Delay on new 2.0 hospital design stalls big build plan

Aaron Morby 2 years ago
Share

The Government needs to quadruple planned spending on its new hospital programme to get close to meeting already revised building plans.

Midland Metropolitan University Hospital, due to open next year, is 67% over budget
Midland Metropolitan University Hospital, due to open next year, is 67% over budget

A thorough audit of progress on the Boris Johnson Government’s commitment to build 40 new hospitals by 2030 has revealed serious flaws in progress to date.

The National Audit Office report warns the Government will miss its target by 2030 and urged NHS officials to speed up delivery of the second phase of projects.

Much of the major project element of the building programme has been loaded into 2025 starts, yet the plans to standardise design to modularise and cut costs of the next generation of hospitals has failed to materialise.

While the new 2.0 standard design for major hospitals is hoped to be completed by May next year, all major schemes seeking outline budget approval have been stalled by the design delay.

According to a new NAO report the whole programme is looking in serious ill health, due to inflation already driving up costs on smaller committed to projects and the lack of design certainty needed for accurate projected building cost savings on the next generation of larger hospitals expected to cost over £1bn each.

Auditors are calling on Government to push forward smaller schemes in the second phase due to start next year to avoid a serious logjam on the progress of the major hospital schemes being brought through in phase three.

The report warns that the four contractors singled out to deliver the programme –  ISG, Kier, Laing O’Rourke and Wates – could face serious capacity constraints if the throughput of projects is bunched.

Meg Hillier MP, Chair of the Committee of Public Accounts: “English hospitals are in poor condition, after years of underinvestment.

“Today’s NAO report shows the government’s woeful lack of progress against its commitment to build 40 new hospitals by 2030.

“It has failed to even begin construction on any of the new hospitals in its second cohort which it thought were quick wins.”

She added: “The Department of Health and Social Care has been trying to move the goalposts so it can claim it has met its target. Patients and clinicians are going to have to wait much longer than they expected before their new hospitals are completed.”

When the health department officially set out the plan in October 2020, eight hospital construction projects already underway were not included in the target. But recent government statements about building 40 new hospitals include these eight projects, referred to as “legacy hospitals”.

Also last May, the government changed the scope of the programme to include hospitals in urgent need of repairs, including five judged to be at risk of collapse because of crumbling concrete infrastructure.

New hospital programme progress and budgets


First phase – eight legacy projects


Second Phase – due to complete construction by early 2028


Phase three  –  bulk of major projects

Phase four

NAO recommendations to DHSC, NHS England and government more widely include:

  • Announcements about major capital programmes extending over more than one spending review period should fully reflect known uncertainties.
  • DHSC should choose future hospital construction projects transparently and keep full records.
  • Further bunching of construction schemes should be avoided.
  • NHP should reconsider assumptions that may result in ‘minimum viable product’ future hospitals being too small.

Gareth Davies, the head of the NAO said: “The programme has innovative plans to standardise hospital construction, delivering efficiencies and quality improvements.

“However, by the definition the government used in 2020 it will now deliver 32 rather than 40 new hospitals by 2030.

“Delivery so far has been slower than expected, both on individual schemes and in developing the Hospital 2.0 template, which has delayed programme funding decisions.

“There are some important lessons to be drawn for major programmes from the experience of the New Hospital Programme so far.

“These include strengthening the business case process to improve confidence on affordability and delivery dates, and improving transparency for key decisions.”

Latest news

Plan for film studios switched to data centre cluster

Plans in for six data centre buildings in Buckinghamshire
21 hours ago

Hunt for firm to deliver £75m Cambridge Civic Quarter

Work includes £41m Guildhall and £21m Corn Exchange revamps
5 hours ago

Plans in for £200m Middlesbrough regen scheme

Wates is lined up to deliver landmark Gresham rental homes scheme
5 hours ago

£600m Bristol shopping centre redevelopment approved

Galleries centre will be demolished for homes and offices quarter
6 hours ago

Ant Yapi lands ultra prime London homes job

Prestige scheme replicates Regency mansions around nearby Regent’s Park
6 hours ago

CITB survives another review

Report published after two more years talking about skills crisis
21 hours ago

Strucktor wins record M&E package from Ardmore

Major subcontract on £240m Tribeca life science development
6 hours ago

Over 800 high-rise resi jobs stalled by safety regulator

Building safety regulator project logjam hits Government growth plan
1 day ago

McAlpine under fire after another panel comes loose from hotel

High winds cause more problems at recently completed Woking hotel
2 days ago

McGee starts demolition for £500m South Bank scheme

Former ITV studios will be replaced by two office towers
1 day ago

Four arrested after hospital construction site burglary

Damage and copper wiring stolen at Hinckley and District General Hospital new building
2 days ago

Caddick kicks off Digbeth regen plan with £43m flats job

First phase 211 flats job starts wider £260m Upper Trinity Street scheme
1 day ago

Sisk starts work on £300m Children’s Cancer Centre

Great Ormond Street Hospital job will employ 500 on site and last three years
1 day ago

McAlpine clinches £1.25bn Port Talbot low carbon steelworks job

Deal to build one of the largest electric arc furnaces in the world
3 days ago

McLaren to build top-down on £60m New Bond Street contract

Contractor working to tight technical guidelines on busy Mayfair site
2 days ago

Project delays dull Van Elle first-half results

Piling specialist upbeat about year ahead as order book up 24%
2 days ago

Aggregate Industries appoints new contracting chief

Kevin Murgatroyd promoted to new role
2 days ago

Bouygues wins Immingham £170m import jetty job

French civils firm to build bulk ammonia import facility for hydrogen economy
3 days ago

Plans in for latest phase of Leith port revamp

Construction to start this year on transforming waterfront
2 days ago

Avant Homes starts redundancy consultation

Jobs under threat at Central region
3 days ago

Plans in for Barnet leisure park and 1500 homes

Regal to redevelop Great North Leisure Park in Finchley
3 days ago

JRL wins shell and core for £400m London scheme

220 Blackfriars Road project will rise to 21 and 15 storeys
4 days ago

Robertson strengthens East Midlands leadership

Woodcock promoted to ops director and Brown joins from BAM as commercial director
3 days ago

Match-maker service for stalled S106 housing projects

Clearing website to release logjam of unbuilt developer affordable home commitments
3 days ago

Turnover flat as Glencar rethinks strategy

Industrial and logistics building specialist targets "the right type of work"
4 days ago

McLaren lures another director from McAlpine

Glen Harding to help grow recently launched construction management division
4 days ago

£200m Edinburgh Lloyds HQ redevelopment plan

Landmark Port Hamilton building revamp is Edinburgh's largest ever pre-let deals
3 days ago

Chinese super embassy plan edges closer to go-ahead

Met Police drop concerns about Royal Mint site next to Tower of London
4 days ago

GMI delivers just £1m profit after clearing legacy job

Revenue falls 29% to £232m after 'controlled consolidation'
4 days ago

Construction set for gradual two-year recovery

Construction Products Association says Government will need to deliver on pro-growth strategy
4 days ago

Contractor services