‘Marathon’ bridge build completed on HS2

Grant Prior 1 year ago
Share

Contractors on HS2 have completed a ‘marathon’ bridge build at Streethay near Lichfield involving 18 specialist construction companies.

Work involved excavating 14,000 tonnes of earth, building a 140 metre retaining wall and moving a 2,600 tonne bridge deck 130 metres into place under the South Staffordshire freight railway.

The work was carried out during a 10 week blockade. It was completed by HS2’s civils contractor in the West Midlands, Balfour Beatty VINCI, and designers Mott MacDonald as part of a Design Joint Venture with SYSTRA (MMSDJV), together with teams from 18 specialist supply chain companies.

At the end of July, the 2,600 tonne bridge deck, which had been cast on land adjacent to the railway was moved 130 metres into position using self-propelled modular transporters.

Since then, each side of the bridge was backfilled, the rail tracks were reinstated, with the railway line was successfully handed back to Network Rail last week and now reopened.

The 25 metres long and 18 metres wide Streethay overbridge sits within HS2’s Streethay cutting and will enable HS2 trains to travel under the existing railway between Birmingham and Crewe.

Through design development, Mott MacDonald engineers were able to reduce the total length of wall structures for the railway at Streethay from 1.6 kilometres to 420 metres, meaning 80% less concrete is needed – saving around 420,000 tonnes of carbon, supporting HS2’s ambition to cut carbon on the project.

The Streethay bridge sits on top of the larger 420 metre long retaining wall structure which will have two additional bridges crossing it – the south bound A38 slip road bridge, and the Rykneld Bridge which carries the A38 north bound slip road and the A38 north and south bound carriageway.

At its peak, over 150 people worked on the complex construction operation, with teams from 18 specialist companies, delivering design, surveys, piling works, bridge build, concrete pouring, crane operations, reinforcements, modular transportation, track and systems removal and reinstatement.

The work was delivered in parallel to the construction of the nearby Fulfen Wood bridge, which involved moving a giant 6,200 tonne single span structure under the West Coast Main Line – the UK’s heaviest drive to install an intersection bridge.

David Millar, Rail Interface Manager at Balfour Beatty VINCI said: “The successful delivery of this complex and challenging piece of engineering near Lichfield is another proud moment for Balfour Beatty VINCI on the HS2 project.

“It’s only been possible thanks to the skill, dedication and support shown by the project team over the past few years, including our supply chain. Together, we’ve had to work around existing transport infrastructure, including the South Staffordshire freight railway and the A38, making this achievement even more rewarding.”

Prior to the railway blockade, retaining walls were installed on either side of the railway, enabling the areas to be excavated. The bridge deck was constructed on land adjacent to the existing railway, 130 metres from its final position.

Once the railway was closed to freight trains, the track and embankment were removed. Bachy Soletanche Balfour Beatty Ground Engineering joint venture then installed an additional 76 secant piles measuring 1.3 metres diameter and 30 metres deep, linking to the piles they installed prior to the blockade, to create two retaining walls which act as the walls for the bridge.

A concrete capping beam was installed over the retaining walls, then the bridge was moved into place using self-propelled modular transporters with 344 wheels. Concrete was poured to attach the deck to the capping beam, the embankment was back filled using 2,500 tonnes of structural backfill, on either side of the bridge, before the railway line was reinstated.

The 18 companies which delivered the project were:

  • J. Murphy & Sons constructed the bridge deck and the concrete elements during the blockade
  • Bachy Soletanche Balfour Beatty Ground Engineering JV (SB3) undertook all piling works, both before and during the blockade
  • The bridge parapets were made by Explore precast
  • Podtrak and RSS Infrastructure delivered rail systems work
  • Balfour Beatty VINCI delivered earthworks
  • Pile break-down was by Pile Breaking Systems UK Ltd
  • Trackway supplied by TPA
  • Jacking the structure and modular transportation by Mammoet UK
  • Survey works track monitoring by Aecom
  • Crane supply by King Lifting supported by BBV lifting teams
  • Concrete provided by CEMEX
  • Reinforcement by ROM – specialist reinforcement manufacturers
  • Temporary works by RMD
  • Permanent works design by Design JV (Mott Macdonald and Systra)
  • Temporary works design by Taylor Woodrow

Latest news

Fraudsters jailed after £22m construction tax scam

Gang sentenced after bogus payroll firm failed to pay VAT and CIS money to revenue
4 hours ago

MPB clinches substructure for HS2 Curzon Street station

Contracts for station superstructure to be let in coming months
20 hours ago

Flood defence spend rises to record £2.65bn over two-years

Key projects mapped as Government injects extra £250m to shore up defences
3 hours ago

Turnaround strategy continues to pay off for Careys

Profits continue to rise as £50m investment plan in full swing
21 hours ago

All change on £800m Eastern Highways Alliance

Octavius and Winvic sweep up all three lots in new line-up
3 hours ago

Vinci bags first phase of £350m Stockport scheme

Contractor edges-out Willmott Dixon to start major mixed-used project
20 hours ago

Crest Nicholson slumps to £144m loss

Incoming CEO review unearths further writedowns on fire remediation and closed divisions
1 day ago

Piling job cuts loom over safety regulator project delays

Bottleneck in high rise project approvals hits demolition and foundation firms
2 days ago

Developer Ghelamco swaps to self delivery for Battersea tower

John F Hunt no longer part of project team on 24-storey resi scheme
2 days ago

Pagabo starts renewal race for two mega frameworks

Contractors and developers asked for input on reshaping deals worth billions
1 day ago

Giant HS2 viaduct deck slide breaks records: Video

EKFB consortium oversees four-day installation
1 day ago

Ferrovial lands £230m National Grid tunnel

Work to start shortly on Grain to Tilbury electricity infrastructure upgrade
2 days ago

Tax-row tunnellers down tools on Balfour Hinkley job

Lodge allowance tax dispute hits tunnelling site
2 days ago

Go-ahead for Square Mile’s fifth tallest tower

Multiplex set to start 99 Bishopsgate job late next year
3 days ago

New £4.5bn funding model for stalled London rail schemes

Residential TIF funding offers key to unlock Bakerloo and DLR extensions
2 days ago

Speedy Hire latest to be hit by slow CP7 rail spending

Plant-hire firm flags issues with latest Network Rail spending round
2 days ago

FM Conway family chair steps away from business after Vinci deal

Joanne Conway steps away as Andrew Hansen becomes MD
2 days ago

Manchester Hotspur Press mill scheme rescued

37-storey student tower will now go-ahead
2 days ago

Watkin Jones to advance 260-room London aparthotel

Development deal for New Kent Road project
4 days ago

Plan for film studios switched to data centre cluster

Plans in for six data centre buildings in Buckinghamshire
6 days ago

Hunt for firm to deliver £75m Cambridge Civic Quarter

Work includes £41m Guildhall and £21m Corn Exchange revamps
5 days ago

Plans in for £200m Middlesbrough regen scheme

Wates is lined up to deliver landmark Gresham rental homes scheme
5 days ago

£600m Bristol shopping centre redevelopment approved

Galleries centre will be demolished for homes and offices quarter
5 days ago

Ant Yapi lands ultra prime London homes job

Prestige scheme replicates Regency mansions around nearby Regent’s Park
5 days ago

CITB survives another review

Report published after two more years talking about skills crisis
6 days ago

Strucktor wins record M&E package from Ardmore

Major subcontract on £240m Tribeca life science development
5 days ago

Over 800 high-rise resi jobs stalled by safety regulator

Building safety regulator project logjam hits Government growth plan
6 days ago

McAlpine under fire after another panel comes loose from hotel

High winds cause more problems at recently completed Woking hotel
7 days ago

McGee starts demolition for £500m South Bank scheme

Former ITV studios will be replaced by two office towers
6 days ago

Four arrested after hospital construction site burglary

Damage and copper wiring stolen at Hinckley and District General Hospital new building
7 days ago

Contractor services