HS2 Euston Station can be built to budget and open early

Aaron Morby 1 year ago
Share

Mace chief Mark Reynolds has called for a speedy restart of construction for the London HS2 terminus in Euston.

Reynolds says there is a deliverable and cost-effective solution for HS2 Euston Station
Reynolds says there is a deliverable and cost-effective solution for HS2 Euston Station

New pared-down plans for HS2’s terminus at Euston will be built with just six platforms, almost half of its original scope, according to Government documents released yesterday.

The new design will also axe a planned tunnel connecting the HS2 terminus to Euston Square tube station.

Reynolds said the newly-revised plans could deliver the Euston Station terminus within the existing budget and earlier than expected.

He warned that if the vast station project is delayed further an opportunity would be missed to activate the potential of a new development zone around the large site announced yesterday by Prime Minister Rishi Sunak.

The government aims to establish a Development Corporation to create a transformed ‘Euston Quarter’, modelling the successful regeneration of Battersea Power Station, Nine Elms and Kings Cross.

It will potentially offer up to 10,000 homes – five times the number of its close neighbour King’s Cross – and a huge expansion of commercial and laboratory space.

The government announced last March that work on the station would be paused for two years in a bid to cut costs. According to the public accounts committee these have nearly doubled to £4.8bn from an original estimate of £2.6bn.

Yesterday Sunak also revealed that client HS2 would no longer be responsible for managing the Euston site. The Government will appoint a development company, separate from HS2 Ltd, to manage the delivery of the Euston regeneration project

He said: “There must be some accountability for the mistakes made, for the mismanagement of this project.

“We have spent four years on two unaffordable designs, with a gold-plated and over-specified station. That will change.

“We are going to strip back the project and deliver a station that works, and that can be open and running trains as soon as possible, and which has the leadership in place to deliver maximum value to the taxpayer.”

“We will instead create a new Euston development zone building thousands of new homes for the next generation of homeowners, new business opportunities and a station that delivers the capacity we need and in doing so, for the first time in the life cycle of this project – we will have cut costs.”

A joint venture between Mace and Spanish contractor Dragados is delivering the vast London station scheme.

Reynolds, Chairman and CEO of Mace, responded to the announcement warning that work should not be delayed any further at Euston.

“HS2 will not deliver the growth and capacity we need without it terminating in central London – and so it is positive news for the country and the industry that the Prime Minister has committed once again to build the new station at Euston, working with the private sector to find a solution that works for everyone.

“His proposed Euston business and development zone may work, but the detail will be critical.

He added: “We know there is a deliverable and cost-effective solution to Euston Station that can be built within the existing budget, allowing the station to open much earlier; enabling housing and placemaking to be offered sooner; and most importantly that delivers the best value to the taxpayer.

“We look forward to working with the Government to bring those proposals forward.

“It is important that we push on ahead with delivering the station at speed, providing clarity to industry on the pipeline of work and avoiding further disruption to the local community.”

 

Latest news

Deck falls off huge scissor lift at Winvic site

Two men seriously injured as platform plunges to the ground
22 hours ago

Bouygues seals deal for £119m Cardiff college campus

Construction to start in June on two new buildings
1 day ago

Bid race starts for £15bn schools framework refresh

DfE throws framework open to more contractors
1 day ago

Berkeley’s £600m Borough Triangle project approved

Controversial scheme features two towers of 38 and 44-storeys
2 days ago

London Mayor calls in blocked 600-bed student scheme

Refused 20-storey London PBSA block may still be built
1 day ago

HG to build 500-bed London Stratford student scheme

Work will start later this year subject to gateway 2 safety approval
2 days ago

Arrest after pedestrian death on construction site

Tragedy during site preparation works for new Wigan car park
1 day ago

British Steel threatens closure of Scunthorpe blast furnaces

Chinese owners say sectional steel and rail supplies will be maintained
2 days ago

Planning green light for Sheffield warehouse site

Existing factories to be demolished in new scheme for Rula Developments
1 day ago

New rail property company to unlock land for 40,000 homes

First four sites released in Newcastle, Cambridge, Manchester, and Nottingham
2 days ago

Drainage specialist Subscan files administration notice

Specialist employing 131 people files court notice
2 days ago

Four win Network Rail £300m engineering design deal

Eastern region deal will include design for Northern Powerhouse Rail
2 days ago

Funding go-ahead for Banwell bypass after fresh cost hike

Galliford Try contract rises £14m to £64m after final design change
3 days ago

Graham wins Southport £75m Marine Lakes Centre

Firm replaces Kier which parted ways with backer Sefton Council
3 days ago

Chancellor unveils extra £2bn capital spend a year

Construction promised a defence dividend in military base and homes upgrade work
3 days ago

McLaren confirms subcontractor team on £135m warehouse job

Work starts on TN2 Gateway site in Kent.
3 days ago

Vistry profits slump after site costs reporting debacle

House builder launches internal whistle-blowing service in business culture review
3 days ago

Severfield chief to step down

Alan Dunsmore to leave structural steel group by end of June
3 days ago

Funding hurdle remains as Lower Thames Crossing gains consent

Government claims £9bn project may start in 2026 as private finance options explored
4 days ago

Mace wins £600m Euston Tower overhaul

1970s tower's foundations and core to be retained as floor plates extended
4 days ago

Summer start for main works on London green tower

Axa sanctions start at 50 Fenchurch Street 36-storey office block
3 days ago

Japan’s leading flats builder JVs with L&G for UK push

Partners plan to build over 1,000 rental homes in London
3 days ago

Wates submits plan for 1,000 homes Harrow council scheme

Former civic centre Poets' Corner site kicks off housing partnership
4 days ago

Morgan Sindall upgrades forecast for next 12 months

Overbury fit-out arm gets off to a flying start in 2025
4 days ago

Restructure underway at Henry Boot Construction

New management team restructures business after drop in turnover
4 days ago

Government pledges £2bn stop-gap funding for 18,000 homes

Funding avoids cliff-edge in social housing delivery before new grant programme agreed
4 days ago

Just two major new roads schemes to start this year

National Highways sets out one-year interim spending plan after RIS3 delay
4 days ago

Plans go in for £400m GRAHAM Manchester site

Demolition and enabling works underway with main construction set to start next year
4 days ago

Building safety levy rate set at up to £10,000 a home in London

Levy introduction pushed back a year to Autumn 2026 - list of new rates
5 days ago

BAM wins £100m revamp of Broadgate Tower in London

Front of tower 3-storey extension to use cross laminate time and re-used steel
5 days ago

Contractor services