5 days ago

Three firms land £170m Gentoo Sunderland housing deal

PHS Solutions, Esh and RE:GEN to deliver 10-year home upgrade plan
6 days ago

Gateway gridlock hits build-to-rent delivery as starts nosedive

Build to rent starts plunge 18% in the capital
6 days ago

Call to shift Gateway 2 checks to end building bottleneck

"The current system isn't working but we all want to see safe buildings"
6 days ago

GBN launches £600m bid race for SMR engineer roles

Owner engineers to provide technical and assurance services
6 days ago

Wates hires ex-Homes England chief to head public sector push

Robert Stone to spearhead its public sector and national frameworks strategy
6 days ago

Contractor services