Delay on new 2.0 hospital design stalls big build plan

Aaron Morby 2 years ago
Share

The Government needs to quadruple planned spending on its new hospital programme to get close to meeting already revised building plans.

Midland Metropolitan University Hospital, due to open next year, is 67% over budget
Midland Metropolitan University Hospital, due to open next year, is 67% over budget

A thorough audit of progress on the Boris Johnson Government’s commitment to build 40 new hospitals by 2030 has revealed serious flaws in progress to date.

The National Audit Office report warns the Government will miss its target by 2030 and urged NHS officials to speed up delivery of the second phase of projects.

Much of the major project element of the building programme has been loaded into 2025 starts, yet the plans to standardise design to modularise and cut costs of the next generation of hospitals has failed to materialise.

While the new 2.0 standard design for major hospitals is hoped to be completed by May next year, all major schemes seeking outline budget approval have been stalled by the design delay.

According to a new NAO report the whole programme is looking in serious ill health, due to inflation already driving up costs on smaller committed to projects and the lack of design certainty needed for accurate projected building cost savings on the next generation of larger hospitals expected to cost over £1bn each.

Auditors are calling on Government to push forward smaller schemes in the second phase due to start next year to avoid a serious logjam on the progress of the major hospital schemes being brought through in phase three.

The report warns that the four contractors singled out to deliver the programme –  ISG, Kier, Laing O’Rourke and Wates – could face serious capacity constraints if the throughput of projects is bunched.

Meg Hillier MP, Chair of the Committee of Public Accounts: “English hospitals are in poor condition, after years of underinvestment.

“Today’s NAO report shows the government’s woeful lack of progress against its commitment to build 40 new hospitals by 2030.

“It has failed to even begin construction on any of the new hospitals in its second cohort which it thought were quick wins.”

She added: “The Department of Health and Social Care has been trying to move the goalposts so it can claim it has met its target. Patients and clinicians are going to have to wait much longer than they expected before their new hospitals are completed.”

When the health department officially set out the plan in October 2020, eight hospital construction projects already underway were not included in the target. But recent government statements about building 40 new hospitals include these eight projects, referred to as “legacy hospitals”.

Also last May, the government changed the scope of the programme to include hospitals in urgent need of repairs, including five judged to be at risk of collapse because of crumbling concrete infrastructure.

New hospital programme progress and budgets


First phase – eight legacy projects


Second Phase – due to complete construction by early 2028


Phase three  –  bulk of major projects

Phase four

NAO recommendations to DHSC, NHS England and government more widely include:

  • Announcements about major capital programmes extending over more than one spending review period should fully reflect known uncertainties.
  • DHSC should choose future hospital construction projects transparently and keep full records.
  • Further bunching of construction schemes should be avoided.
  • NHP should reconsider assumptions that may result in ‘minimum viable product’ future hospitals being too small.

Gareth Davies, the head of the NAO said: “The programme has innovative plans to standardise hospital construction, delivering efficiencies and quality improvements.

“However, by the definition the government used in 2020 it will now deliver 32 rather than 40 new hospitals by 2030.

“Delivery so far has been slower than expected, both on individual schemes and in developing the Hospital 2.0 template, which has delayed programme funding decisions.

“There are some important lessons to be drawn for major programmes from the experience of the New Hospital Programme so far.

“These include strengthening the business case process to improve confidence on affordability and delivery dates, and improving transparency for key decisions.”

Latest news

Kier wins first phase of £700m Warwick Uni campus build

Firm to start work on science and engineering precinct last this year
9 hours ago

Torsion and Khalbros to build new Leeds £1bn neighbourhood

Eastgate Quarter site acquired from Hammerson
9 hours ago

JCB to double size of US factory in wake of Trump tariffs

$500m Texas factory under construction to expand to 1m sq ft
10 hours ago

Green light for £2.4bn Luton Airport expansion

Government go-ahead to transform airport
10 hours ago

Diversification pays off for concrete frame specialist Statom

Strong results as £180m turnover firm expands into infrastructure sector
12 hours ago

Cardo in talks to buy Breyer roofing arm

More than 100 jobs could be saved at Breyer Roofing
17 hours ago

Quartet win £750m Wales & Western railway deal

Network Rail confirms partners for Reactive and Minor Works framework
17 hours ago

Plans in for £350m London Bridge life sciences hub

Snowsfields Quarter will consist of three buildings containing labs
18 hours ago

Surging labour costs push tender price forecast up

Pick-up in tender prices despite weak growth
18 hours ago

Permasteelisa wins cladding deal on Multiplex city tower

Facade specialist wins work on Fenchurch Street ‘hanging gardens’ tower
17 hours ago

Wates wins fit-out for Manchester First Street Hub

Smartspace arm secures another Government hub deal
2 days ago

Peel Ports reveals winners for £750m framework

18 firms win places on deal: Full list
2 days ago

Big trade names dropped in M Group rebrand

Acquisitive group formed from Morrison Utility services in 2016
2 days ago

Breyer Group files administration notice

Staff hope rival firm could buy assets and save jobs
2 days ago

Former Severfield director takes helm at Embrace Steel

New CEO Martin Kelly aims to step up expansion of steelwork contractor
2 days ago

£302m upgrade funding awarded to FE colleges – list

Cash shared out between England’s 179 college groups
2 days ago

FK Facades thrives but construction arm hit by ISG row

Dispute with failed contractor costs specialist £5.5m
2 days ago

Galliford Try gets go-ahead for Milton Keynes PRS tower

33-storey tower needs gateway 2 approval before work can start
2 days ago

Small house builders get £150m funding for green homes

Developers will have to meet-up to ten new criteria to benefit from interest rate discounts
2 days ago

Lendlease Construction renamed Bovis

US private equity firm completes £35m purchase of UK contracting business and rebrands
3 days ago

Breyer Group battles for survival as rivals circle

Housing maintenance firm fights three winding up petitions in a month
3 days ago

Careys facing £2.4m claim by developer over demolition cartel

Giant Hong Kong developer claims it was overcharged on Lots Road Power Station job
3 days ago

Multiplex profit drops a third as revenue rises to £780m

Spate of new orders sets contractor up for three years of work
3 days ago

Galliford Try and Breheny land latest Sizewell C road deals

More infrastructure deals for new nuclear power station
3 days ago

Worker trapped in collapsed septic tank pit

Contractor and director fined after worker suffers multiple fractures
3 days ago

Homes England buys stalled Broad Marsh site

Demolition to finally be completed as developer hunt begins
3 days ago

Vistry go-ahead for 353 homes at Rochester Riverside

Work to start on next phase of Kent town regeneration at end of this year
4 days ago

M&E firm J S Wright collapsed owing £19m

Trade creditors hit for £11.4m by employee-owned Midlands firm
4 days ago

Right to work checks to be extended to self-employed

Government plans crackdown on illegal working and rogue employers
4 days ago

Midlands developer turns to London with £1bn resi schemes trio

SevenCapital plans 1,000 flats in Kensington, Islington and the Isle of Dogs projects
4 days ago

Contractor services