MPs call for ‘reality check’ on revised 2.0 new hospital programme

Aaron Morby 1 year ago
Share

Spending watchdog MPs have raised doubts about the Government’s ability to deliver its revised hospital programme of 40 new hospitals by 2030.

New Moorfields eye hospital site where work started this summer
New Moorfields eye hospital site where work started this summer

Public accounts committee MPs challenged plans for the revised new hospital programme warning that spending and delivery timeframes ‘didn’t stack up’.

NHS procurement chiefs revealed the new hospital programme was costed on the basis that contractors using modern methods of construction would build 25% cheaper and 20% quicker than previous hospital projects.

But final standardised 2.0 hospital designs will not completed until next May. These are critical because they will rely heavily on offsite assembly and use of repeat components and specifications across the programme.

MPs were also concerned about the further impacts the RAAC concrete crisis would have on the ambitious plans.

At least 23 more hospitals have been identified with RAAC problems needing mitigation works budgeted at £685m on top of the seven RAAC hospitals recently moved into the new hospital programme for complete rebuilds.

PAC chairwoman Meg Hillier warned that the National Audit Office had already declared it believed only 32 hospital could be delivered.

NHS officials said the programme would cost £21bn, although broad costings of the five cohorts of projects to be built added up to £38bn, warned Sir Geoffrey Clifton-Brown MP.

So far the first two hospitals in the new hospital programme – the National Rehabilitation Centre and Moorfield Eye Hospital – are due to be delivered in 2025 and 2027 with the remaining due to be started and completed in the next seven years.

Procurement chiefs are planning to share the vast programme between just four contractors, which Sir Geoffrey warned would cause inflationary pressures.

He called on the NHS chiefs to set out a fully costed and timetable list of projects to clarify the delivery plan.

Shona Dunn, permanent secretary, Department of Health and Social Care, said: “This is a very big and complex major Government programme that is not just building 40 hospitals, it is attempting to shift the way in which we build hospital infrastructure.

“I completely accept therefore this is a period of time at the outset of that major programme where we are delivering hospital 2.0, we are changing the approach to the delivery of that infrastructure and you are quite right to say we rely on that change of approach being successful in order to build to these time frames.

“So what I am saying is the recent past needs not to be an indicator of what happens over the next seven years.”

Commenting on the programme delivery plans, Mark Francois MP said the department’s confidence that it could build the remaining 39 hospitals in just seven years after only delivering one in the first three years “defied logic”

“This is truly worse than the MoD and that is saying something,” he added.

 

Latest news

Staff stunned as engineering consultancy Clarkebond closes

Firm was only bought three months ago by rival Independent Design House Group
3 days ago

Vistry issues third profit warning in three months

Profit expected to fall £50m below forecast due to delayed completions
3 days ago

Miller Homes buys St Modwen Homes for £215m

Scottish house builder snaps up £368m turnover rival
6 days ago

Keltbray fine increased to £18m after failed bid rigging appeal

Contractor loses penalty discount for settling with competition authorities
6 days ago

Luxury house builder goes under with 70 job losses

Octagon Developments in administration after 40 years in business
7 days ago

Top Ten best read stories of 2024

The biggest headlines of an eventful year. Have a good one and here's to a successful 2025
7 days ago

BAM Nuttall fined £800,000 after concrete skip tragedy

Young labourer killed by falling bale arm
1 week ago

Keltbray infrastructure business reveals new name

AUREOS means "new dawn" after private equity acquisition
7 days ago

Stiffer fines for over-running street works from next Summer

Cash raised from lane rentals to be channeled into pothole repairs
7 days ago

£113m Basildon rental homes scheme seals build finance

Work expected to start early next year on Market Square project
7 days ago

Notting Hill Genesis seeks more tier 1 repairs contractors

London housing trust seeks eight firms for new £1.5bn repairs framework
7 days ago

Reclaimed steel oil rig columns worked into London office revamp

Curo will use reclaimed bricks and steel for Fitzrovia office overhaul
1 week ago

CITB delays levy approval consultation

Levy agreement talks pushed back by ongoing review into effectiveness of training body
1 week ago

Ofwat approves £104bn water industry spending plan

Household water bills to rise by 36% to fund quadrupling of investment
1 week ago

Costain/ Siemens JV clinches HS2 power supply job

£300m deal for HV power supply systems over the 225km route
1 week ago

Demolition team assembles on Multiplex London Wall site

Erith to start work next month at Deutsche Bank's former headquarters
1 week ago

Norwich Council acts to revive £300m Anglia Square scheme

Council uses Homes England funding to buy stalled site with planning for 1,100 homes
1 week ago

Go-ahead for 4,500-home Cambridgeshire new town

Waterbeach new town plan stalled three years ago after an Environment Agency objection
1 week ago

Henry Boot to take total control of Stonebridge Homes

Deal worth at least £30m
1 week ago

HS2 costs could hit £66bn

Government looking for next estimate to be lower
1 week ago

Mace to close construction logistics arm

Specialist business being wound down
1 week ago

National Grid to invest £35bn over next five years

Plan set out for record investment in electricity transmission infrastructure
1 week ago

Profits double at Barhale

Civils specialist sees order book top £1bn
1 week ago

Balfour wins 68km HV underground power cable deal

Main works to start next year on Eastern Green Link 2 job
1 week ago

Stunning site wrap unveiled on Sloane Street

Hoarding creates illusion of fully formed façade on £53m Galliford Try job
1 week ago

Heathrow Airport upgrade spend takes off again

Airport operator will spend £2.3bn over the next two years
1 week ago

Government buys back over 36,000 military homes

Public ownership deal to release wave of upgrade and new build work
1 week ago

Story Contracting staff braced for rail job losses

Work coming through slower than expected from Network Rail
1 week ago

Ballymore submits two plans for 3,700 East London homes

Construction could start in 2025 on Thames Road and Knights Road schemes
1 week ago

Blackpool council steps in on failed developer’s £300m scheme

Blackpool Central site clearance to start in the New Year as hunt starts for new developer
1 week ago

Contractor services