Firms put on alert for £1.6bn of decarbonisation frameworks

Aaron Morby 2 years ago
Share

Procurement body Pagabo has readied firms for two new decarbonisation projects frameworks set to come out to tender in September.

Both frameworks will be valued at £1.6bn and run for four years and each will have its own contracting authority.

One framework will be dedicated for healthcare schemes, with Great Ormond Street Hospital serving as a sector-specialist host.

The second framework will be hosted by Hull City Council and be open to all other sectors.

Both frameworks will offer a dozen regional lots to ensure SME and local-based supplier involvement.

Each of these regions will be separated into two main service lots:

  • Lot 1 – Retrofit Consultancy
  • Lot 2 – Main Contractor Delivery

Under Lot 1, clients will be able to appoint retrofit assessors, coordinators, designers and evaluators to provide specialist consultancy services for decarbonisation projects.

Firms will be able to provide a full business case for the delivery, then sit client-side throughout the delivery phase in a coordination role.

To be appointed to the lot, consultants will be required to hold relevant accreditations, such as PAS2035 or PAS2038 for the assessment of domestic dwellings and commercial buildings for energy retrofit.

Under Lot 2, main contractors will be appointed to provide a complete business solution for clients.

Lot 2 will be split into four value bands

  • Lot 2a – £250k to £1m
  • Lot 2b – £1m to £5m
  • Lot 2c – £5m to £15m
  • Lot 2d – £15m and above

The general building decarbonisation framework will also be divided into three building classes, with a requirement to submit evidence case studies. These scopes will cover:

  • Domestic Low Rise
  • Domestic High Rise
  • Non-Domestic – commercial, education, and leisure

A Dynamic Purchasing System (DPS) will be created after the commencement of frameworks.

Jason Stapley, chief procurement officer at Pagabo, said: “There is a wide understanding of the need to design for net zero, but there is still a long way to go to meet government targets and improving our current building stock will play a key role in this.

“There are a lot of specialist organisations out there that are able to assist clients with their net-zero projects and strategies, and having these dedicated frameworks means that their services will be easier to access in a compliant manner for public sector organisations.”

It is expected that the invitation to tender will open in early September, ahead of the frameworks going live late January 2024.

Interested parties can register to join a pre-market engagement event on Thursday 10 August here 

Latest news

MPB clinches substructure for HS2 Curzon Street station

Contracts for station superstructure to be let in coming months
16 hours ago

Vinci bags first phase of £350m Stockport scheme

Contractor edges-out Willmott Dixon to start major mixed-used project
16 hours ago

Turnaround strategy continues to pay off for Careys

Profits continue to rise as £50m investment plan in full swing
17 hours ago

Crest Nicholson slumps to £144m loss

Incoming CEO review unearths further writedowns on fire remediation and closed divisions
23 hours ago

Piling job cuts loom over safety regulator project delays

Bottleneck in high rise project approvals hits demolition and foundation firms
2 days ago

Developer Ghelamco swaps to self delivery for Battersea tower

John F Hunt no longer part of project team on 24-storey resi scheme
2 days ago

Pagabo starts renewal race for two mega frameworks

Contractors and developers asked for input on reshaping deals worth billions
23 hours ago

Giant HS2 viaduct deck slide breaks records: Video

EKFB consortium oversees four-day installation
23 hours ago

Ferrovial lands £230m National Grid tunnel

Work to start shortly on Grain to Tilbury electricity infrastructure upgrade
2 days ago

Tax-row tunnellers down tools on Balfour Hinkley job

Lodge allowance tax dispute hits tunnelling site
2 days ago

Go-ahead for Square Mile’s fifth tallest tower

Multiplex set to start 99 Bishopsgate job late next year
2 days ago

New £4.5bn funding model for stalled London rail schemes

Residential TIF funding offers key to unlock Bakerloo and DLR extensions
2 days ago

Speedy Hire latest to be hit by slow CP7 rail spending

Plant-hire firm flags issues with latest Network Rail spending round
2 days ago

FM Conway family chair steps away from business after Vinci deal

Joanne Conway steps away as Andrew Hansen becomes MD
2 days ago

Manchester Hotspur Press mill scheme rescued

37-storey student tower will now go-ahead
2 days ago

Watkin Jones to advance 260-room London aparthotel

Development deal for New Kent Road project
4 days ago

Plan for film studios switched to data centre cluster

Plans in for six data centre buildings in Buckinghamshire
6 days ago

Hunt for firm to deliver £75m Cambridge Civic Quarter

Work includes £41m Guildhall and £21m Corn Exchange revamps
5 days ago

Plans in for £200m Middlesbrough regen scheme

Wates is lined up to deliver landmark Gresham rental homes scheme
5 days ago

£600m Bristol shopping centre redevelopment approved

Galleries centre will be demolished for homes and offices quarter
5 days ago

Ant Yapi lands ultra prime London homes job

Prestige scheme replicates Regency mansions around nearby Regent’s Park
5 days ago

CITB survives another review

Report published after two more years talking about skills crisis
6 days ago

Strucktor wins record M&E package from Ardmore

Major subcontract on £240m Tribeca life science development
5 days ago

Over 800 high-rise resi jobs stalled by safety regulator

Building safety regulator project logjam hits Government growth plan
6 days ago

McAlpine under fire after another panel comes loose from hotel

High winds cause more problems at recently completed Woking hotel
6 days ago

McGee starts demolition for £500m South Bank scheme

Former ITV studios will be replaced by two office towers
6 days ago

Four arrested after hospital construction site burglary

Damage and copper wiring stolen at Hinckley and District General Hospital new building
7 days ago

Caddick kicks off Digbeth regen plan with £43m flats job

First phase 211 flats job starts wider £260m Upper Trinity Street scheme
6 days ago

Sisk starts work on £300m Children’s Cancer Centre

Great Ormond Street Hospital job will employ 500 on site and last three years
6 days ago

McAlpine clinches £1.25bn Port Talbot low carbon steelworks job

Deal to build one of the largest electric arc furnaces in the world
1 week ago

Contractor services